Kashagan Field

Kashagan Field

Location of Kashagan Field

Country Kazakhstan
Region Pre-Caspian Basin
Location Near Atyrau
Offshore/onshore Offshore
Coordinates 46°10′N 51°35′E / 46.167°N 51.583°E / 46.167; 51.583Coordinates: 46°10′N 51°35′E / 46.167°N 51.583°E / 46.167; 51.583
Operator North Caspian Operating Company
Partners Eni (16.81%)
KazMunayGas (16.88%)
Royal Dutch Shell (16.81%)
Total S.A. (16.81%)
ExxonMobil (16.81%)
China National Petroleum Corporation (8.4%)
Inpex (7.56%)
Field history
Discovery 2000
Start of development 2001
Start of production Sept. 2013[1]
Abandonment after 2040
Production
Estimated oil in place 38,000 million barrels (~5.2×10^9 t)
Recoverable oil 13,000 million barrels (~1.8×10^9 t)
Producing formations Carboniferous limestones

Kashagan Field is an offshore oil field in Kazakhstan's zone of the Caspian Sea.[2] The field, discovered in 2000, is located in the northern part of the Caspian Sea close to Atyrau and is considered the world's largest discovery in the last 30 years, combined with the Tengiz Field.[3]

It is estimated that the Kashagan Field has recoverable reserves of about 13 billion barrels (2.1×10^9 m3) of crude oil. Harsh conditions, including sea ice during the winter, temperature variation from −35 to 40 °C (−31 to 104 °F), extremely shallow water and high levels of hydrogen sulfide, together with mismanagement and disputes, make it one of the most challenging oil megaprojects.[4][5] Commercial production began in September 2013.[1] It has been designated as the main source of supply for the Kazakhstan-China oil pipeline.[6] CNN Money estimates that development of the field had cost US$116 billion as of 2012, which made it the most expensive energy project in the world,[7][8] while other sources report the cost at up to $50 billion.[4][5]

A stake in the field was acquired by the Chinese government in September 2013 after Xi Jinping struck a deal with Kazakhstan for around $5 billion.[9]

History

Interest in the Caspian Sea first began in 1992 when an exploration program was announced by the Kazakh government. They sought the interest of over 30 companies to partake in the exploration. In 1993 the Kazakhstancaspiishelf was formed which consisted of Eni, BG Group, BP/Statoil, Mobil, Royal Dutch Shell and Total S.A., along with the Kazakh government. This consortium lasted 4 years until 1997, when seismic exploration of the Caspian Sea was undertaken.

Upon completion of an initial 2D seismic survey in 1997, the company became Offshore Kazakhstan International Operating Company (OKIOC). In 1998 Phillips Petroleum Company and Inpex joined the consortium. Kashagan was discovered in 2000.[10]

The consortium changed when it was decided that one company was to operate the field instead of joint operatorship as had been agreed before. Eni was named the exclusive operator in 2001. In 2001 BP/Statoil sold their stake in the project to the remaining partners. With Eni as the operator, the project was renamed Agip Kazakhstan North Caspian Operating Company NV (Agip KCO).

In 2003, BG Group attempted to sell their stake in the project to two Chinese companies, CNOOC and Sinopec. However, the deal did not go through due to the partners' exercise of their pre-emptive privileges. Eventually, in 2004 the Kazakh government bought half of BG's stake in the contract, with the other half shared out among other five Western partners in the consortium that had exercised their pre-emptive rights. The sale was worth approximately $1.2 billion. The Kazakh stake was transferred to the state-owned oil company KazMunayGas. On 27 September 2007, the parliament of Kazakhstan approved a law enabling the government to alter or cancel contracts with foreign oil companies if their actions were threatening national interests.[11]

With President Nursultan Nazarbayev appointing Maksat Idenov [12] to lead negotiations,[13] KazMunayGas further increased its stake in January 2008,[14] after its six partners and the Kazakhn government agreed on compensation for the probable five-year delay that was taken in developing the field. Eni operated this project under the JV company name of AgipKCO (Agip Kazakhstan North Caspian Operating Company N.V.).[15] Following the agreements reached on 31 October 2008 between Kazakh authorities and co-ventures under the North Caspian PSA (NCPSA), operatorship of the NCPSA was formally transferred from AGIP KCO to a new company, North Caspian Operating Company BV (NCOC), on 23 January 2009.[16]

In October 2008, Agip KCO handed a $31 million letter of intent for FEED work on phase two to a joint venture of Aker Solutions, WorleyParsons and CB&I. WorleyParsons and Aker Solutions are also engaged in phase one, carrying out engineering services, fabrication and hook-up.[17]

In November 2012, ONGC Videsh agreed to buy ConocoPhillips's 8.4% stake. The Kazakh government, however, decided in July 2013 to use its pre-emptive right to buy ConocoPhillips's stake, which it sold to CNPC later that year.[4][7][18] The deal was already approved by Eni.[19]

On 11 September 2013, Kashagan began oil production after years of delay, with ExxonMobil and ConocoPhillips planning to increase production over the next several years.[1] The Oil and Gas Minister of Kazakhstan has estimated the oil field will pump 8 million tonnes of oil in 2014.[20][21]

When the pipeline was shutdown, Hydrogen Sulfide remaining in the pipe was burned off as an emergency measure, releasing Sulfur Dioxide into the atmosphere. As a result, in March 2014, Kazakhstan's environment ministry levied a fine upon the operating companies of $735 million.[22][23][24]

Geology

The Kashagan contract area covers an area of over 5,500 square kilometres (2,100 sq mi) and consists of five separate fields, producing formations from the Precaspian Basin. These fields are Kashgan, Kalamkas A, Kashagan Southwest, Aktote and the Kairan.[10]

Kashagan is a carbonate platform of Late Devonian to middle Carboniferous age. The "reef" is about 75 kilometres (47 mi) long and 35 kilometres (22 mi) across with a narrow neck joining two broader platforms (Kashagan East and Kashagan West). The top of the reservoir is about 4,500 metres (14,800 ft) below sea level and the oil column extends for over 1,000 metres (3,300 ft). The field is in very shallow water, 3 to 9 metres (9.8 to 29.5 ft) deep. The seal is middle Permian shale and late Permian salt. The reservoir consists of limestones with low porosities and permeabilities. The oil is a light oil with 45 API gravity with a high gas-oil ratio and hydrogen sulphide (H2S) content of 19%.[25] The field is heavily overpressurized, which presents a significant drilling challenge. The figures for oil in place range between 30 and 50 billion barrels (4.8 and 7.9 billion cubic metres) with a common publicly quoted figure of 38 billion barrels (6.0×10^9 m3). The recovery factor is relatively low (15-25%) due to reservoir complexity, with between 4 and 13 billion barrels (640 and 2,070 million cubic metres) being the estimated ultimate recoverable resource.[26] Three of the other fields in the contract area, Kashagan SW, Kairan, and Aktote, are also Carboniferous carbonate platforms. Kalamkas offshore has a Jurassic sandstone reservoir.

Repairs

The original pipeline that went to production in September 2013 leaked immediately.. This was because the pipe metallurgy was susceptible to high levels of wet H2S found in the Kashagahan oil. The old pipeline was replaced by a inconel cladded steel pipe. This pipeline is expected to go into production 23 October 2016.[27]

Development

Aerial view of the field structures

The field is developed by the international consortium under the North Caspian Sea Production Sharing Agreement. The Agreement is made up of 7 companies consisting of Eni (16.81%), Royal Dutch Shell (16.81%), Total S.A. (16.81%), ExxonMobil (16.81%), KazMunayGas (16.81%), China National Petroleum Corporation (8.4%), Inpex (7.56%).[18]

The main development for the field operation is a structure named Island D, connected with 12 oil wells. It consists of two trains of production, separating oil and gas, delivering them to the onshore plant and dehydrating and partly re-injecting the sour gas into the reservoir. In 2012, about 5,000 workers were employed there. Oil is transported onshore by a 92-kilometre (57 mi) long pipeline.[5] Workers are accommodated on the living quarters barge Vivaldi delivered by Wagenborg Offshore in cooperation with Wagenborg Kazakhstan B.V. and Ersai Caspian Contractor LLC.[28]

The initial production is expected to be 90,000 barrels per day (14,000 m3/d). It should reach a production rate of 370,000 barrels per day (59,000 m3/d).[29]

Oil production

Kashagan sent its first crude for export in the amount of 26,500 metric tons in October 2016. North Caspian Operating Co., which took over running of the field from Eni SpA in 2009, said it’s working to gradually increase production capacity to a target level of 370,000 barrels a day by the end of 2017.[30] The commercial output of oil started at Kashagan in November 2016.[31]

The Kashagan field produced over 450,000 tonnes of raw materials as of November 2016. Over 350,000 tonnes of oil from the Kashagan field was transported through the Caspian Pipeline Consortium (CPC) pipeline in 2016.[32]

The machinations of nations and oil companies competing for rights to exploit the Kashagan Field play a major role in Victor Robert Lee's[33] espionage novel Performance Anomalies.[34]

See also

References

  1. 1 2 3 Kramer, Andrew E. (11 September 2013). "Kazakhstan Oil Field Begins Production After Years of Delay". The New York Times. Retrieved 1 April 2014.
  2. Yenikeyeff, Shamil (November 2008). "Kazakhstan's Gas: Export Markets and Export Routes" (PDF). Oxford Institute for Energy Studies. Retrieved 17 November 2011.
  3. Johnston, Daniel (2003). International Exploration. Economics, Risk, and Contract Analysis (1 ed.). PennWell Corporation. p. 199. ISBN 0-87814-887-6.
  4. 1 2 3 Crooks, Ed; Chazan, Guy (26 November 2012). "Conoco sells stake in Kashagan field". Financial Times. Retrieved 8 December 2012.
  5. 1 2 3 Demytrie, Rayhan (7 December 2012). "Development challenge of Kazakhstan's giant oilfield". BBC News. Retrieved 8 December 2012.
  6. "Caspian oil exports heading east". Asia Times. 9 February 2005. Retrieved 20 May 2007.
  7. 1 2 "Kazakhstan's Kashagan tagged world's most expensive energy project". Tengrinews.kz. 29 November 2012. Retrieved 1 April 2014.
  8. Hargreaves, Steve (27 August 2012). "10 most expensive energy projects in the world". CNNMoney. Retrieved 1 April 2014.
  9. Mariya Gordeyeva (7 September 2013). "China buys into giant Kazakh oilfield for $5 billion". Reuters.
  10. 1 2 "Project: Kashagan". Rigzone. Archived from the original on 30 June 2006. Retrieved 26 April 2006.
  11. "A New Oil Bully in the Caspian?". BusinessWeek. 18 July 2007. Retrieved 18 July 2008.
  12. "The creation of a new operating company rules out operatorship in Kashagan". New Europe. Retrieved 24 March 2013.
  13. "Kazakhstan, consortium agrees to new Kashagan terms". Oil and Gas Journal. Retrieved 24 March 2013.
  14. "Краткая информация по Северо-Каспийскому проекту". KazMunayGas. Retrieved 21 March 2015.
  15. "Eni to share Kashagan operator status with other consortium members". The Telegraph. AFX. 14 January 2008. Retrieved 8 December 2012.
  16. "Change of guard at Kashagan helm". Upstream Online. NHST Media Group. 23 January 2009. Retrieved 30 January 2009.
  17. "Trio tuck in to Kashagan FEED". Upstream Online. NHST Media Group. 21 October 2008. Retrieved 26 October 2008.
  18. 1 2 "ONGC Videsh buys Kashagan entry ticket". Upstream Online. NHST Media Group. 26 November 2012. Retrieved 8 December 2012.
  19. "ONGC gets project operator's nod for $ 5-bn Kashagan stake buy". The Financial Express. 7 December 2012. Retrieved 8 December 2012.
  20. Kazakhs expect 8m tonnes of oil from Kashagan in 2014. Central Asia Online. http://centralasiaonline.com/en_GB/articles/caii/newsbriefs/2013/09/19/newsbrief-11
  21. "ENI cuts production guidance, cites Libya and Nigeria disruptions". Oil Patch Asia. Retrieved 7 January 2014.
  22. Williams, Selina (31 March 2014). "How a Giant Kazakh Oil Project Went Awry". The Wall Street Journal. Retrieved 13 October 2014.
  23. "There is still uncertainty at Kashagan: KazMunaiGas National O&G Company Head". Tengri News. 25 February 2014. Retrieved 13 October 2014.
  24. Pasternack, Alex (17 April 2014). "The World's Most Toxic Money Pit". Motherboard. Retrieved 13 October 2014.
  25. Zempolich, W.; Negri, A.; Leo, C.; Van Ojik, K.; Verdel, A. (10 March 2002). The Kashagan Discovery: An Example of the Successful Use of a Multi-disciplined Approach in Reducing Geologic Risk (PDF). Annual Meeting. Houston, Texas: AAPG. Retrieved 8 December 2012.
  26. Eytchison, Patrick (2003). "The Caspian Oil Myth". Synthesis/Regeneration (32). Retrieved 23 January 2008.
  27. https://www.neweurope.eu/article/long-delays-kashagan-oil-slowly-come-stream/
  28. "Living quarter barge delivered to Kashagan oilfield". Heavy Lift & Project Forwarding International. 4 December 2012. Retrieved 8 December 2012.
  29. http://thediplomat.com/2015/06/kazakhstan-kashagan-hopes-are-up/
  30. Gizitdinov, Nariman (2016-10-14). "Oil From $50 Billion Kashagan Field Starts Flowing to Export". Bloomberg.com. Retrieved 2016-10-14.
  31. "Commercial oil output commences at Kashagan - Minister". inform.kz.
  32. "More Than 350,000 Tonnes of Kashagan Oil Shipped For Export". astanatimes.com.
  33. Diplomat, James Pach, The. "Interview: Victor Robert Lee". The Diplomat. Retrieved 2017-06-03.
  34. Lee, Victor Robert. Performance Anomalies by Lee, Victor Robert (2012) Hardcover. Perimeter Six 2012.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.