Kukule Ganga Dam

Kukule Ganga Dam
Location of Kukule Ganga Dam in Sri Lanka
Country Sri Lanka
Coordinates 06°34′48″N 80°19′37″E / 6.58000°N 80.32694°E / 6.58000; 80.32694Coordinates: 06°34′48″N 80°19′37″E / 6.58000°N 80.32694°E / 6.58000; 80.32694
Purpose Power
Status Operational
Construction began July 1999 (1999-07)
Opening date June 2005 (2005-06)
Construction cost Rs.16.5 billion
Dam and spillways
Type of dam Gravity dam
Impounds Kukule River
Spillways 4
Reservoir
Creates Kukule Ganga Reservoir
Total capacity 1,630,000 m3 (58,000,000 cu ft)
Catchment area 312 km2 (120 sq mi)
Surface area 88 ha (0.88 km2)
Normal elevation 205 m (673 ft)
Power station
Coordinates 06°37′00″N 80°16′33″E / 6.61667°N 80.27583°E / 6.61667; 80.27583
Type Run-of-the-river
Turbines 2 × 40 megawatts (54,000 hp)
Installed capacity 80 megawatts (110,000 hp)
Annual generation 317 gigawatt-hours (1,140 TJ)

The Kukule Ganga Dam is a 110 m (360 ft) gravity dam built across the Kukule River in the Sabaragamuwa Province of Sri Lanka. The run-of-river-type dam feeds an underground hydroelectric power station located approximately 5 kilometres (3.1 mi) away, via tunnel.[1][2]

Dam and reservoir

The gravity dam is built across the Kukule River, which is a major mid-basin tributary of the Kalu River. The dam measures 110 m (361 ft) and 20 m (66 ft) in length and height respectively, with four spillways, and a sand trap on the left-bank.[1] Each spillway gate measures 9.3 m (31 ft) high and 12 m (39 ft) wide, and uses the same automated technology as the Victoria Dam.[3]

The dam creates the Kukule Ganga Reservoir, which has a capacity and catchment area of 1,630,000 m3 (58,000,000 cu ft) and 312 km2 (120 sq mi) respectively. After passing through the dam and sand traps, water from the reservoir is fed into a 5.71 km (3.55 mi) long tunnel, which leads to the underground power station. The tunnel from the dam to the power station, with an internal diameter of 10.5–4.8 m (34.4–15.7 ft), creates a gross head of 185 m (607 ft).[3]

Power station

Water from the tunnel is fed into the 80 MW underground power station, consisting of two 40 MW units. This capacity was intentionally limited to 70 MW due to load issues.[4] The power station generates an average of 317 GWh annually.[2]

Two transformers step up the voltage of the power generated to 132 kV, which is then transferred to the national grid at the Mathugama Substation, via a 27 kilometres (17 mi) long 132 kV double-circuit transmission line.[2]

See also

References

  1. 1 2 "Kukule Ganga Dam, Sri Lanka". Water-Technology. Retrieved 11 February 2014. External link in |publisher= (help)
  2. 1 2 3 Vimukthi Fernando (11 May 2003). "Kukule Ganga Hydro Power Project: Relief from shocking electricity bills?". Sunday Observer. Retrieved 11 February 2014.
  3. 1 2 Kamal Laksiri (3 June 2003). "Kukule Ganga: The story so far.". Water Power Magazine. Retrieved 11 February 2014. External link in |publisher= (help)
  4. "Kukule Ganga Hydroelectric Power Project" (PDF). Japan International Cooperation Agency. Retrieved 11 February 2014.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.