North Coast Corridor

The North Coast Corridor is an infrastructure improvement project in northern San Diego County, California that will upgrade road, rail, pedestrian, and bicycle transportation infrastructure, as well as fund environmental restoration. The project has a $6 billion budget, and after beginning the first phases of construction in late 2016 is planned to be completed over the following 40 years.[1]

First phase

The $700 million initial phase of construction began in 2016 with a groundbreaking on November 29 at the San Elijo Lagoon.[1] The projects in this phase are scheduled to be completed by 2021.[1]

Highway

Two new bridges are to be built on Interstate 5one across the San Elijo Lagoon in Solana Beach and Encinitas, and one across the Batiquitos Lagoon in Carlsbad.[1] Other road projects include added carpool lanes and sound barriers.[1] The total cost of the highway portion of the first phase was budgeted for $480 million.[2]

Rail

Two segments of the major passenger rail line following the coast from San Diego north, used by Coaster commuter trains and Pacific Surfliner intercity trains, are to be double tracked. Work began initially on a 2.4 kilometres (1.5 mi) segment of track between Cardiff-by-the-Sea and San Elijo Lagoon, including replacement of the railroad bridge over the lagoon.[2] In mid-2017, work is scheduled to begin on a similar project near the Batiquitos Lagoon, including a bridge replacement and 1.2 kilometres (0.75 mi) of new double track.[2] These projects, as well as grade crossing work, are budgeted for $102 million.[2]

Other transportation

$40 million is to be spent on bicycle path and pedestrian improvements, along with local community enhancements.[1]

Environment

The San Elijo Lagoon will receive $80 million for restoration efforts, such as dredging and filling to bring sediment to natural levels, as well as additional conserved area to mitigate the impact of the new road and rail bridges.[1] This work is scheduled to begin in 2017.[1]

References

  1. 1 2 3 4 5 6 7 8 "Work begins on 700m in North Coast corridor projects". San Diego Union-Tribune. November 29, 2016. Retrieved December 7, 2016.
  2. 1 2 3 4 "California launches $US 6bn North Coast Corridor project". International railway Journal. December 1, 2016. Retrieved December 7, 2016.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.