Istanbul New Airport
Istanbul New Airport İstanbul Yeni Havalimanı | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Summary | |||||||||||||||||||||||||||||||
Operator | IGA (Istanbul Grand Airport) Havalimanı İşletmesi A.Ş. | ||||||||||||||||||||||||||||||
Serves | Istanbul, Turkey | ||||||||||||||||||||||||||||||
Location | Arnavutköy | ||||||||||||||||||||||||||||||
Opened |
| ||||||||||||||||||||||||||||||
Coordinates | 41°15′39.97″N 28°44′32.54″E / 41.2611028°N 28.7423722°ECoordinates: 41°15′39.97″N 28°44′32.54″E / 41.2611028°N 28.7423722°E | ||||||||||||||||||||||||||||||
Website |
www | ||||||||||||||||||||||||||||||
Map | |||||||||||||||||||||||||||||||
Istanbul New Airport Location of airport in Turkey | |||||||||||||||||||||||||||||||
Runways | |||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||
Statistics | |||||||||||||||||||||||||||||||
|
Istanbul New Airport (Turkish: İstanbul Yeni Havalimanı), or Third Airport (Turkish: Üçüncü Havalimanı),[1] is an international airport under construction in Arnavutköy district on the European side of Istanbul, Turkey.
The airport is planned as the largest airport in the world,[2] with a 150 million passenger annual capacity,[3] and was planned due to lack of capacity in the existing airports of Istanbul.[4] It will be the third international airport to be built in Istanbul after Istanbul Atatürk Airport and Sabiha Gökçen International Airport. Atatürk Airport will be closed down once the new airport is operational.[5] As of July 2017, around 55% of the construction of the airport was completed.[6] The commercial opening of the airport will be October 29, 2018. [7]
Origins of and need for Project
The existing Atatürk Airport, Istanbul's main airport, located on the European side of Istanbul, is surrounded by urban Istanbul and is incapable of cost effective expansion to meet increasing demand. Additionally, there is an increasing problem of air traffic congestion. Atatürk Airport itself became the third busiest airport in Europe in 2015, edging out Frankfurt Airport for the first time. However by 2017, Atatürk Airport fell back on the 5th place behind Frankfurt and Amsterdam.[8]
There is no space to build an additional runway on the Atatürk Airport site, as the airport is within the city of Istanbul. Industrial areas are situated north of the airport, with residential areas to the west and east of it. Because of the limited capacity, the Turkish Airspace Authority does not allow additional cargo or charter flights to the airport. Airlines that want to start new routes or add additional flights cannot do so. Due to lack of slots and parking spaces, some of Turkish Airlines' aircraft are based in Sabiha Gökçen Airport, which is on the Asian side of Istanbul. Sabiha Gökçen Airport itself is already at maximum terminal capacity of 25 million passengers, and handled 28 million passengers in 2015 after posting traffic growth rates averaging over 20% a year since 2013.
In 2014, the two Istanbul airports handled more than 80 million passengers, with almost 90 million passengers in 2015 and 2016.[9] In terms of area airports, the four London-area airports serve around 150 million passengers a year, while the three Paris-area airports serve around 100 million passengers a year.
Location
The new airport is constructed at the intersection of junction roads of Arnavutköy, Göktürk and Çatalca, north of European side of Istanbul between the Black Sea regions of Yeniköy and Akpınar. The construction zone is a 7,659-hectare region near Lake Terkos. Some 6,172 hectares of this area is state-owned forest. The distance between Istanbul New Airport and Atatürk Airport is approx. 35 km (22 mi) as the crow flies. The area encompasses old open-pit coal mines, which are to be filled up with soil.[10] The new airport will be linked by several lines of the Istanbul Metro to Istanbul city centre in 2018, one starting from Gayrettepe station, on the M2 line, an other from Halkalı on the Marmaray rail.[11]
As stated by the Forestry Ministry, a study conducted on the environmental impact of the project and published in April 2013, reports that there are a total of 2,513,341 trees in the area and 657,950 of them will need to be cut indispensably while 1,855,391 trees will be moved to new places.[10]
The project
The tender for construction and plan for up to 17-year contract until 2030 for operation of the facility was held on May 3, 2013.[3] The project is made up of four construction stages. If all stages are completed, the airport could then be the biggest airport of the world with a passenger capacity of 150 million passengers. The first stage of construction is planned to finish within 42 months of the handover of the area. Total project cost is expected to be approximately €7 billion, excluding financing costs. It has guaranteed 342 million passengers for 12 years.
At the bidding session on May 3, 2013, from fifteen Turkish and two foreign companies that were qualified as bidders, only four showed up. The Turkish joint venture consortium of Cengiz-Kolin-Limak-Mapa-Kalyon won the tender for Istanbul's third airport, and were obliged to pay the government €26.142 billion including value-added tax for a 25-year lease starting from 2018. The completion of the construction's first stage was officially set for 2018, 42 months after the finalization of the tender approval.[10]
The Turkish Chamber of Environmental Engineers (ÇMO) has taken the project tender to court on grounds that the project violated the existing legislation for the preparation of the environmental impact assessment report.[10] In February 2014, an Istanbul administrative court ordered suspension of the construction of İstanbul's third airport.[12] However, the groundbreaking ceremony took place a few months later, on 7 June 2014.[13] The construction only started in May 2015 after the official handover of the land.[5]
Project stages
The construction of the airport is set to take place in several stages, expanding the airport and its facilities over time:
First Stage (estimated late 2017)[3]
- A main terminal with a total passenger capacity of 90 million, with an area of 680,000 m2 (7,300,000 sq ft)
- Second terminal building with an area of 170,000 m2 (1,800,000 sq ft)
- 88 aircraft passenger bridges at terminals
- Indoor parking with 12,000 vehicles capacity
- 2 independent runways
- 8 parallel taxiways
- Approximately 4,000,000 m2 (43,000,000 sq ft) of apron space
- 3 technical blocks
- 1 air traffic control tower
- VIP Lounge
- Cargo and general aviation terminals
- Other services including hospitals, prayer rooms, convention centers, hotels etc
Second Stage[3]
- 2 runways
- 1 parallel taxiway
Third Stage[3]
- A terminal with a capacity of 30 million passengers at sea side with an area of 500,000 m2 (5,400,000 sq ft)
- 1 runway
- 1 parallel taxiway
- Apron
Fourth stage[3]
- A terminal with a capacity of 30 million passengers, built in an area of 340,000 m2 (3,700,000 sq ft)
- 1 runway
Upon completion (estimated before 2030)[3]
- 6 runways
- 16 taxiways
- 150 million passengers capacity – extendable to 200 million[14]
- 1,500,000 m2 (16,000,000 sq ft) indoor area
- 165 aircraft passenger bridges at all terminals
- 4 terminal buildings, with rail access between terminals
- 3 technical blocks
- 1 air traffic control tower
- 8 ramp control towers
- A 6,500,000 m2 (70,000,000 sq ft) apron with 500 aircraft parking capacity
- VIP Lounges
- Cargo and general aviation terminals
- State Palace
- Indoor and outdoor parking with a capacity of approx. 70,000 cars
- Aviation medical center
- Aircraft rescue and firefighting stations
- Garage buildings
- Hotels
- Convention centers
- Power plants
- Water treatment and waste facilities
See also
References
- ↑ 3. havalimanı erken bitebilir (Turkish)
- ↑ Limak to construct new terminal at Kuwait International Airport
- 1 2 3 4 5 6 7 "Dünyanın en büyük havalimanı İstanbul'a yapılıyor". Star. 2013-01-24. Retrieved 2013-01-24.
- ↑ "TAMAMLANDIĞINDA DÜNYANIN EN BÜYÜĞÜ OLACAK…(23.01.2013 – 15.03.2013)". dhmi.gov.tr. 2013-01-24. Retrieved 2013-01-24.
- 1 2 "Construction of new Istanbul airport officially starts under shadow of challenges, questions". 18 July 2015. Retrieved 21 July 2015.
- ↑ "Istanbul Airport City to make world premiere at top real estate fair in Cannes". Daily Sabah. Retrieved 2016-11-30.
- ↑ "Istanbul Airport City to make world premiere". Daily Sabah. Retrieved 2016-11-30.
- ↑ Weiss, Richard (2017-01-13). "‘Full’ Heathrow Extends European Hub Lead as Terror Hurts Rivals". Bloomberg Business. Retrieved 2017-01-15.
- ↑ "Turkish Airport Traffic Statistics". DHMI Turkey. Retrieved 18 March 2016.
- 1 2 3 4 "Consortium wins Istanbul airport tender for 22.1 billion euros". Hürriyet Daily News. 2013-05-03. Retrieved 2013-05-03.
- ↑ "Turkey to build new metro lines for the third airport in Istanbul". Railway Pro. Retrieved 2017-03-29.
- ↑ "İstanbul court orders suspension of 3rd airport's construction". Today's Zaman. 2014-02-10. Archived from the original on 2014-02-26. Retrieved 2014-06-08.
- ↑ Grundsteinlegung für Mega-Flughafen in Istanbul. welt.de, 7. Juni 2014; retrieved, 8 June 2014
- ↑ Ay, Hasan. "Havalimanı değil zafer anıtı". sabah.com.tr. Sabah. Retrieved 8 June 2014.