Selby Coalfield
Selby coalfield (also known as the Selby complex, or Selby 'superpit') was a large scale deep underground mine complex based around Selby, North Yorkshire, England, with pitheads at Wistow Mine, Stillingfleet Mine, Riccall Mine, North Selby Mine, Whitemoor Mine and at Gascoigne Wood Mine; all coal was brought to the surface and treated at Gascoigne Wood, being distributed onwards by rail. The primary purpose of the pit was to supply coal for electrical power generation; much of it was used in the nearby Aire valley power stations.
Mining peaked in 1993–4 at 12 million tonnes a year. The mines were acquired by RJB Mining in 1997 after the privatisation of the coal industry; loss of subsidy, geological problems, and low UK coal prices made the pits unprofitable by the 21st century. Closure was announced in 2002, and mining completely ceased by 2004.
History
In 1974, the Labour Government and National Coal Board (NCB), backed by the National Union of Mineworkers (NUM) initiated a decade-long, ambitious expansion of coal production, named the Plan for Coal; the plan was based on maximising income from indigenous coal reserves, at a time when oil prices had risen (1973 oil crisis) to above that of coal. The plan included continued closure of older pits, and investment in new capacity; Selby Coalfield was a major element of the plan.[1][2][3]
Exploratory drilling in the Selby area had taken place in the 1960s, and detailed exploration was carried out in the early 1970s, showing that a northern extension of the 'Barnsley Seam' was present and between 1.9 and 3.25 m thick, resulting in an estimate of 600 million tonnes of coal in the seam, with total estimated coal reserves of 2,000 million tonnes. Open extraction would have required a stripping ratio of around 500:1, so the coal was extracted by underground mining. A geological report "Coal reserves in the Selby Area" was published 1972, and planning permission sought for a mine in 1974, which was given in 1976 after opposition, including concerns about flooding of low-lying land due to subsidence; extraction was limited to the Barnsley seam, though other seams existed.[2][4]
The project was formally inaugurated by the Duchess of Kent in 1976. Initial estimates were for a construction cost of £400 million, with 4,000 people employed, with extraction beginning in the early 1980s and lasting for 40 years, producing 10 million tons per year. The scheme used an unusual arrangement of pits in the coal field – all coal was brought to the surface at the drift mine of Gascoigne Wood, whilst five pits were created to the east (Wistow, North Selby, Riccall, Stillingfleet, and Whitemoor) which transferred their coal via underground tunnels to Gascoigne Wood.[5][6] As part of the construction processes, the NCB paid for diversion of the East Coast Main Line from Selby (see Selby Diversion) to avoid areas that could be subject to mining subsidence.[7] Above ground equipment such as the winding gear was constructed enclosed by cladding and with limited height, to limit the visual impact on the environment, which was a predominately rural landscape.[8][9] Shafts for the pits were first sunk in the late 1970s, and in 1983 the Wistow Mine began production.[5][8]
Many of the miners were moved under transfer packages from other collieries that were being closed down, particularly in the Wakefield area.[10] Large car parks were built to facilitate commuting.[10]
The new mine produced no coal in 1984/5 due to the UK miners' strike (1984–1985).[11] Gascoigne Wood was the scene of clashes between pickets and police.[9][12]
Output steadily rose during from 1984 to 1994, reaching 10 million tonnes a year in 1992–93.[11]
In 1993/4, the complex had peak output of 12 million tonnes p.a.[5] In 1994, the Coal Industry Act created the legal framework for the breakup of British Coal;[13] in 1995, the coalfield was acquired by RJB Mining. Geological problems caused some coal seams to be ignored, and Whitemoor Mine was merged with Riccall Mine in 1996, and North Selby Mine with Stillingfleet Mine in 1997. By 2000, production was 4.4 million tonnes p.a.[5][14]
Between 1995 and 1999, the operation turned from being successfully profitable to loss-making, with the first loss recorded in 1999; relatively fixed costs associated with the single exit-point at Gascoigne Wood meant that the mine became less profitable as production was reduced at the five pits. By 2000, the loss was (£30 million pa), and it received no subsidy; in 2002, it was announced by UK Coal that the Selby coalfield would close in 2003/4. Mining ended in 2004 at Wistow (May), Stillingfleet (July), and Riccall (October). The total amount of coal mined was 121 million tonnes.[5][8][15]
Post closure
The Gascoigne Wood Mine site is the largest, with 44 ha (110 acres) developable land, and best connected of the former mine sites, with rail connection onto the former Leeds and Selby Railway (Leeds-Hull Line) including sidings for trains of up to 775 m. On site facilities include a 58 MW electrical grid connection, and the site is close to the large Sherburn-in-Elmet Industrial Estate, and directly south of the Sherburn-in-Elmet Airfield. Planning permission for re-use of buildings and infrastructure was granted in 2007.[16][17] Beginning 2008 part of the site has been used on short term lease to British Gypsum for storage of Gypsum produced at Drax Power Station as a byproduct of flue gas desulphurisation.[16][18] The site has also been proposed for use as a manufacturing site for rail vehicles (Hitachi, rejected 2010),[19] and an Eco-town development (rejected by Selby district council 2008).[20]
The Whitemoor Mine site has been converted to mixed commercial use as Whitemoor Business Park.[16][21]
Riccall Mine has been converted to an industrial and office development, having received planning permission for the development in 2007.[16][22]
In 2009 the North Selby Mine was proposed as a renewable energy site, using waste as a feedstock for electricity generation. The initially proposed energy generation methods of incineration and gasification were dropped in 2011 with the plan had been modified to include a larger facility for anaerobic digestion, as well as using in vessel composting of organic waste.[23] As of March 2012 the status of the development is undecided.[24]
As of early 2012 Stillingfleet Mine has been partially redeveloped, being used for extraction and generation from coal mine gas,[25] further redevelopment is being sought.[16]
As of early 2012 Wistow Mine has not been redeveloped,[26] land manager Haworth Estates, is seeking redevelopment of the site which utilises the legacy on site facilities, which includes a 12 MW electrical grid connection.[16]
References
- ↑ Sources:
- Barlow, Keith (2008), The labour movement in Britain from Thatcher to Blair (2 ed.), Peter Lang, p. 166, ISBN 978-3-631-55137-0
- Taylor, Andrew (2005), "3. Plans for Coal", The NUM and British Politics: Volume2: 1969–1995, Ashgate Publishing, pp. 111–142, also Preface, p.x, ISBN 0 7546 5333 1
- 1 2 Bayliss-Smith, Tim; Owens, Susan, eds. (1990), Britain's changing environment from the air, Cambridge University Press, pp. 202–3, ISBN 0 521 32712 1
- ↑ NERA, 2003, Keeping the Selby Complex Open, "2. Background", p.2
- ↑ Sources:
- Nicholas Valéry (19 July 1973), "Coal ... all the way to Newcastle?", New Scientist
- R.F. Goosens (1972/3), "Coal reserves in the Selby area"
- PRODUCTION ENDS AT SELBY COALFIELD, UK Coal, 26 October 2004, "Key Dates" : 1972 – 1976
- "2.6 Underground mining". Energy resources: Coal. openlearn.open.ac.uk. The Open University. Box 2. "The rise and fall of an underground coalfield: the Selby complex in North Yorkshire". Retrieved 4 April 2012.
- 1 2 3 4 5 PRODUCTION ENDS AT SELBY COALFIELD, UK Coal, 26 October 2004, "Selby Coalfield, Background Notes"; "Key Dates" : 1976 – 2004
- ↑ "1976: Duchess opens massive Selby coalfield", On This Day, BBC, 29 October 1976, retrieved 6 December 2013
- ↑ Sources:
- Simmons, Jack; Biddle, Gordon (1997), The Oxford companion to British railway history from 1603 to the 1990s, Oxford University Press, pp. 137, 498
- Davies, P. B.; Fenwick, T. H.; Bastin, R. D. (1983). "Selby Diversion of the East Coast Main Line. 1. The Background and Study of Alternatives. 2. Route Design. 3. Bridges". ICE Proceedings. 74 (4): 719. doi:10.1680/iicep.1983.1361.
- 1 2 3 Hilary Macaskill (26 October 2004), "Dust to dust"
- 1 2 Dave Douglas, "The Selby Complex
- 1 2 Adeney, Martin; Lloyd, John (1988). The Miners' Strike 1984-5: Loss Without Limit. London: Routledge & Kegan Paul. p. 26. ISBN 0-7102-1371-9.
- 1 2 Production Ends at Selby Coalfield, UK Coal, 26 October 2004, "Annual Production"
- ↑ Clark, Matt (3 March 2010), "Former Selby miner Steve Shaw-Wright remembers the miners strike of 1984–85", The York Press, retrieved 2 April 2012
- ↑ "Coal Industry Act 1994", www.legislation.gov.uk, The National Archive
- ↑ "Selby Coalfield", Hansard: House of Commons, 16 April 2002
- ↑ Sources:
- Macalister, Terry (16 July 2002), "Selby closes with loss of 5,000 jobs", The Guardian, retrieved 8 April 2013
- Hughes, Marcia (25 October 2004), "Mourning subdued as last Selby pit shuts", BBC News, BBC, retrieved 8 April 2013
- NERA, 2003, Keeping the Selby Complex Open, "Executive Summary", pp.1–2; "3. Selby", pp.4–5
- 1 2 3 4 5 6 Selby local development framework proposed changes to the submission draft core strategy : Representations on behalf of Harworth Estates former Selby Mine Complex sites (PDF), BNP Paribas Real Estate, 9 February 2012, retrieved 8 April 2013
- ↑ Sources:
- Gascoigne Wood Business Park, UK Coal, retrieved 4 April 2012
- Gascoigne Interchange (PDF), DTZ, November 2009, retrieved 8 April 2013
- "Gascoigne Interchange", gascoigne-interchange.co.uk, retrieved 8 April 2013
- "Business park approved at ex-mine site", York Press, 18 August 2007, retrieved 8 April 2013
- ↑ Sources:
- "Gascoigne Wood mine building gets new lease of life", Selby Times, 3 December 2008, retrieved 8 April 2013
- Grimshaw, Gerran (29 December 2007), "Rail deal will reduce roads’ load", York Press, retrieved 8 April 2013
- "Rail transport of gypsum will avoid thousands of lorry journeys a year", Yorkshire Post, 10 December 2007, retrieved 8 April 2013
- ↑ Harris, Richard (21 August 2010), "Hopes dashed for rail jobs in Selby", York Press, retrieved 8 April 2013
- ↑ "Other site thrown out", Selby Times, 13 February 2008, retrieved 8 April 2013
- ↑ Sources:
- Whitemoor, Barlby, Selby, UK Coal, retrieved 4 April 2012
- Whitemoor Business Park, Selby, Y08 6EG, Haworth Estates, retrieved 4 April 2012
- ↑ Sources:
- Riccall Business Park, UK Coal, retrieved 4 April 2012
- Riccall, UK Coal, retrieved 4 April 2012
- ↑ Sources:
- "150 jobs hope at former North Selby mine site", Selby Times, 4 May 2009, retrieved 8 April 2013
- Stead, Mark (30 July 2010), "Electricity plant plan for former North Selby mine moves on", York Press, retrieved 8 April 2013
- "Plug pulled on planned incinerator for Selby", Selby Times, 2 April 2012, retrieved 8 April 2013
- North Selby Renewable Energy Centre – Peel Environmental, Peel Holdings, retrieved 8 April 2013
- ↑ "Escrick Parish Council Meeting" (PDF), www.escrick.co.uk, 19 March 2012, retrieved 8 April 2013
- ↑ Stillingfleet, Selby, Y019 6HX, Haworth Estates, retrieved 4 April 2012
- ↑ Wistow, Selby, YO8 3, Haworth Estates, retrieved 4 April 2012
Sources
- Goosens, R.F. (1972–73), "Coal reserves in the Selby area", Min.Eng, 132: 237–246
- Douglas, Dave, "The Selby Complex", www.minersadvice.co.uk
- "The end of the "superpit"", www.workersliberty.org, 23 November 2004
- Macaskill, Hilary (26 October 2004), "Dust to dust", The Guardian
- "Selby Coalfield", Hansard: House of Commons, 383, cc.147WH-155WH, 16 April 2002
- Valéry, Nicholas (19 July 1973), "Coal ... all the way to Newcastle?", New Scientist, 59 (855): 132–133, ISSN 0262-4079
- PRODUCTION ENDS AT SELBY COALFIELD (PDF), UK Coal, 26 October 2004
- NERA Economic Consulting (11 February 2003), "Keeping the Selby Complex Open", www.nera.com
Literature
- Massey, C. T.; Eaton, W. M. (1984). "The Selby coalfield–a new concept for an old industry". Proceedings of the Institution of Mechanical Engineers, Part A: Power and Process Engineering 1983-1988. 198 (13): 241. doi:10.1243/PIME_PROC_1984_198_029_02.
Locations
- 53°53′28″N 1°00′56″W / 53.89101°N 1.01557°W, North Selby Mine, about 1 mile (1.6 km) northeast of Escrick
- 53°48′53″N 0°59′29″W / 53.81472°N 0.99131°W, Whitemoor Mine, about 2.5 miles (4 km) east-northeast of Barlby
- 53°48′45″N 1°07′47″W / 53.81247°N 1.12971°W, Wistow Mine, about 1 mile (1.6 km) west of Wistow
- 53°49′30″N 1°01′57″W / 53.82493°N 1.03243°W, Riccall Mine, about 1 mile (1.6 km) southeast of Riccall
- 53°51′25″N 1°05′05″W / 53.85706°N 1.08474°W, Stillingfleet Mine, about 0.6 miles (1 km) southeast of Stillingfleet
- 53°46′48″N 1°12′26″W / 53.78004°N 1.20709°W, Gascoigne Wood Mine, about 1.8 miles (3 km) east of South Milford, rail connected to the Leeds and Selby Railway east of junction with the former York and North Midland Railway York to Castleford line
External links
Wikimedia Commons has media related to Selby Coalfield. |
- Ross, Pamela Y., Selby complex history
- "The Selby Coalfield Superpit", BBC North Yorkshire, BBC, 2004, BBC Radio 4 documentary (.ram RealAudio streaming file)