The Koror–Babeldaob Bridge is a bridge in Palau that connects Koror and Babeldaob Islands. It is a reinforced concrete, portal frame, cable-stayed bridge with a total length of 413 m. It was built by the Kajima Corporation of Japan in 2002, to replace the former, collapsed bridge built by Socio Construction Co. of Korea in 1978 and collapsed in 1996.

The former KB Bridge

The preserved slate of the former Koror-Babeldaob Bridge; January 2011.

The original Koror–Babeldaob Bridge was a balanced cantilever prestressed concrete box girder bridge with a main span of 240.8 m and total length of 385.6 m (1265 ft). In addition to carrying traffic, it also carried piping and conduits for fresh water and electricity. It was designed by Dyckerhoff & Widmann AG and Alfred A. Yee and Associates. It was constructed by Dyckerhoff & Widmann AG, contractor was Palau based[1][2] Korean company, Socio Construction Co.[3][4] It was the world's largest bridge of its type,[5] until its record was broken by the 260 m span of the Gateway Bridge in Brisbane, Australia, finished in 1985.

The middle hinge point of the bridge began to noticeably sag in the middle 10 years after its completion. This led to two studies carried out by Louis Berger International and the Japan international Co-operation Agency in 1990. They concluded that the bridge was "safe" as of now (in 100 year increments it will cave in 90 cm) and the large deflections were due to creep and the modulus of elasticity of the concrete in place being lower than anticipated.[6]

On September 26, 1996, after having reinforcement work done, the bridge suddenly collapsed and shut off fresh water and electricity between the islands. In addition, the collapse killed two people and injured four more. This caused the government to declare a state of emergency. By request of Kuniwo Nakamura, then the country's President and foreign minister, Japan provided emergency aid as well as a temporary bridge.[7] [8]

Reason for the collapse

The 18-year-old, Koror-Babeldaob bridge (KB bridge) collapsed abruptly and catastrophically. The failure occurred during benign weather and loading conditions, six years after two independent teams (Louis Berger International and the Japan international Co-operation Agency[6]) of bridge engineers had evaluated the bridge and declared it safe, and less than three months after completion of a strengthening programme to correct a significant midspan sag that was continuing to worsen.

Original Koror-Babeldaob Bridge collapse

By 1990, a physical phenomenon called creep had caused the midline of the bridge to sag 1.2 meters, causing discomfort to drivers and concern for officials. The Palau government commissioned two studies by Louis Berger International and Japan International Co-operation Agency. They both concluded that the bridge was structurally safe as of 1990 though 1m more of creep would occur in the future.Based on the studies, the Palau government decided to counteract the cosmetic damage caused by creep with resurfacing and reinforcement of the bridge.[9]

According to British civil engineers Chris Burgoyne and Richard Scantlebury, the reinforcement operation had 4 main components.

  1. The bridge midspan was modified, changing the originally non-weight-bearing hinged joint to a continuous block of concrete.
  2. Eight prestress cables were added to straighten the span.
  3. Eight flat-jacks were added to the center of the structure to add additional prestress, loading the center of the bridge.
  4. The bridge was resurfaced to smooth out the sagging road.

The most probable progression of the collapse began with a weakening of the Babeldaob side. This caused a shear failure, resulting in all of the weight of the continuous main span coming to rest on the Koror side. This unbalanced moment caused the backspan of the Koror side to fail and tipped the bridge into the channel. The new design of the bridge hastened the bridge's collapse, but did not actually cause the fatal weakening of the Babeldoab flange. The cause of collapse remains unknown though it was studied in some detail by professional firms and researchers.[10][9]The repair and resurfacing operation may have contributed to the bridge failure, but since the lawsuit over the collapse was settled out of court, no final cause has ever been definitively published.

Japan-Palau Friendship Bridge

Japan Palau Friendship Bridge

As the Palau government lacked sufficient funds to rebuild immediately, a new bridge to provide a steady transportation system was constructed with significant Japanese Grant Aid in ODA. Its construction began in 1997 by Kajima Corporation, a Japanese construction company, and was completed in December, 2001. It was named "Japan-Palau Friendship Bridge" on its opening ceremony on January 11, 2002.[11]

See also

References

  1. Socio Website
    ...Welcome to Socio's website. Socio is a construction and engineering firm located in Koror, Palau and operated under Surangel and Sons Co.
  2. Locate and HeadQuarter of Surangel and Sons Company
  3. A picture of the plate in Hangul and English which is recessed at the former KB Bridge.
  4. According to Structurae database, the bridge was completed in 1978. However, there are also sources which describe it as in 1977.
  5. Troyano, L.F., "Bridge Engineering: A Global Perspective", Thomas Telford Publishing, 2003, p.426
  6. 1 2 The Collapse of the K-B Bridge in 1996 Matthias Pilz, Institut für Massivbau und Baustofftechnologie, Universität Leipzig
  7. Pontoon Type (Floating Structure with Flat Plates) bridge, Palau History; page 1 Britannica Online Encyclopedia
  8. Picture of the temporary bridge Stuffedwombat.com
  9. 1 2 Burgoyne, C. Scantlebury, R. (2006) "Why did Palau Bridge Collapse?" http://www-civ.eng.cam.ac.uk/cjb/papers/p56.pdf
  10. http://www.wje.com/projects/detail.php?pid=1996.2868.0
  11. Palau History; page 10 Britannica Online Encyclopedia

Coordinates: 7°21′43″N 134°30′15″E / 7.36204°N 134.50424°E / 7.36204; 134.50424

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.