TAZARA Railway

Tanzania–Zambia Railway
Overview
Type Heavy rail
Status Minimally operational
Near-collapse
Termini Dar es Salaam
Kapiri Mposhi
Website tazarasite.com
Operation
Opened 1975
Operator(s) Tanzania–Zambia Railway Authority
Technical
Line length 1,860 km (1,160 mi)
Track gauge 1,067 mm (3 ft 6 in)
Tanzania railway network
(interactive version)
1000mm gauge, 1067mm gauge (TAZARA)

The TAZARA Railway, also called the Uhuru Railway or the Tanzam Railway, is a railroad in East Africa linking the port of Dar es Salaam in Tanzania with the town of Kapiri Mposhi in Zambia's Central Province. The single-track railway is 1,860 km (1,160 mi) long and is operated by the Tanzania-Zambia Railway Authority (TAZARA).

The governments of Tanzania, Zambia and China built the railway to eliminate landlocked Zambia's economic dependence on Rhodesia (now Zimbabwe) and South Africa, both of which were ruled by white-minority governments.[1] The railway provided the only route for bulk trade from Zambia's Copperbelt to reach the sea without having to transit white-ruled territories. The spirit of Pan-African socialism among the leaders of Tanzania and Zambia and the symbolism of China's support for newly independent African countries gave rise to TAZARA's designation as the "Great Uhuru Railway", Uhuru being the Swahili word for Freedom.

The project was built from 1970 to 1975 as a turnkey project financed and supported by China. At the time of its completion, two years ahead of schedule, the TAZARA was the single longest railway in sub-Saharan Africa.[2] TAZARA was the largest single foreign-aid project undertaken by China at the time, at a construction cost of US $500 million (the equivalent of US $3.08 billion today)[3]

TAZARA has faced operational difficulties from the start and required further technical assistance from China, European countries and the United States in subsequent decades. Freight traffic reached 1.2 million tons in 1986, but began to decline in the 1990s as the end of Apartheid in South Africa and independence of Namibia opened alternative transport routes for Zambian copper. To keep the railway running, China waived 50% of its loan-free construction debt in 2011.[4] Freight traffic fell to 88,000 metric tons in Fiscal Year (FY) 2014/2015, less than 2% of the railway's design capacity of 5 million tonnes per year.[5][6] but rebounded to 130,000 tons in FY2015/16 and was expected to reach 380,000 tons in FY2016/17.[7]

Tanzania-Zambia
Railway (TAZARA)
km
0.0 Dar es Salaam
1.9 to Port of Dar es Salaam
3.0 Yombo
18.1 Mwakanga
28.7 Vigama
33.7 Kazimzumbwi
42.0 Kifuru
64.7 Chakenge
70.6 Mzenga
89.8 Nyani
103.0 Gwata
130.8 Kidunda
161.8 Kinyanguru
191.2 Fuga
199.3 Metambwe
217.0 Kisaki
247.1 Lumango
274.8 Pwaga

305.5
0
Msolwa

24.1 Kidatu
109.5 Kilosa

Tanzania Railways
Central Line
315.3 Katulukilla
321.2 Mang’ula
331.1 Kiberege
342.5 Siginali
360.0 Ifakara
378.7 Idete
394.1 Ruipa
412.5 Mbingu
430.3 Mngeta
447.0 Ikule
462.1 Chita
480.3 Chisano
496.1 Mlimba
509.1 Lumumwe
521.7 Kimbwe
534.8 Mpanga
555.9 Kitete
569.3 Uchindile
584.3 Mgololo
596.7 Kiyowela
621.3 Kitandililo
633.8 Mahongole
651.5 Makambako
671.5 Wanging’mbe
690.6 Kangaga
704.9 Rujewa
720.7 Msesule
749.4 Chimala
769.4 Igurusi
784.4 Ilongo
800.3 Malamba
810.6 Lumba
822.9 Inyala
832.9 Uyole
848.8 Mbeya
860.1 Mbalizi
872.1 Idiga
890.1 Chikola
915.4 Mlowo
926.2 Vwawa
952.4 Mpemba
969.6 Tunduma
Tanzania
Zambia
border
971.0 Nkonde
982.1 Mwenzo
990.1 Msanza
1008.6 Kawila
1023.7 Luchinde
1038.0 Chozi
1056.0 Luchewe
1088.0 Kalulu
1103.0 Makasa
1135.9 Kayaya
1151.0 Chimba
1169.0 Malenge
1183.3 Nseluka
Proposed line to
Port Mpulungu
1212.8 Kungu
1222.3 Kasama
1264.9 Nkolemfumu
1282.4 Ishitu
1315.4 Chambeshi
1329.5 Mpepo
1358.9 Kasongo
1386.6 Kabuka
1412.0 Sabwa
1424.0 Mpika
1448.1 Chilonga
1469.0 Kapoko
1493.2 Kalonje
1505.8 Salamo
1525.9 Mununga
1535.4 Finkuli
1559.5 Lukulu
1597.7 Luslwasi
1593.5 Kanona
1617.0 Chakalamo
1643.8 Kawaluma
1664.2 Serenje
Zambia Railways
to Lusaka
1690.8 Chisangwa
1720.1 Ndabala
1734.9 Mkushi River
1747.6 Nkolonga
1773.0 Mkushi
1792.9 Ngambwa
1817.6 Lunsemfwa
1844.1 Luanshimba
1863.1 New Kapiri Mposhi
1864.6
649.6
Kapiri North Junction
to Congo DR

Route

Running some 1,860 km (1,160 mi) from Tanzania's largest city, Dar es Salaam, on the coast of the Indian Ocean to Kapiri Mposhi, near the Copperbelt of central Zambia, the TAZARA is sometimes regarded as the greatest engineering effort of its kind since the Second World War. The railway crosses Tanzania in a southwest direction, leaving the coastal strip and then entering largely uninhabited areas of the vast Selous Game Reserve. The line crosses the TAN-ZAM highway at Makambako and runs parallel to the highway toward Mbeya and the Zambian border, before entering Zambia, and linking with Zambia Railways at Kapiri Mposhi.

Map showing the course of the TAZARA in relation to Tanzania's geography, national parks and game reserves.
Tazara Railway Station in Dar es Salaam
Tazara locomotive passing through the Selous Game Reserve

From sea level, the railway climbs to 550 metres (1,800 feet) at Mlimba, and then reaches its highest point of 1,789.43 metres (5,870.8 feet) at Uyole in Mbeya before descending to 1,660 metres (5,450 feet) at Mwenzo, the highest point in Zambia, and settling to 1,274.63 metres (4,181.9 feet) at Kapiri Mposhi.[8]

Dar es Salaam metropolitan area

In greater Dar es Salaam, the TAZARA is also used for passenger commuter rail. The Dar es Salaam commuter rail was launched in 2012 to relieve traffic congestion. The TAZARA offers two routes on its 20.5 km rail network.[9] The first from its station in Dar es Salaam to Mwakanga which lies on the outskirts of the city. It stops at Kwa Fundi Umeme, Kwa Limboa, Lumo Kigilagila, Sigara, Kitunda road, Kipunguni B, Majohe and Magnus. The second service runs from its Dar es Salaam station to Kurasini via Kwa Fundi Umeme, Yombo, Chimwaga, Maputo, Mtoni Relini and Kwa Aziz Ali Relini.[10]

Tanzanian interior

Upon leaving the coast, TAZARA runs west, through the Pwani Region, then dips south of Mikumi National Park and enters the wilderness in the northern part of the Selous Game Reserve in the Morogoro Region. The Selous is one of the largest faunal reserves in the world and passengers can often see wildlife such as giraffe, elephant, zebra, antelope and warthog, which have become accustomed to the rumbling of the trains.[11] The railway crosses the Great Ruaha River for the first time in the Selous.

Further south, the railway cuts through the fertile Kilombero Valley, and skirts the great Kibasira Swamp. The next section, between Mlimba (the Kingdom of Elephants) and Makambako (the Place of Bulls) was to be 158 km (98 mi) long, and presented the builders of the railway with the greatest challenge. To lay track across rugged mountains, precipitous valleys and deep swamps, it was necessary to construct 46 bridges,18 tunnels, and 36 culverts.[12] Because of the heavy rainfall in this area, intricate drainage works had to be integrated with every feature. But perhaps, the most spectacular feature is the bridge across Mpanga River valley, which stands above the river on three 50 m (164 ft) tall pillars.

At Kidatu, a metre gauge branch railway connects to the Central Line at Kilosa. The TAZARA then climbs into Southern Highlands of the Iringa Region and levels out onto a rolling plateau. Here, in the coffee and tea country of the Njombe Region, the weather becomes noticeably cooler, the air sharper. On the approach to Makambako, the Udzungwa Mountains National Park rise 2,137 m (7,011 ft) to the north, while the Kipengere Range roll ahead to the south. Makambako is one of the meeting points of the railway and the Tanzania-Zambia Highway.

From Makambako the railway and the highway run a parallel course towards Mbeya running past the Kipengere Range that towers to the south. Here in the Mbeya Region, the TAZARA crosses several upstream tributaries of the Great Ruaha, which are lined with belts of forest and grasslands.

After the Kipengere Mountains, the Uporoto Range takes over with the Usangu Flats stretching to the north. From Mbeya town, both the railway and the highway heads northwest to Tunduma where they cross the border into Zambia.

Zambia

The TAZARA enters northeastern Zambia at Mwenzo, in the Northern Province and heads southwest to Kasama. It then turns due south and crosses the Chambeshi River en route to Mpika. After entering the Central Province, the railway again turns to the southwest, running along the northern foothills of the Muchinga Mountains, past Serenje and Mkushi to Kapiri Mposhi, located due north of the Lusaka.

Passenger service

Zambian TAZARA staff in Kapiri Mposhi in 2012.

As of February 2016, two passenger trains per week traverse the entire TAZARA in each direction. Departures are on Tuesdays and Fridays in each direction. The brand new Express train travels Fridays from Dar and Tuesdays from New Kapiri Mposhi. The Ordinary train makes all possible stops, and the Express service makes fewer stops[11][13] The entire journey, as scheduled, takes 36 hours, though delays can extend the trip to as long as 50 hours or more.[11][14] Trains on the TAZARA are slower than overland bus service but cheaper and safer.[4][11] The TAZARA trains have attracted foreign tourists wishing to see the landscape and wildlife along route.[11]

Rovos Rail of South Africa operates the Pride of Africa, a luxury train, that runs periodic tours from Cape Town to Dar es Salaam via the TAZARA.[15] Commuter train service on the TAZARA between Dar es Salaam and its suburbs commenced in 2012.

Rail gauge and standards

The TAZARA has a track gauge of 3 ft 6 in (1,067 mm), also known as the Cape Gauge, which is widely used throughout southern Africa.[16] TAZARA connects to the Cape-gauge Zambia Railways at Kapiri Mposhi. The remainder of Tanzania’s railways have 1,000 mm (3 ft 3 38 in) metre gauge tracks.[17] A transshipment station with a break of gauge station was built in Kidatu in 1998.[17]

Except for the rail gauge, TAZARA generally reflects Chinese railway standards of the 1970s. The technical characteristics of the line were:

Equipment

Locomotives

Locomotive on the TAZARA at the Kapiri Mposhi Station in 2012.
Type Quantity Manufacturer Notes Sources
SDD20 10 CSR Qishuyan [22][23]
U30C 10 Krupp Variant of GE U26C, not to be confused with the identically-named GE U30C. [23]
CK6 CSR Chengdu Shunting locomotive [24]

History

Origins of the project

In the late 19th century, a railway from British Rhodesia to Tanganyika (then German East Africa) to carry copper ore was envisaged by Cecil Rhodes.[2] After World War I, Tanganyika was handed over to the United Kingdom for administration as a League of Nations Mandate, and British colonial authorities again explored the idea.[2]

TAZARA train station in Ifakara

Following World War II, interest in railway construction revived.[2] A map from April 1949 in the Railway Gazette showed a proposed line from Dar es Salaam to Kapiri Mposhi, not far from the route that would eventually be taken by the Chinese railway.[25] A report in 1952 by Sir Alexander Gibb & Partners concluded that the Northern Rhodesia-Tanganyika railway would not be economically justified, due to the low level of agricultural development and the fact that existing railways through Mozambique and Angola were adequate for carrying copper exports.[26] A World Bank report in 1964 projected that only 87,000 tons of cargo would be carried between Zambia and Tanzania by the year 2000, not enough to support a railway, and recommended that a road be built instead.[27]:43

In 1961, Tanganyika became independent under the leadership of Julius Nyerere, and in 1964 the country joined with Zanzibar to form the United Republic of Tanzania. Also in 1964, Northern Rhodesia was granted independence as Zambia, under the leadership of Kenneth Kaunda. Both Nyerere and Kaunda were charismatic socialist African leaders who supported the self-determination of their African neighbors.[2] A railway connecting their two countries would help to develop the agricultural regions of southwestern Tanzania and northeastern Zambia.[28]

Attempts to secure funding

Nyerere and Kaunda pursued different avenues for the construction of a rail route. When Nyerere visited Beijing in February 1965, he was hesitant to raise the issue of the railway out of concern that China was also a poor country. President Liu Shaoqi offered to assist Tanzania and Zambia in building a railway between the two countries.[14][29] Chairman Mao Zedong told Nyerere, “You have difficulties as do we, but our difficulties are different. To help you build the railway, we are willing to forsake building railways for ourselves.”[14] Chinese leaders assured Nyerere that the full ownership of the railway would be handed to Tanzania and Zambia upon completion along with the technology and equipment for operations.[29] Nyerere did not immediately accept the Chinese offer but sought to use it to induce Western backing for the railway, but none was forthcoming.[30] He did, however, accept a team of Chinese surveyors, who produced a short report in October 1966.

The Mpanga River Bridge and tunnel.

Kaunda was wary of Communist involvement and wanted to maintain friendly ties with Britain. He turned down an offer from the Chinese Embassy in Lusaka to build the railway. In addition, Zambia and Rhodesia were joint owners of the Zambian Railway and the joint ownership agreement would penalize Zambia for diverting traffic to other railways. The resulting Canadian-British aerial survey produced a favourable report in July 1966, but Western funding was not forthcoming.[31] Britain, Japan, West Germany, World Bank, the United States and United Nations all declined to fund the project.[2][32] The Soviet Union was similarly uninterested.[32]

Chinese support

At the time, China was actively seeking diplomatic support in the Third World against the United States and Soviet Union. Some believe that Mao supported the construction of the railway to secure votes against the Soviet Union at the Asia-Africa summit of Algiers of 1965.[33] Though the Algiers conference was cancelled, Chinese support for the TAZARA continued.

The TAZARA station at Makambako.

Trade Minister Abdulrahman Mohamed Babu and other ministers from Zanzibar were instrumental in lobbying Chinese leaders for support and then persuading Nyerere to accept the assistance.[34] At the 1965 Commonwealth prime minister's conference, British prime minister Harold Wilson was so struck by Tanzania's pro-China attitude that he felt many of Nyerere's ministers were "directly in the Chinese pay." [35] Canadian prime minister Lester Pearson also questioned whether Nyerere should get so close to the Chinese.[36] Nyerere later complained that Western nations opposed the Chinese plans for the railway, but did not offer him any alternative.[37]

"... all the money in this world is either Red or Blue. I do not have my own Green money, so where can I get some from? I am not taking a cold war position. All I want is money to build it."
Julius Nyerere, PRO, DO183/730, From Dar es Salaam to CRO, No. 1089, 3 July 1965.

In November 1965, Southern Rhodesia's white-led colonial government issued its Unilateral Declaration of Independence from Britain, and threatened to sever Zambia's trade routes to the sea. Kaunda dropped his objections to Chinese involvement and accepted the Chinese offer while visiting China in January 1967.[38][39] Nyerere and Kaunda continued to supported black liberation movements in Rhodesia, South Africa, and Mozambique, and the Tanzania-Zambia Railway became a critical tool for preserving Zambia's political and economic independence.[28] On September 6, 1967, an agreement was signed in Beijing by the three nations. China committed itself to building a railway between Tanzania and Zambia, supplying an interest-free loan of RMB988 million (approx. US$500 million) to be repaid over 30 years.[14][40]

The West reacted to Chinese backing for the project with both alarm and derision. Critics questioned construction quality and competence of the Chinese, calling the TAZARA, the "bamboo railway".[32] The Wall Street Journal stated in 1967, "the prospects of hundreds and perhaps thousands of Red Guards descending upon an already troubled Africa is a chilling one for the West."[41] The United States funded the Tan-Zam Highway, which was built from 1968 to 1973, to compete with the railway.[42]

Construction

Construction was begun in 1970 and operation commenced in October 1975, two years ahead of schedule. Before the railway construction began, 12 Chinese surveyors travelled for nine months on foot from Dar es Salaam to Mbeya in the Southern Highlands to choose and align the railway's path.

Mbeya station on the Tazara Railway

In all, from surveying, to construction, to training and management, China sent about 50,000 personnel from 1965 to 1976, including 30,000 to 40,000 workers.[43] An estimated 60,000 Africans participated in the railway's construction.[43] At the height of construction in 1972, there were 13,500 Chinese and 38,000 African workers on the project.[44]

Chinese assistance was provided in large part by the Railway Engineering Corps, then part of the People’s Liberation Army (predecessor of China Railway Construction Corporation) and the foreign aid department of the Ministry of Railways (predecessor of China Civil Engineering Construction Corporation).[45] Chinese personnel sent to Africa were selected for political dependability, moral probity, technical expertise and personal fitness, and underwent as long as two months of training.[46] Chinese assistance followed the country's socialist ethos of the time, following a labor-intensive instead of a capital-intensive model widely used in the West.[47] Chinese engineers lived and worked according to the same standards as their African counterparts.[2][47]

Construction camps were set up for each 40-mile (64 km) section of track, being relocated as the work progressed. Papaya and banana trees were grown to provide shade and food, and workers tended vegetable gardens in the camps in off-hours.[48]

The work involved moving 330,000 tons of steel rail and 89 million cubic meters of earth and rock, and the construction of 93 stations, 320 bridges, 22 tunnels and 2,225 culverts.[46][49] Virtually all building materials, equipment and significant amounts of food and medical supplies were shipped from China, including ambulance vans sent to transport the sick and injured.[46] Braving rain, sun and wind, the workers laid the track through some of Africa's wildest and most rugged landscapes. One Chinese worker recalled that his team was trapped in the wilderness for a week after floods and landslides washed away the only connecting road.[46] "We lived in fear of lions and hyenas." [46]

The bridge across the Mpanga River is 160 feet (49 m) in height, and the Irangi Number Tunnel is 1.5 mi (2.4 km) long.[50] The section from Mlimba to Makambako crosses mountains and steep valleys and contains almost 30 percent of the bridges, tunnels, viaducts, and earthworks of the entire route are located a 10-mile (16 km) stretch of this section.

Over 160 workers, including 64 Chinese nationals, died in construction accidents.[49]

The project pressed forward despite the enormous political upheaval and economic dislocation in China caused by the Cultural Revolution, during which most domestic railway building projects were halted or delayed as vast numbers of government officials were purged. President Liu Shaoqi, who had made the offer to President Nyerere in 1965, was removed from power in 1966, publicly vilified and died in 1969. In Tanzania, Abdulrahman Mohamed Babu, who had persuaded the Chinese to back the TAZARA, was sentenced to death in 1972 for allegedly plotting to overthrow the Zanzibar government. He was pardoned by Nyerere in 1978.

Initial difficulties

The TAZARA has been a major economic conduit in the region, but it faced operating difficulties from the start and never reached its intended capacity of 5 million metric tons as originally envisioned.

Bridge crossing on the Tazara Railway in Zambia in 2009.
The new Kapiri Mposhi Station in 2009

In each the first two fiscal years of operation, FY1976/77 and 1977/78, the TAZARA carried over 1.1 million metric tons of cargo. The diesel hydraulic locomotives sent by the Chinese were insufficiently powerful to haul heavy loads up the steep escarpment between Mlimba and Makambako, limiting the line's carrying capacity.[32]

In their haste to complete the railway ahead of schedule, the Chinese did not train sufficient African technicians to take over management of the railway.[32] When the Chinese rolling stock broke down, there was limited local capacity to for repair.[32] By 1978, 19 to 27 of the locomotives were out of operation for repair and so were half of the rail cars.[51]

The railway was beset with staff difficulties. In 1972, two hundred Tanzanian and Zambian students were enrolled in the Northern Jiaotong University in Beijing to learn railway management, but a dozen of them were expelled in the first year for misbehavior.[27]:99 Employee theft was serious enough that 20 Zambian crew members were fired in 1978 for stealing and drivers were brought back from China for a return run, and hundreds of other Chinese advisers had their stay extended.[51] These problems resulted in much lengthier than planned turnaround times for freight and in 1978 Zambia had to break ranks and reopen links with South Rhodesia for its copper exports.[52]

Freight cargo fell to 923,000 tons in 1978/79 and below 800,000 tons per annum until 1982/83. The proximate cause for the steep decline was the destruction three bridges including Chambeshi River Bridge in 1979 during the Rhodesian Bush War.[21] TAZARA played an important role in the black nationalist struggles of the late 1970s and 1980s against white-dominated governments in southern Africa and their proxies. The railway served as an trade route for Zambia, Zimbabwe, and Malawi that did not pass through Apartheid South Africa or Angola and Mozambique, which were embroiled in civil war with proxies backed by South Africa.[21] During Zimbabwe's struggle for independence, the white-led Rhodesian government targeted Zimbabwe People's Revolutionary Army's supply lines from Tanzania and forced Zambia to send its exports through Rhodesia and South Africa.[53] The Chambeshi River Bridge was blown up by the Selous Scouts, the special forces of the Rhodesian Army, and took a year to reconstruct.[54][21]

In addition, landslides and washouts frequently disrupted service, especially during the rainy season of 1979 and 1985/86.[32][54] Freight volumes rebounded to 824,000 tons in 1982/83 and 973,000 the following due in part to the arrival of higher capacity disesel electric locomotives.[54] Passenger volumes, which tend to be based on shorter trips and less prone to segment disruptions, grew steadily from 826,000 in FY1976/77 to 1.397 million in FY1978/79, but fell to just 564,000 due to motive power shortage as locomotives were diverted to carry freight.[54]

Foreign Support in the 1980s

The interior of the New Kapiri Mposhi Station in October 2012.

In 1983, Tanzania and Zambia invited the Chinese back to help manage the railway.[55] About 250 Chinese managers were assigned to railway bureaus along route.[55] They brought operational profitability to the railway and paid for their expenses through revenues.[55] Cargo reached 973,000 tons, but the Chinese had to issue additional zero-interest loans to pay for spare parts and rehabilitation.

In 1985, seven European countries pledged additional aid to the TAZARA and provided $150 million from 1987 to 1993.[32] The donors sought to reduce dependence of landlocked Zambia, Zimbabwe and Zaire on transport routes through Apartheid South Africa and war-torn Angola and Mozambique.[56] Sweden supplied 25 tank wagons and 350 HSO goods wagons, though the TAZARA was deemed to need 1,000 new wagons.[56] Austria and Switzerland provided mechanized track maintenance equipment.[56] Switzerland and Sweden provided railburn repair equipment and training.[56] Finland financed a rescue crane, rerailing equipment and accident prevention training.[56] The European Economic Community (EEC) financed wheel lathes to maintain wagons and locomotives. Norway paid for human resource development.[56]

China joined the donor conference, hosted training of TAZARA personnel, sent senior technicians to overhaul Chinese locomotives and agreed to provide steel rail. The TAZARA generated operational profits in FY1986/87.[56]

In 1987, the United States also joined in the donor efforts to improve the TAZARA and reduce the dependency of "frontline states" on South Africa.[57][54][58] A 1987 report commissioned for the USAID identified inadequate motive power and poor maintenance of existing equipment as constraints to operational capacity.[57] The report found TAZARA mechanics to be poorly trained and supervised, many could not read and write and had to operate a diverse range of equipment from various donor countries.[57] The USAID then funded a four-year, $50 million program, then extended to seven years, that provided 17 new GE diesel electric locomotives and spare parts, repaired existing GE/Krupp locomotives, a remodeled workshop at Mbeya and comprehensive training, maintenance, cost accounting management procedures.[54] Equipment repairs would only "reduce some short-range problems" the report highlighted the need to address "underlying causes", such as the locomotive workshops lacking basic supplies and spare parts, and less than 20% of the employees at the locomotive workshops were actually doing work.[57]

The USAID then funded a four-year, $50 million program, then extended to seven years, that provided 17 new GE diesel electric locomotives and spare parts, repaired existing GE/Krupp locomotives, a remodeled workshop at Mbeya and comprehensive training, maintenance, cost accounting management procedures.[54] As a result, the annual cargo hauling capacity of the TAZARA increased from 1.0 to 1.9 million metric tons from 1986 to 1991, the locomotive availability rate rose from 46% to 65% and wagon turnaound time was reduced to 20 days from 35 days over the same period.[54]

Passenger traffic on the railway rebounded from 564,000 in the FY1982/83 to 1.335 million FY1986/87 to 1.6 million in FY1990/91.[54][21][32] Local goods accounted for nearly half of the cargo shipped on the line between 1985 and 1988.[32]

The USAID projected cargo increasing to 1.5 million metric tons by 1995.[54]

Decline

Abandoned rolling stock
along the TAZARA
Photos taken in Oct. 2012

In the 1990s, the economic performance of the railway began to decline with changes to the broader economic and political environment. With the independence of Namibia in 1990 and the end of apartheid in South Africa in 1994, southern Africa was no longer dominated by white minority governments, and Zambian copper had more economic outlets to the south and east. Road transport provided competition in the form of the Trans–Caprivi Highway and the Walvis Bay Corridor to Namibia.

The privatization of Zambia's copper mines forced railways in Zambia to compete for previously-guaranteed government cargo.[59] Traffic on Zambian Railways fell from 6 million tonnes in 1975 to 690,000 tonnes in 2009. TAZARA suffered an even greater drop in traffic.

In the early 2000s, after the end of civil wars in Angola and Mozambique opened further rail outlets to Zambian copper.[60][61] In 2008, the railway's condition was described as being "on the verge of collapse due to financial crisis," and dangerous track conditions were discovered by Chinese technicians inspecting the line.[62] The company's cash flow difficulties have led to delays in paying salaries, resulting in frequent strikes by the workforce.[63] By 2012, TAZARA had only 10 operational main line locomotives.[64] In September 2013, the TAZARA was reporting monthly losses of about $1 million on $1.53 million in monthly revenue against $2.5 million in average monthly expenditures.[4]

Attempts at revitalization

The railway is sometimes described as an economic "lifeline" for Zambia and the government in Lusaka has ostensibly remained committed to its revitalization.[4] In April 2013, Zambia’s second largest copper miner, Konkola Copper Mines, agreed to re-commence shipping copper on the TAZARA after a five-year hiatus.[65] By November 2013, the line was reported shipping 15,000 tons of copper weekly, but still prone to breakdowns and delays.[65] In addition to carrying copper, manganese, cobalt and other minerals for export, the TAZARA also transports Asian imports and fertilizer to Zambia, Congo DR, Malawi, Burundi, and Rwanda.[4]

The Chinese government has also been unwilling to see the complete shutdown of its signature foreign aid project. In 2011, China cancelled half of the debts it was owed by the TAZARA.[4] Since the loan was interest-free, inflation had already reduced the real value of the debt by more than 80%, as $500 million in 1970 was the equivalent of US $2.90 billion in 2011.

Additional Chinese aid has kept TAZARA in a state of minimal operation. At the beginning of 2010, the Chinese government gave TAZARA a US$39 million interest-free loan to revive its operations.[66][67] However, TAZARA management estimated that it would require US$770 million to become commercially viable.[68] In October 2012, the Chinese government gave $42 million for four new main locomotives, two shunting locomotives, other equipment, spare parts and staff training.[64]

In March 2014, Tanzanian, Zambian and Chinese officials held talks to recapitalize the TAZARA and to split the management into two companies, one in each of Tanzania and Zambia.[69] The Tanzania-Zambia Railway Authority took delivery in 2015 of four diesel-electric locomotives and 18 coaches supplied from China and there will be more to follow. TAZARA’s Dar es Salaam workshop has also begun a programme to refurbish 24 out-of-use coaches.[70]

In FY2014/15, freight traffic fell to 88,000 metric tons in Fiscal Year (FY) but rebounded to 130,000 tons in FY2015/16 and was expected to reach 380,000 tons in FY2016/17.[7]

Statistics

Freight Volume
Yearmetric tons±% p.a.
1977 1,135,000    
1978 1,273,000+12.16%
1979 923,000−27.49%
1980 790,000−14.41%
1981 752,000−4.81%
1982 796,000+5.85%
Yearmetric tons±% p.a.
1983 824,000+3.52%
1984 973,000+18.08%
1985 1,096,000+12.64%
1986 984,000−10.22%
1987 1,221,000+24.09%
1988 1,204,000−1.39%
Yearmetric tons±% p.a.
1989 1,075,000−10.71%
1991 1,011,823−2.98%
2007 538,500−3.87%
2008 527,600−2.02%
2009 383,000−27.41%
2010 523,000+36.55%
Yearmetric tons±% p.a.
2014 203,538−21.02%
2015 88,000−56.76%
2016 130,000+47.73%
Source: FY1977/78 to FY1988/89;[71] FY2006/07 to FY2009/10;[72] FY2014/15;[6] FY2013/14[73] FY2016/17[7]
Passenger Volume
Yearthousands±% p.a.
1977 826    
1978 1,134+37.29%
1979 1,312+15.70%
1980 1,397+6.48%
Yearthousands±% p.a.
1981 1,024−26.70%
1982 987−3.61%
1983 564−42.86%
1984 1,198+112.41%
Yearthousands±% p.a.
1985 1,065−11.10%
1986 1,161+9.01%
1987 1,335+14.99%
1988 1,400+4.87%
Yearthousands±% p.a.
1989 1,677+19.79%
Source: FY1977/78 to FY1988/89[71]

Social impact

A Tanzanian police band performs at the TAZARA terminus in Dar es Salaam.

The TAZARA has had a strong impact on the rural regions along route. In the 1970s, the Tanzanian government resettled villagers into ujamaa villages that were near the railway,[32] and the villages were tasked with providing security for the railway, against foreign sabotage.[74] As the Tanzanian economy liberalized in the 1990s, the villagers began to use the railway to trade local produce.[32]

Vendors selling items to passengers on the Mukuba Express Train.

The railway also enabled settlers to move to the fertile Kilombero valley, between Mbeya and Kidatu, to grow cash crops such as rice and vegetables that they can readily ship to other communities.[32] As the TAZARA traverses diverse ecosystems, it facilitates trade in local produce across previously isolated communities, including maize, beans and vegetables from the highlands of Makambako, rice from Ifakara, oranges from Mlimba, cooking bananas from Mngeta and Idete.[32] The TAZARA ran the kipsi shuttle trains in the "passenger belt" of southern Tanzania to serve the region.[32] Many settlements have grown into large towns and districts.[75]

The TAZARA also spurred other large-scale economic developments in the region, including a hydroelectric power plant at Kidatu and a paper mill at Rufiji.

The TAZARA Railway Authority has also become a large state employer. In 40 years of operation, as many as one million people have been employed by the railway.[75] Chinese involvement has also been credited for increasing the opportunities of women to enter male-dominated jobs such as train driver.[76]

Legacy

The TAZARA remains an enduring symbol of the solidarity of the developing world and Chinese support for African independence and development. When Beijing hosted the 2008 Summer Olympic Games, the starting point of the torch relay in Tanzania was the grand terminal of the TAZARA.[77]

The difficulties with TAZARA made the Chinese government wary about funding other rail projects in Africa. China would not build another new main line railway in Africa for the next 41 years. While TAZARA was 100% funded by an interest-free loan, the new Chinese railway loans charged interest and required the recipient government to supply matching funds.[78]

See also

Maps

References

  1. Thomas W. Robinson and David L. Shambaugh. Chinese Foreign Policy: theory and practice, 1994. Page 287.
  2. 1 2 3 4 5 6 7 Brautigam 2010: 40
  3. "Historical Milestones". Tanzania Zambia Railway Authority.
  4. 1 2 3 4 5 6 Amy Fallon, "Throwing the Tanzania-Zambia Railway a Lifeline" IPS 2013-12-11
  5. 1 2 "Services". Tanzania-Zambia Railway Authority. Retrieved 27 March 2015. With a designed capacity of five (5) million tonnes of freight per annum ...
  6. 1 2 "Tazara's new CEO pledges to revive Chinese-built railway line". Xinhuanet. Xinhua. Archived from the original on 3 July 2016.
  7. 1 2 3 "Tanzania: TAZARA Sets to Double Cargo Movement By June 2017" Tanzania Daily News (Dar es Salaam) 11 July 2016
  8. Route Map & Profile Tazarasite.com
  9. Kolumbia, Louis (29 October 2012). "Dar train services begin". The Citizen (Tanzania). Retrieved 4 December 2013.
  10. KAZOKA, LUDOVICK (27 October 2012). "Dar Commuter Train Starts On Monday". Retrieved 4 December 2013.
  11. 1 2 3 4 5 Philip Briggs, Tanzania: With Zanzibar, Pemba and Mafia Bradt Travel Guides, 2009 ISBN 1841622885 P. 475
  12. Meandering through inhospitable terrainsTazarasite.com
  13. "Adjustment to the passenger train running schedules - TAZARA". 4 February 2016. Retrieved 11 January 2017.
  14. 1 2 3 4 (Chinese) 记者重走我国援建的坦赞铁路:年久失修常晚点 新华社-瞭望东方周刊 2010-08-04
  15. "Luxury Train Club - Pride of Africa Rovos Rail". 25 June 2012. Retrieved 11 January 2017.
  16. "Services". Tanzania-Zambia Railway Authority. Retrieved 27 March 2015. The TAZARA railway line is designed with a 1067mm-gauge, which allows through traffic operations with other Southern African railways, such as Spoornet of South Africa, Botswana Railways, National Railways of Zimbabwe, Zambia Railways Limited Namibia Railways, Mozambique Railways and Societe Nationale Des Chemins De Fer Du Congo Sarl (SNCC) of the DRC.
  17. 1 2 "Types of Gauges & Links" Tazarasite.com
  18. RailwaysAfrica 2008/1 p8
  19. 1 2 3 "East African Railways Master Plan". Retrieved 13 April 2012.
  20. "TAZARA Expansion Project Brief" (PDF). Tripartite and IGAD Investment Conference, 28–29 September 2011, Nairobi.
  21. 1 2 3 4 5 Harden, Blaine (7 July 1987). "The Little Railroad that Could". The Washington Post.
  22. Batwell, John (6 March 2014). "Tazara orders more Chinese locomotives". International Railway Journal. TANZANIA-Zambia Railway Authority (Tazara) has awarded CSR Qishuyan Locomotive Company, China, a contract worth US$12.5m to supply four additional type SDD20 diesel locomotives for use on its 1860km line between Dar Es Salaam, Tanzania, and New Kapiri Mposhi in Zambia.
  23. 1 2 "TAZARA, Chinese firm sign pact for four locomotives". Lusaka Voice. 1 March 2014. TAZARA now has a fleet of about 16 mainline locomotives at its disposal, six of the SDD20 were acquired recently while the remaining 10 were the old Diesel Electric U30C Locomotives aged over 25 years whose reliability has reduced drastically due to overuse and lack of maintenance.
  24. "Types of Freight and Vehicles". Tanzania-Zambia Railway Authority. Retrieved 27 March 2015. The CK6 diesel locomotive is a diesel-hydraulic locomotive manufactured for TAZARA by CSR Chengdu Co, Ltd of China. ... It is suitable for the shunting and transfer services only.
  25. Hall & Peyman 1976: 31
  26. Hall & Peyman 1976: 32
  27. 1 2 Bailey, Martin (1976). Freedom Railway: China and the Tanzania-Zambia Link. London: Rex Collings. ISBN 0860360245.
  28. 1 2 "How it all began" Tazarasite.com
  29. 1 2 Altorfer-Ong 2009: PDF 9
  30. Altorfer-Ong 2009: PDF 9-10
  31. Hall & Peyman 1976: 88
  32. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Jamie Monson, "Freedom Railway: The unexpected successes of a Cold War development project" Boston Review 2004-12-01
  33. Jung Chang, Jon Halliday, "Mao, The Unknown Story", p. 604
  34. Altorfer-Ong 2009: PDF 6
  35. Altorfer-Ong 2009: PDF 16
  36. Altorfer-Ong 2009: PDF 16-17
  37. Altorfer-Ong 2009: PDF 22-23
  38. Altorfer-Ong 2009: PDF 24
  39. Hall and Peyman, p.98
  40. Hall & Peyman 1976: 100
  41. Monson 2009: 6
  42. Altorfer-Ong 2009: PDF 26
  43. 1 2 Monson 2009: 33
  44. Monson 2009: 58
  45. Brautigam 2010: 163
  46. 1 2 3 4 5 (Chinese) 【中国输出】坦赞铁路今昔 2009-09-22
  47. 1 2 Monson 2009: 36
  48. Hall & Peyman 1976: 127
  49. 1 2 "TAZARA: The Uhuru Railway…" Zambia Daily Mail 2014-03-25
  50. Hall & Peyman 1976: 138
  51. 1 2 Copper, John Franklin (1979). "China's Foreign Aid in 1978". Occasional Papers/Reprints Series in Contemporary Asian Studies. 29 (8).
  52. Preston 2005: 161
  53. Petter-Bowyer, P. J. H. (2003). Winds of Destruction: The Autobiography of a Rhodesian Combat Pilot. Johannesburg: 30° South Publ. p. 369. ISBN 9780958489034.
  54. 1 2 3 4 5 6 7 8 9 10 Regional Transport Development, Dar es Salaam Corridor Project (TAZARA) Project No. 690-0240, "Interim Project Evaluation", November 1989
  55. 1 2 3 Brautigam 2010: 84
  56. 1 2 3 4 5 6 7 Tanzania-Zambia Railway Authority, "TAZARA Ten Year Development Plan" Documentation from Donors Conference, 2-3 February 1988
  57. 1 2 3 4 Forman, J. F. (May 1987). "Identified Improvements to the Equipment Fleet of the TAZARA Railway" (PDF). United States Agency for International Development. Increases in motive power through addition of new diesel electrics and additional re-engining of selected (operational) Chinese DFH2 locomotives will reduce some short-range problems TAZARA will experience with the increase in freight and passenger traffic demands. However, without direct attention to some of the underlying causes of low availability of main-line locomotives, the unacceptable current performance in workshops/depots will continue and availability will remain low.
  58. De Leuw, Cather International Limited, "Final Report of Train Operations Improvement Study" Presented to the USAID, Harare, Zimbabwe 16 December 1992
  59. Adam, Christopher; Collier, Paul; Gondwe, Michael, eds. (2014). Zambia: Building Prosperity from Resource Wealth. Oxford University Press. p. 279. ISBN 9780191636264.
  60. Amos Chanda, "Angola, Zambia to reconstruct Benguela railway" Southern African News Features SANF 05 No. 39 April 2005
  61. "Freight train will link Mozambique, Zimbabwe and Zambia" Macauhub 11 September 2015
  62. "Save the 'Uhuru Railway' from collapse" "This Day", Wednesday, October 29, 2008.
  63. Amani, Victor (27 May 2011). "Strikes cost Tazara 6bn shillings in revenue in a year".
  64. 1 2 "Tazara receives US$42 million railway funding from China" African Review 2012-10-01
  65. 1 2 "Tazara Railway Accident Hits Zambia Copper Exports" Wall Street Journal 2013-11-20
  66. Editor, Chief. "Zambia : China injects $39m into TAZARA operations". Retrieved 11 January 2017.
  67. Southern Times, June 2010
  68. "TAZARA seeks funding from shareholders". Daily News. 2 January 2012.
  69. TAZARA to change management structure DailyNews Online 2014-03-24
  70. UK, DVV Media. "TAZARA takes delivery of locos and coaches". Retrieved 11 January 2017.
  71. 1 2 "Regional Transport Development Dar es Salaam Corridor Project (TAZARA) Project Number 690-0240 Interim Internal Project Evaluation" USAID, November 1989 pg. 8
  72. Christopher Adam,Paul Collier & Michael Gondwe, Zambia : building prosperity from resource wealth Oxford University Press, 2014, pg. 279
  73. Shem Oirere, "Tazara suffers huge fall in freight traffic", International Rail Journal 23 December 2015
  74. Monson 2009: 81-83
  75. 1 2 "Achievements" Tazarasite.com
  76. Ng’uni, Chambo (7 December 2014). "Day with Evelyn Mwansa, Zambia's first female locomotive driver". TAZARA. Archived from the original on 29 March 2015. Retrieved 4 July 2016. When she joined TAZARA, she had no clue that one day she would be the first woman in Zambia to venture into an all-man dominated field. In those days it was unheard of for a woman to take up such a profession which was a preserve for men. “It is the Chinese (we were working with) who suggested that I start driving the train. For me, it never crossed my mind that I could drive a train. The Chinese motivated me and once I took on this challenge I never looked back,” she said.
  77. Monson 2009: 154
  78. Omondi, George (September 2, 2013). "Kenya to repay Chinese loan at floating rate". Business Daily Africa. Transport secretary Michael Kamau said last month’s loan for the standard gauge railway (SGR), energy and wildlife protection was negotiated at a floating interest rate of 360 basis points above the London Interbank Offered Rate (Libor).... Other than the Chinese loan, the remaining part of Sh340 billion railway modernisation project will be financed by the recently introduced railway development levy.

Sources

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.