Tasang Dam

Tasang Dam

Salween River downstream of Tasang Dam site
Location of Tasang Dam in Myanmar
Location Shan State, Myanmar
Coordinates 20°27′23″N 98°39′0″E / 20.45639°N 98.65000°E / 20.45639; 98.65000Coordinates: 20°27′23″N 98°39′0″E / 20.45639°N 98.65000°E / 20.45639; 98.65000
Opening date 2022 est.
Construction cost 6+ billion USD
Operator(s) Myanmar Electric Power Enterprise
Dam and spillways
Impounds Salween River
Height 228 metres (748 ft)
Reservoir
Surface area 870 km2 (340 sq mi)
Power Station
Installed capacity 7110 MW
Annual generation 35,446 GWh per year

The Tasang Dam (Burmese: တာဆန်းဆည်), also known as the Mong Ton Dam, is a planned multi-purpose dam on the Salween River in the Shan State, Myanmar. The Tasang dam’s location will be 480 km (300 mi) northeast of Rangoon and 52.8 km (32.8 mi) west of Mongtong. The Tasang Dam will be the first dam on the Salween River and will be the largest hydroelectric dam in Myanmar and the tallest dam in Southeast Asia if completed. The Tasang will cost more than $6 billion USD and is planned for completion in 2022.[1][2] The groundbreaking ceremony was in March 2007, but construction has been stalled, and there has been little activity at the dam site as of 2008.[1]

Substantial domestic and international controversy surrounds the Tasang Dam project. The Tasang dam is one of five dams the Myanmar Government plans to build on the Salween River.[3]

Background

Since the late 1990s, the Burmese Government proposed to build the Tasang dam but was unable to implement the construction plan until this decade because of civil unrest. Nippon Koei, a Japanese company conducted studies for the dam in 1981 and subsequent studies were done in 2002. Thailand’s MDX Group agreed in 2002 to develop the project. Thailand is the main investor in the dam project and the trade of the TaSang’s electricity is expected to help relations between Thailand and Burma. 85% of the hydro-electricity produced is expected to be transmitted to Thailand.[1]

Design

The Tasang concrete-faced rockfill dam is designed to be 228 meters tall and house a hydro-power station with a 7,110 MW capacity to produce 35,446 GWh annually.[4] Tasang’s 870 km2 (340 sq mi) reservoir will bisect a large portion of Shan State, preluding serious social and environmental problems.[1]

Construction

Construction on the dam is being led by the Thai MDX Group along with the China Gezhouba Group Co., Sinohydro Corporation, China Southern Power Grid Company, China Three Gorges Project Corporation and the British Malcolm Dunstan & Associates. The groundbreaking ceremony for the dam was in March 2007, but since the ceremony, actual construction of the dam has been stalled, and there has been little activity at the dam-site.[1]

Social Impact

Since 1996, as many as 300,000 villagers, mostly Shan people have been displaced to make room for the Tasang Dam’s reservoir. Thousands more relocations are expected as construction progresses. The dam’s reservoir will dissect Shan State in half –almost to the Chinese border – and will negatively impact the local communities and ecosystems. Myamar’s Junta is responsible for the relocations and there have reports of serious human rights violations including executions.[1][5]

References

  1. 1 2 3 4 5 6 "Tasang Dam". Burma Rivers Network. 2008. Retrieved 6 February 2010.
  2. "Myanmar-Thai hydropower project starts on Thanlwin river". Salween Watch. Live Journal. 4-5-2007. Retrieved 8 February 2010. Check date values in: |date= (help)
  3. "Thailand renews plans to build controversial Myanmar dam". Trend Capital. 2008-03-16. Retrieved 2009-12-24.
  4. "Flooding the Future: Hydropower and Cultural Survival in the Salween River Basin". Burma Project. EarthRights International. 2005-04-28. Retrieved 8 February 2010.
  5. Mizzima News:Dam construction endangers lives of locals: report, August 5, 2009, Retrieved on April 28, 2011