Phasor measurement unit

Using a PMU, it is simple to detect abnormal waveform shapes. A waveform shape described mathematically is called a phasor.

A phasor measurement unit (PMU) is a device which measures the electrical waves on an electricity grid using a common time source for synchronization. Time synchronization allows synchronized real-time measurements of multiple remote measurement points on the grid. The resulting measurement is known as a synchrophasor. PMUs are considered to be one of the most important measuring devices in the future of power systems.[1] A PMU can be a dedicated device, or the PMU function can be incorporated into a protective relay or other device.[2]

History

In 1893, Charles Proteus Steinmetz presented a paper on simplified mathematical description of the waveforms of alternating current electricity. Steinmetz called his representation a phasor.[3] With the invention of phasor measurement units (PMU) in 1988 by Dr. Arun G. Phadke and Dr. James S. Thorp at Virginia Tech, Steinmetz’s technique of phasor calculation evolved into the calculation of real time phasor measurements that are synchronized to an absolute time reference provided by the Global Positioning System. We therefore refer to synchronized phasor measurements as synchrophasors. Early prototypes of the PMU were built at Virginia Tech, and Macrodyne[4] built the first PMU (model 1690) in 1992.[5] With the growth of increasingly more distributed energy resources on the power grid, more observability and controls systems will be needed to monitor power flow. Historically, power has been delivered in a uni-directional fashion through passive components to customers. With an increasingly more complex network of generation and loads, it is imperative that the electrical conditions of transmission and distribution networks are continuously being observed through advanced sensor technology––PMUs and uPMUs.

In simple terms, the public electrical grid that a power company operates was originally designed to take power from a single source: the operating company's generators and power plants, and feed it into the grid, where the customers consume the power. Now, some customers are operating power generating devices (solar panels, windmills, etc.) and to save costs (or to generate income) are also feeding power back into the grid. As the electric utility is required by law to buy power produced by customers, the utility wants to make sure this does not damage the grid. The grid must now be measured and controlled in order to ensure the power going into the grid from other sources is of the same quality and standards that customer equipment has been expecting from it, or, if this is not done, as Rob Landley put it, "people's light bulbs start exploding."[6] This measurement function is what these devices do.

Operation

A PMU can measure 50/60 Hz AC waveforms (voltages and currents) typically at a rate of 48 samples per cycle. The analog AC waveforms are digitized by an analog-to-digital converter for each phase. A phase-locked oscillator along with a Global Positioning System (GPS) reference source provides the needed high-speed synchronized sampling with 1 microsecond accuracy. However, PMUs can take in multiple time sources including non-GPS references as long as they are all calibrated and working synchronously. The resultant time-stamped phasors can be transmitted to a local or remote receiver at rates up to 120 samples per second. Historically, only small numbers of PMUs have been used to monitor transmission lines with acceptable errors of around 1%. These were simply coarser devices were installed to prevent catastrophic blackouts. Now, with the invention of micro-synchronous phasor technology, many more of them are desired to be installed on distribution networks where power can be monitored at a very high degree of precision. This high degree of precision creates the ability to drastically improve system visibility and implement smart and preventative control strategies. No longer are PMUs just required at sub-stations, but are required at several places in the network including tap-changing transformers, complex loads, and PV generation buses. [7]

Technical overview

A phasor is a complex number that represents both the magnitude and phase angle of the sine waves found in electricity. Phasor measurements that occur at the same time are called "synchrophasors". While it is commonplace for the terms "PMU" and "synchrophasor" to be used interchangeably they actually represent two separate technical meanings. A synchrophasor is the metered value whereas the PMU is the metering device. In typical applications, phasor measurement units are sampled from widely dispersed locations in the power system network and synchronized from the common time source of a Global Positioning System (GPS) radio clock. Synchrophasor technology provides a tool for system operators and planners to measure the state of the electrical system and manage power quality.

PMUs measure voltages and currents at principal intersecting locations (critical substations) on a power grid and can output accurately time-stamped voltage and current phasors. Because these phasors are truly synchronized, synchronized comparison of two quantities is possible in real time. These comparisons can be used to assess system conditions-such as; frequency changes, MW, MVARs, kVolts, etc. The monitored points are preselected through various studies to make extremely accurate phase angle measurements to indicate shifts in system (grid) stability. The phasor data is collected either on-site or at centralized locations using Phasor Data Concentrator technologies. The data is then transmitted to a regional monitoring system which is maintained by the local Independent System Operator (ISO). These ISO's will monitor phasor data from individual PMU's or from as many as 150 PMU's — this monitoring provides an accurate means of establishing controls for power flow from multiple energy generation sources (nuclear, coal, wind, etc.).

The technology has the potential to change the economics of power delivery by allowing increased power flow over existing lines. Synchrophasor data could be used to allow power flow up to a line's dynamic limit instead of to its worst-case limit. Synchrophasor technology will usher in a new process for establishing centralized and selective controls for the flow of electrical energy over the grid. These controls will affect both large scale (multiple-states) and individual transmission line sections at intersecting substations. Transmission line congestion (over-loading), protection, and control will therefore be improved on a multiple region scale (US, Canada, Mexico) through interconnecting ISO's.

Phasor networks

A phasor network consists of phasor measurement units (PMUs) dispersed throughout the electricity system, Phasor Data Concentrators (PDC) to collect the information and a Supervisory Control And Data Acquisition (SCADA) system at the central control facility. Such a network is used in Wide Area Measurement Systems (WAMS), the first of which began in 2000 by the Bonneville Power Administration.[8] The complete network requires rapid data transfer within the frequency of sampling of the phasor data. GPS time stamping can provide a theoretical accuracy of synchronization better than 1 microsecond. "Clocks need to be accurate to ± 500 nanoseconds to provide the one microsecond time standard needed by each device performing synchrophasor measurement." [9] For 60 Hz systems, PMUs must deliver between 10 and 30 synchronous reports per second depending on the application. The PDC correlates the data, and controls and monitors the PMUs (from a dozen up to 60).[10] At the central control facility, the SCADA system presents system wide data on all generators and substations in the system every 2 to 10 seconds.

PMUs often use phone lines to connect to PDCs, which then send data to the SCADA or Wide Area Measurement System (WAMS) server.[11] Additionally, PMUs can use ubiquitous mobile (cellular) networks for data transfer (GPRS, UMTS), which allows potential savings in infrastructure and deployment costs, at the expense of a larger data reporting latency.[12][13] However, the introduced data latency makes such systems more suitable for R&D measurement campaigns and near real-time monitoring, and limits their use in real-time protective systems.

PMUs from multiple vendors can yield inaccurate readings. In one test, readings differed by 47 microseconds – or a difference of 1 degree of at 60 Hz- an unacceptable variance.[14] China's solution to the problem was to build all its own PMUs adhering to its own specifications and standards so there would be no multi-vendor source of conflicts, standards, protocols, or performance characteristics.[15]

Installation

Installation of a typical 10 Phasor PMU is a simple process. A phasor will be either a 3 phase voltage or a 3 phase current. Each phasor will, therefore, require 3 separate electrical connections (one for each phase). Typically an electrical engineer designs the installation and interconnection of a PMU at a substation or at a generation plant. Substation personnel will bolt an equipment rack to the floor of the substation following established seismic mounting requirements. Then the PMU along with a modem and other support equipment will be mounted on the equipment rack. They will also install the Global Positioning Satellite (GPS) antenna on the roof of the substation per manufacturer instructions. Substation personnel will also install "shunts" in all Current transformer (CT) secondary circuits that are to be measured. The PMU will also require communication circuit connection (Modem if using 4-wire connection or Ethernet for network connection).[7]

Implementations

Applications

  1. Power system automation, as in smart grids
  2. Load shedding and other load control techniques such as demand response mechanisms to manage a power system. (i.e. Directing power where it is needed in real-time)
  3. Increase the reliability of the power grid by detecting faults early, allowing for isolation of operative system, and the prevention of power outages.
  4. Increase power quality by precise analysis and automated correction of sources of system degradation.
  5. Wide area measurement and control through state estimation,[17] in very wide area super grids, regional transmission networks, and local distribution grids.
  6. Phasor measurement technology and synchronized time stamping can be used for Security improvement through synchronized encryptions like trusted sensing base. Cyber attack recognition by verifying data between the SCADA system and the PMU data.[18]
  7. Distribution State Estimation and Model Verification. Ability to calculate impedances of loads, distribution lines, verify voltage magnitude and delta angles based on mathematical state models.
  8. Event Detection and Classification. Events such as various types of faults, tap changes, switching events, circuit protection devices. Machine learning and signal classification methods can be used to develop algorithms to identify these significant events.
  9. Microgrid applications––islanding or deciding where to detach from the grid, load and generation matching, and resynchronization with the main grid.[19]

Standards

The IEEE 1344 standard for synchrophasors was completed in 1995, and reaffirmed in 2001. In 2005, it was replaced by IEEE C37.118-2005, which was a complete revision and dealt with issues concerning use of PMUs in electric power systems. The specification describes standards for measurement, the method of quantifying the measurements, testing & certification requirements for verifying accuracy, and data transmission format and protocol for real-time data communication.[11] This standard was not comprehensive- it did not attempt to address all factors that PMUs can detect in power system dynamic activity.[10] A new version of the standard was released in December 2011, which split the IEEE C37.118-2005 standard into two parts: C37.118-1 dealing with the phasor estimation & C37.118-2 the communications protocol. It also introduced two classifications of PMU, M — measurement & P — protection. M class is close in performance requirements to that in the original 2005 standard, primarily for steady state measurement. P class has relaxed some performance requirements and is intended to capture dynamic system behaviour.

Other standards used with PMU interfacing:

See also

References

  1. Yilu Liu; Lamine Mili; Jaime De La Ree; Reynaldo Francisco Nuqui; Reynaldo Francisco Nuqui (2001-07-12). "State Estimation and Voltage Security Monitoring Using Synchronized Phasor Measurement". Research paper from work sponsored by American Electric Power, ABB Power T&D Company, and Tennessee Valley Authority (pdf). Virginia Polytechnic Institute and State University. CiteSeerX 10.1.1.2.7959Freely accessible. "Simulations and field experiences suggest that PMUs can revolutionize the way power systems are monitored and controlled. However, it is perceived that costs and communication links will affect the number of PMUs to be installed in any power system."
  2. KEMA, Inc. (November 2006). "Substation Communications: Enabler of Automation / Technologies". UTC — United Telecom Council: 3–40.
  3. Charles Proteus Steinmetz (1893). "Complex Quantities and Their Use in Electrical Engineering". Proceedings of the International Electrical Congress, Chicago. Chicago, Illinois 1893 conference of the AIEE: American Institute of Electrical Engineers Proceedings: 33–74.
  4. Macrodyne model 1690
  5. Phadke, A.G. (Virginia Polytechnic Institute and State University) (2002-10-10). "Synchronized phasor measurements-a historical overview" (pdf). Transmission and Distribution Conference and Exhibition 2002: Asia Pacific. IEEE/PES. Institute of Electrical and Electronics Engineers (IEEE). 1: 476. doi:10.1109/TDC.2002.1178427. Retrieved 2008-11-27.
  6. "Optimizing a new processor architecture ", Rob Landley, Linux Conf Australia, January 2017, https://www.youtube.com/watch?v=o0milqmt4ao (Retrieved May 20, 2017)
  7. 1 2 "Phasor Advanced FAQ". CERTS. Retrieved 6 January 2013.
  8. "Gridwise History: How did GridWise start?". Pacific Northwest National Laboratory. 2007-10-30. Retrieved 2008-12-03.
  9. KEMA, Inc. (November 2006). "Substation Communications: Enabler of Automation / An Assessment of Communications Technologies". UTC — United Telecom Council: 3–54.
  10. 1 2 3 Jim Y. Cai; Zhenyu Huang; John Hauer; Ken Martin (2005). "Current Status and Experience of WAMS- Implementation in North America" (pdf). Transmission and Distribution Conference and Exhibition: Asia and Pacific, 2005 IEEE/PES. Institute of Electrical and Electronics Engineers (IEEE): 3. doi:10.1109/TDC.2005.1546889. Retrieved 2008-12-06. Lay summary.
  11. 1 2 Pei Zhang; J. Chen; M. Shao (October 2007). "Phasor Measurement Unit (PMU) Implementation and Applications (DOCID 1015511)" (pdf). Electric Power Research Institute (EPRI). Retrieved 2008-11-27.
  12. S. Skok; D. Brnobic; V. Kirincic (August 2011). "Croatian Academic Research Wide Area Monitoring System — CARWAMS" (pdf). Institute of Electrical and Electronics Engineers. Retrieved 2011-12-23.
  13. Brnobic, Dalibor (2013-09-10). "WAMSTER Architecture Details". Wamster.
  14. A. P. Meliopoulos; Vahid Madani; Damir Novosel; George Cokkinides; et al. (October 2007). "Synchrophasor Measurement Accuracy Characterization" (pdf). North American SynchroPhasor Initiative Performance & Standards Task Team. Consortium for Electric Reliability Technology Solutions. Retrieved 2008-11-27.
  15. 1 2 Qixun Yang, Board Chairman, Beijing Sifang Automation Co. Ltd., China and .Bi Tianshu, Professor, North China Electric Power University, China. (2001-06-24). "WAMS Implementation in China and the Challenges for Bulk Power System Protection" (pdf). Panel Session: Developments in Power Generation and Transmission INFRASTRUCTURES IN CHINA, IEEE 2007 General Meeting, Tampa, FL, USA, 24–28 June 2007 Electric Power, ABB Power T&D Company, and Tennessee Valley Authority. Institute of Electrical and Electronics Engineers. Retrieved 2008-12-01.
  16. Wald, Matthew L. (31 July 2013). "New Tools for Keeping the Lights On". New York Times.
  17. Yih-Fang Huang; Werner, S.; Jing Huang; Kashyap, N.; Gupta, V. (September 2012). "State Estimation in Electric Power Grids: Meeting New Challenges Presented by the Requirements of the Future Grid". IEEE Signal Processing Magazine. 29 (5): 33,43. doi:10.1109/MSP.2012.2187037.
  18. Mazloomzadeh, Ali; Mohammed, Osama; Zonouz, Saman (2013). "TSB: Trusted sensing base for the power grid". SmartGridComm: 2013 IEEE International Conference on Smart Grid Communications. ISBN 978-1-4799-1526-2. doi:10.1109/SmartGridComm.2013.6688058.
  19. Alexandra von Meier (2014). "Micro-synchrophasors for Distribution Systems". Proceedings of the International Electrical Congress, Chicago. Innovative Smart Grid Technologies Conference.