Line 5 Eglinton
Line 5 Eglinton | |
---|---|
Promotional logo of the construction project | |
Overview | |
Type | Light rail |
Status | Under construction |
Locale | Toronto, Ontario, Canada |
Termini |
Mount Dennis Kennedy |
Stations | 25 (phase 1), 61 (phase 2) |
Operation | |
Planned opening | September 2021[1] |
Owner | Metrolinx |
Operator(s) | Toronto Transit Commission[2] |
Depot(s) | Black Creek Carhouse |
Rolling stock | Flexity Freedom (planned) / Citadis Spirit (backup)[3] |
Technical | |
Line length | 19 km (12 mi) |
Track gauge | 1,435 mm (4 ft 8 1⁄2 in) standard gauge |
Electrification | 750 V DC overhead [4] |
Operating speed | 80 km/h (50 mph) |
Line 5 Eglinton, known during construction and planning as the Eglinton Crosstown Line, is a light rail line that is under construction in Toronto, Ontario, Canada. Owned by Metrolinx and operated by the Toronto Transit Commission (TTC), the line will be part of the Toronto subway system as its fifth route. The first constructed phase of line will run entirely along Eglinton Avenue for 19 km (12 mi) from the future Mount Dennis station underground to Sunnybrook Park, after which it will run predominantly at-grade along the street's median to Kennedy station, where it will connect underground with Line 2 Bloor–Danforth and Line 3 Scarborough.[4]
The line was conceived in 2007 by then-Toronto mayor David Miller and then-chair of the TTC Adam Giambrone as part of Transit City, a large-scale transit expansion plan. The first phase of the line is expected to be completed in 2021.[5] Additional extensions to the line in both directions, with proposed termini at Toronto Pearson International Airport in the west and the University of Toronto Scarborough in the east, were approved by Toronto City Council on March 31, 2016.[6] The line will include up to 25 stations upon opening in 2021, and an addition of 36 new stations beyond 2021 (61 total stations), which will make it the longest in Toronto with an estimated 100 million trips annually in 2031.[7]
History
Original concept
The Eglinton Crosstown Line was conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 by Toronto Mayor David Miller and TTC chair Adam Giambrone. It was part of the Transit City plan, which included the implementation of six other light rail lines across Toronto. The original version of the line would have run from Pearson Airport along Silver Dart Drive to Convair Drive. The line would have then turned southwest, to a bridge over Highway 401 to reach Commerce Boulevard on the other side, where it would run south to reach Eglinton Avenue and the east end of the Mississauga Transitway. The rest of the line would run east along Eglinton Avenue, including a portion along which the proposed Eglinton West subway line would have been built. The line would then traverse the city, connecting with the Yonge-University and Bloor-Danforth subways, and with the Scarborough RT.
There were 43 stops planned for the Eglinton Crosstown LRT, 13 of which would be underground.[8] Surface stops would be spaced on average 500 metres (550 yd) apart and the underground stations would be 850 m apart on average, as constructing numerous underground stops would be costly. The average speed would be 28 kilometres per hour (17 mph),[9] compared with the existing bus routes along Eglinton that have an average speed of 16 to 18 km/h (9.9 to 11.2 mph).[10] The line would terminate at Kennedy Station to the east in Scarborough where it would meet Line 2 Bloor–Danforth, the proposed Scarborough Malvern LRT and the Stouffville GO train line. The expected cost was $4.6 billion.[11] As a result of provincial funding cuts, construction of the line was divided into two phases: Phase One would end at Jane Street, and Phase Two would terminate as had been planned at Pearson Airport.
Ford era redesigns
Miller's successor, Rob Ford, announced the cancellation of Transit City on December 1, 2010, the day he took office.[12] He proposed an alternative titled the "Eglinton–Scarborough Crosstown line", which put the 19-kilometre line along Eglinton Avenue completely underground. The line would then follow new route of the Scarborough RT, thus forming a single line continuously from Black Creek Drive to McCowan. The cost would almost double to $8.2 billion and, compared to the original plan, 18 fewer stops were planned, including the elimination of the connection to Pearson Airport. Most of the additional cost would have come from putting 12 additional stations underground and for converting the Scarborough RT.
On February 8, 2012, in a special meeting, Toronto City Council, led by Karen Stintz, voted 25–18 to override Mayor Ford's modifications to the project.[13] The vote reinstated the original proposal to only construct the portion between Laird Drive and Keele Street underground while the remainder of the line is built along the surface.[13] On November 30, 2012, the environmental assessment was revised, such that the east tunnel portal location would be moved from east of Brentcliffe to east of Don Mills;[14] however, this was reversed in May 2013 after receiving community feedback.[15] In January 2013, Toronto City Councillors from Scarborough put forward an alternative plan to proceed with the construction of the Eglinton Avenue portion of the line as planned, but to exclude the Scarborough RT from the line. In July 2013, plans for an "Eglinton-Scarborough Crosstown" line were abandoned, thereby reverting the entire line back to the plan that had been conceived under Transit City.[16][17]
Extensions
Under Mayor John Tory, Toronto city council approved two extensions for the Eglinton Crosstown to the east and west on March 31, 2016.[6] These extensions may be subject to further optimization such as additional grade separations and fewer stops.[18]
Crosstown West
Crosstown West | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
In a later phase, Metrolinx had planned for the Eglinton Crosstown to be extended westward from Mount Dennis along Eglinton Avenue West to Toronto Pearson International Airport. However, during the 2014 Toronto mayoral election, John Tory proposed SmartTrack, which would have included a heavy rail transit line established along this section of Eglinton Avenue.[19][20] In 2016, the City of Toronto released a feasibility report that found this proposal would have significant capital costs ranging from $3.6 billion to $7.7 billion. In comparison, extending the Eglinton Crosstown as approved would cost $1.3 billion. It was also found that a light rail transit line had higher ridership than a heavy rail line.[18]
The City of Toronto's Chief Planner recommended the extension of the Eglinton Crosstown line (referred to as Crosstown West) to Pearson Airport in lieu of establishing SmartTrack on Eglinton Avenue, based upon negative community impacts, higher costs, and lower projected ridership associated with a heavy rail corridor.[18] On January 19, 2016, Tory agreed with the analysis and supported Metrolinx's original plan of extending the Crosstown.[21] Tory has included the Crosstown West as a light-rail component of his SmartTrack plan.[22]
The estimated completion is 2023 as of July 2016.[23] The estimated cost to build the Eglinton West LRT is $2.47 billion of which the City of Toronto contributes $1.18 billion, the federal government contributes $822.9 million, and the City of Mississauga and the Greater Toronto Airports Authority would be asked to contribute $470 million for the portion of the line in Mississauga. Approvals for the financing were still to be secured as of November 2, 2016.[24]
Crosstown East
Crosstown East | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
As part of the planned extension of Line 2 Bloor–Danforth, the City of Toronto drafted a plan to extend the Eglinton Crosstown east into Scarborough, which would terminate at the University of Toronto Scarborough campus.[25]
The 12-kilometre (7.5 mi) extension would connect with Eglinton GO Station and Guildwood GO Station and pass through “neighbourhood improvement areas” (often low-income areas) such as Eglinton East, Scarborough Junction, Morningside, Scarborough Village and West Hill.[26] The extension would add 18 new stops east of Kennedy Station and serve an estimated 43,400 additional riders per day (a ridership similar to that of Line 4 Sheppard subway).[27]
The extension follows the alignment of the Scarborough Malvern LRT, which was proposed as part of Transit City.[28] In 2010, the Scarborough Malvern LRT was cancelled by then-Mayor Rob Ford, despite being approved by Toronto City Council and the Government of Ontario in 2009.[29][30]
In early 2016, the plan for the Scarborough Malvern LRT was revived and rebranded as "Crosstown East".[26] As of July 2016, the project was unfunded with the cost estimated at $1.6-billion to $1.7-billion, with an estimated completion date of 2023.[22]
Construction and implementation
The Eglinton Crosstown line will run underground for 10 km (6.2 mi) from Mount Dennis to just east of Brentcliffe Road before rising to the surface to continue another 9 km (5.6 mi) to end at Kennedy Station.[31] A short portion of the line across the Black Creek valley will be elevated, between Mount Dennis and Keelesdale stations.
Timeline
- 2010
On July 28, 2010, Metrolinx ordered four tunnel boring machines (TBMs) from Caterpillar at a cost of $54 million.[32] Each TBM is 10 metres long, 6.5 metres in diameter and weighs 400 tons. They bore 10 metres per day, 16-20 metres below the surface.[33] The TBMs were named Dennis, Lea, Humber, and Don. The names were chosen by Jason Paris, a moderator of the UrbanToronto blog and forums. Dennis is named after Mount Dennis, Lea is named after Leaside, Humber is named after the Humber River, and Don is named after the Don River. The names Dennis and Lea combined allude to the poet Dennis Lee.[34][35] By the time all four machines reach Yonge Street, enough dirt will have been removed to fill the Air Canada Centre to the height of the CN Tower.[36]
- 2011
In October 2011, the first part of tunnel construction began with the construction of a launch shaft for tunnel boring machines (TBMs) at Black Creek Drive.
On November 9, 2011, in Keelesdale Park, Mayor Rob Ford and then-Premier Dalton McGuinty officially broke ground on the new project.[37]
- 2012
In May 2012, TTC staff released a report saying that completion of the Eglinton Crosstown was unlikely by 2020 and that a more realistic in-service date would be 2022–2023. The main reason given was that the project management had been transferred from the TTC to Infrastructure Ontario which uses the Alternative Finance and Procurement strategy. That strategy would use a private contractor to complete the project, effectively requiring that contractor to redo all design work already completed by the TTC.[38] The TTC also warned that Metrolinx’s aggressive timeline would lead to severe construction-related disruptions to communities and traffic because large stretches of the Eglinton Avenue would have to be torn up concurrently to meet deadlines.[1]
- 2013
In January 2013, Infrastructure Ontario issued a request for qualifications to shortlist companies to construct the line. A request for proposal was expected in the summer of 2013.[39]
On February 22, 2013, TBMs Don and Lea arrived in Keelesdale Park.[40]
In June 2013, the TBMs Don and Lea began tunnelling on the line. Traffic on Eglinton Avenue near Keele Street was reduced to one lane in each direction.[41]
On November 12, 2013, MetroLinx awarded a contract to construct the eastern portion of the Crosstown to a joint venture between Aecon Group Inc. and ACS Dragados Canada Inc. to construct the eastern portion of the line between Yonge Street and Laird Drive.[42]
- 2014
In March 2014, work began to clear utilities and trees on the south side of Eglinton Avenue just east of Brentcliffe Road in order to set up the eastern launch shaft. For two and a half years, traffic around the excavation site will be reduced from two to one lane in each direction. West of the site, more lane restrictions will go into effect to construct head walls (below-ground walls that form the ends of each subway station) at the future Laird, Bayview and Mt. Pleasant stations. There will also be lane restrictions for two years near Hanna Road to build an emergency exit near Leaside High School.[36]
By April 2014, the TBMs had arrived at Caledonia station.[43] In April 2014, The Globe and Mail reported that the two western tunnel boring machines were excavating "approximately 1,000 cubic yards of spoil", per day.[44]
For the year prior to May 2014, the two TBMs Dennis and Lea had been excavating and installing concrete tunnel liners at a rate of approximately 10 metres (33 ft) per day.[45] The tunnels are lined with precast concrete liner segments. Six 2.5 tonne-segments form each ring.
In early December 2014, Dennis and Lea arrived at Eglinton West station.[46] Dennis stopped to allow Lea to catch up, so that they would arrive at Eglinton West station at the same time.
- 2015
On the weekend of April 18–19, 2015, the boring machines, Dennis and Lea, were lifted out of a shaft west of Allen Road and moved about 100 metres to a shaft just east of Allen Road.[47]
In April 2015, merchants along Eglinton Avenue West were complaining of lost revenue (up to a 35% dip in sales), because construction was discouraging customers with snarled traffic, limited parking options, reduced foot traffic and dusty sidewalks.[48]
By September 2015, the TBMs Don and Humber arrived for assembly in the shaft at Brentcliffe Road before starting to drill the 3.25-kilometre (2.02 mi) section west to Yonge Street.[1][36]
On September 24, 2015, Transportation Minister Steven Del Duca issued a statement saying the Crosstown would not operate until September 2021, in order “to mitigate disruption to the local community and infrastructure as much as possible.” The earlier plan had been to open in 2020 with tunnelling and station construction to start in 2012.[49] Infrastructure Ontario has awarded the Crosstown construction contract to Crosslinx, a consortium led by SNC Lavalin. It will take about four years to build the stations, 15 of which will be underground.[1]
On September 29, 2015, TBM Don started to bore the north tunnel from the Brentcliffe Road launching site westward towards Yonge Street. TBM Humber will start boring the south tunnel approximately one month later.[50]
On November 3, 2015, Del Duca announced that the contract awarded to Crosslinx Transit Solutions to complete the Crosstown and maintain it for 30 years will cost $2 billion less than originally estimated.[51]
- 2016
On March 10, 2016, a ground-breaking ceremony was held at the site of Keelesdale station, the first station to be started for construction along the Eglinton Crosstown line.[52]
In February 2016, work began on the extraction shaft for TBMs Humber and Don, which are digging the eastern segment of the line.[53] However, the hole in the street there will be much smaller than the one near Leslie Street.[36]
On April 18, 2016, the façade of the former House of Chan restaurant and the scaffolding to hold it up collapsed, injuring seven people. That location will be used for Forest Hill LRT station.
On May 10, TBMs Dennis and Lea, which had been boring the western segment of the line, completed their work by reaching Yonge Street.[54] Dennis and Lea bored 6.4 kilometres installing 25,647 precast concrete tunnel segments to construct the 4,279 rings to line the twin tunnels.[33]
On August 17, TBMs Don and Humber, which had been boring the eastern segment of the line, completed their work by reaching Yonge Street. Don and Humber bored 3.3 kilometres installing 26,178 precast concrete tunnel segments to construct the 4,363 rings to line the twin tunnels.[33]
On September 1, Bombardier Transportation, which is producing cars for the line, failed to meet the delivery deadline for the pilot vehicle.[55][56] As a result, Metrolinx filed notice to terminate the contract with Bombardier.
On November 3, 2016, Metrolinx file an "notice of intention" to cancel its contract with Bombardier for the Crosstown's rolling stock.[55][56][57]
- 2017
On February 10, 2017, Bombardier filed an injunction, seeking to compel Metrolinx to stick with their contract.[56][57][58] Metrolinx responded that Bombardier did deliver a prototype for testing, as required by the contract. However, Metrolinx claimed that the prototype was so incomplete that it would not power up.[59]
Between March 13 and 17, the TBMs Don and Humber were removed in pieces from the extraction shaft on Eglinton Avenue just east of Yonge Street.[60][61]
In July 2017, construction crews began preparation for constructing the eastern at-grade portion of the line[62] by removing the median in the roadway.[63]
On August 9, the first piece of track, a turnout, was installed at the Eglinton Maintenance and Storage Facility in Mount Dennis. The facility is scheduled for completion in 2018.[63]
- 2021
Metrolinx expects the line to be completed.[64]
Crosslinx
Crosslinx Transit Solutions, a consortium of more than 26 companies, was awarded the contract to design, build and finance the Eglinton Crosstown line and to maintain it for 30 years. The contract, which excludes boring the tunnels, is for completing all other remaining work, including the stations and the finishing work within the tunnels. Some of the members of the consortium are SNC-Lavalin, Aecon, EllisDon, ACS Infrastructure Canada, Dragados, IBI Group and the Bank of Nova Scotia. The contract defines a public–private partnership.[51][65]
The 30-year contract to build and maintain the line will total $9.1 billion. Capital costs will be $5.3 billion, with each of the 15 underground stations costing $80–$100 million to build and the ten street-level stops $3-$5 million each. The remainder will be for financing, lifecycle and maintenance costs.[51]
Route
Stations
The following is the list of stops proposed as of 2013.[66] Metrolinx is proposing changes to the names of seven of the line’s stops.[67] In a report to the TTC Board on November 23, 2015, it was recommended that stations on Line 5 Eglinton LRT should be given unique names.[68]
Stop | Type | Notes |
---|---|---|
Mount Dennis | At grade | Connection to Kitchener line, Union Pearson Express |
Keelesdale | Underground | Originally called Keele. |
Caledonia | Underground | Connection to Barrie line |
Fairbank | Underground | Originally called Dufferin. |
Oakwood | Underground | |
Cedarvale (Eglinton West) | Underground | Connection to Line 1 (University segment) at the current Eglinton West station. The station is to be renamed Cedarvale upon opening of the Eglinton Crosstown.[69] |
Forest Hill | Underground | Originally called Bathurst. |
Chaplin | Underground | |
Avenue | Underground | Oriole Park was once considered, but then rejected, as the station name. |
Eglinton | Underground | Connection to Line 1 (Yonge segment) |
Mount Pleasant | Underground | |
Leaside | Underground | Originally called Bayview. |
Laird | Underground | Easternmost station of the underground central section. |
Sunnybrook Park | At grade | Westernmost of the at grade stops. Side platforms east of Leslie Street.[70] Originally called Leslie. |
Science Centre | Underground | Originally called Don Mills. |
Aga Khan Park & Museum | At grade | Side platforms west of Don Valley Parkway.[71] Originally called Ferrand. |
Wynford | At grade | Side platforms on opposite sides of a new pedestrian crosswalk, which will cross Eglinton west of the bridge over Wynford Drive.[72] GO Transit's Richmond Hill line crosses under Eglinton a short distance to the east, but no contingency has been made for a connection. |
Sloane | At grade | Centre platform east of Bermondsey Road/Sloane Avenue.[73] Originally called Bermondsey. |
O'Connor | At grade | Side platforms east from Victoria Park Avenue to O'Connor Drive.[74] Originally called Victoria Park. |
Pharmacy | At grade | Side platforms east of Pharmacy Avenue.[75] |
Hakimi Lebovic | At grade | Side platforms on opposite sides of Lebovic Avenue/Hakimi Avenue.[76] Originally called Lebovic. |
Golden Mile | At grade | Side platforms on opposite sides of Warden Avenue.[77] Originally called Warden. |
Birchmount | At grade | Side platforms east of Birchmount Road.[78] |
Ionview | At grade | Side platforms west of Ionview Road.[79] |
Kennedy | Underground | Connection to Bloor–Danforth and Kennedy GO Station for Stouffville line |
Operations
Operating characteristics of the line include:
- Usage of automatic train control on the underground section of Eglinton Crosstown.[80]
- On the surface, usage of dedicated right-of-way transit lanes separate from regular traffic[9] and usage of priority signalling at intersections to ensure certainty in travel times.[9]
- Light rail vehicles and subways can both travel as fast as 80 kilometres per hour (50 mph). However, actual speed is determined by the spacing of the stops and the dwell times between stops. Crosstown vehicles will have an average speed of 28 kilometres per hour (17 mph). As a comparison, the average speed of the subway Line 2 Bloor–Danforth is 32 kilometres per hour (20 mph).[81]
- The projected ridership of the line is 5,400 passengers per hour in the peak direction by 2031, but the capacity of the vehicles is 15,000 passengers per hour per direction.[9]
- The Presto card will be available for use across the line.
- Metrolinx requires 76 Flexity Freedom LRVs to operate the line.[82]
- After feeling unsure if the Bombardier vehicle order could be relied upon for timely delivery, Metrolinx made a contingency order with Alstom for 61 Citadis Spirit vehicles, of which 44 would be for Line 5 and the remaining 17 for the Finch West LRT. Should the Flexity order arrive after all, surplus Alstom vehicles will be used on other Metrolinx projects (most likely the Hurontario LRT).[83][84]
- Annual operating and maintenance costs are estimated to be $80 million upon opening of the line. However, fare revenue and the costs saved by eliminating Eglinton bus service would result in a net annual cost of $39 million.[85]
- There will a total of 12 turnbacks along the line to reverse LRT trains - seven at underground stations and five on the surface section. Avenue Station and Laird Station will be turnback stations that also have a storage track that trains can enter and exit in either direction. The storage tracks will accommodate a train in case of an emergency or change in service as well as allowing for a change of direction.[62]
Eglinton LRT Carhouse
A maintenance and storage facility will be required, and this is planned. The Eglinton LRT Carhouse will have storage for 162 Flexity Freedom LRT vehicles and have extensive maintenance facilities to keep them running smoothly.[86] The carhouse is planned to be built near the line's western terminus at Mount Dennis LRT station, on lands formerly occupied by Kodak's Toronto campus.[87][88][89][90][91]
See also
- Finch West LRT
- Sheppard East LRT
- Hurontario LRT
- B-Line (Hamilton)
- Ion rapid transit
- Stadtbahn
- Light rail in Canada
- Toronto streetcar system
- Toronto subway
References
- 1 2 3 4 Tess Kalinowski (September 24, 2015). "Eglinton Crosstown to open a year later than expected". Toronto Star. Retrieved September 24, 2015.
- ↑ Consiglio, Alex (October 3, 2012). "TTC to operate city’s new LRT lines". Toronto Star. Retrieved November 1, 2012.
- ↑ Spurr, Ben (May 12, 2017). "Province had no choice but to seek Bombardier substitute for Eglinton LRT: Del Duca". Toronto Star. Retrieved May 12, 2017.
- 1 2 "Eglinton LRT 2012 update" (PDF). Metrolinx. February 2012. Retrieved November 1, 2013.
- ↑ "FAQs". Eglinton Crosstown: The Project. Metrolinx. Retrieved February 12, 2017.
Q: What is the timeline for the project? A:The project will be complete in 2021
- 1 2 City Council considerations for March 31, 2016 - Developing Toronto's Transit Network Plan: Phase 1
- ↑ "Eglinton-Scarborough Crosstown Update" (pdf). Metrolinx. June 23, 2011.
- ↑ "Eglinton Crosstown Light Rail Transit stops and stations" (PDF). City of Toronto. November 2010. Retrieved July 30, 2011.
- 1 2 3 4 "Eglinton Crosstown Backgrounder". Metrolinx. Retrieved November 8, 2013.
- ↑ Spears, John (August 9, 2008). "Distance between LRT stops criticized". Toronto Star. Retrieved August 14, 2008.
- ↑ "Eglinton Transit City line may survive". CBC News. January 4, 2011. Retrieved April 24, 2011.
- ↑ D'Cruz, Andrew (December 1, 2010). "Mayor Rob Ford: "Transit City is over"". Toronto Life. Retrieved August 4, 2014.
- 1 2 Kalinowski, Tess; Dale, Daniel (February 9, 2012). "Special transit meeting: Mayor Rob Ford dismisses council’s vote against his subway plan". Toronto Star. Toronto. Archived from the original on September 9, 2012.
- ↑ http://thecrosstown.ca/news-media/whats-new/Online-Consultation-Laird-Don-Valley
- ↑ Kalinowski, Tess (May 12, 2013). "Metrolinx puts Leslie back on the Crosstown map". Toronto Star. Retrieved November 8, 2013.
- ↑ Kalinowski, Tess (May 6, 2013). "Scarborough councillors seek subway line instead of LRT: A group of Toronto councillors wants to replace the planned LRT for Scarborough with a subway. But a subway would cost $500 million more". Toronto Star. Archived from the original on July 3, 2013. Retrieved July 3, 2013.
An LRT would use the same route as the SRT. It would be 9.9 km versus 7.6 km of subway. The LRT would have seven stations, the subway, only three.
- ↑ Kalinowski, Tess (January 17, 2013). "TTC report threatens to reopen Scarborough subway debate: One commissioner says it's proof Scarborough can have a new subway line under construction within the decade, but Metrolinx dismisses that". Toronto Star. Archived from the original on July 3, 2013. Retrieved July 3, 2013.
Glenn DeBaeremaeker (Ward 38, Scarborough Centre) said the latest TTC report gives him new confidence that there will be a subway underway in Scarborough within a decade.
- 1 2 3 Jennifer Keesmaat (January 18, 2016). "SmartTrack Western Corridor Feasibility Review" (pdf). City of Toronto. Retrieved February 12, 2017.
The feasibility review examined heavy rail corridor options from several perspectives: technical requirements for heavy rail, service concept and integration with RER, regulatory requirements for heavy rail, land use compatibility and impacts, and cost.
- ↑ Steve Munro (September 16, 2014). "John Tory’s "SmartTrack": Will That Train Ever Leave The Station?". Steve Munro.
- ↑ Steve Munro (October 17, 2014). "SmartTrack: That Pesky Curve in Mount Dennis". Steve Munro.
- ↑ "SmartTrack still on track despite changing plan, Mayor Tory says". Toronto Star. January 19, 2016.
- 1 2 Moore, Oliver (July 13, 2016). "Toronto City Council approves planning for raft of transit projects". The Globe and Mail. Retrieved July 14, 2016.
- ↑ Ben Spurr; Jennifer Pagliaro (June 26, 2016). "Mayor John Tory’s transit priorities face financial, political challenge: analysis". Toronto Star. Retrieved July 20, 2016.
- ↑ San Grewal (November 2, 2016). "Mississauga fumes over $470 million Toronto LRT funding assumption". Toronto Star. Retrieved November 2, 2016.
- ↑ New proposal for Scarborough subway plan includes fewer stops
- 1 2 Jennifer Pagliaro; Tess Kalinowski (January 16, 2016). "New Scarborough transit plan ‘buys peace in the land’". Toronto Star. Retrieved January 20, 2016.
- ↑ Edward Keenan (June 2, 2016). "Priority should be alternative transit routes into downtown: Keenan". Toronto Star. Retrieved June 5, 2016.
- ↑ "Scarborough Malvern Light Rail Transit (LRT): Notice of Completion of the Environmental Project Report" (PDF). City of Toronto. October 16, 2009. Retrieved February 12, 2017.
The Toronto Transit Commission (TTC) and the City of Toronto have completed an Environmental Project Report (EPR) for the fifteen kilometre Scarborough Malvern Light Rail Transit (LRT) which would connect Kennedy Subway Station with north-eastern Scarborough.
- ↑ "Request for Approval of the Scarborough-Malvern LRT Environmental Assessment Study - City Council Decision". City Of Toronto. September 30, 2009. Retrieved February 12, 2017.
City Council approve the recommendations of the Scarborough-Malvern LRT Transit Project Assessment Study and authorize submission of the Environmental Project Report (EPR) to the Ministry of the Environment.
- ↑ "Minister's Notice to Proceed" (PDF). Ontario Ministry of Transportation. December 15, 2009. Retrieved February 12, 2017.
- ↑ "City of Toronto: Get Involved > Eglinton Crosstown Light Rail Transit (LRT) > Frequently Asked Questions > Stations and Stops". City of Toronto. August 20, 2011. Retrieved October 24, 2011.
- ↑ Kalinowski, Tess (July 28, 2010). "Metrolinx orders tunneling machines". Toronto Star.
- 1 2 3 Daniel McKenzie (August 17, 2016). "Big dig wraps for Eglinton Crosstown LRT". Toronto Sun. Retrieved August 18, 2016.
- ↑ "Announcing the winning names of the Tunnel Boring Machine Naming Contest...". Metrolinx. June 5, 2013. Retrieved February 12, 2017.
The most popular set of names were shortlisted and voted on by the public. Thank you to Jason Paris (Dennis and Lea), Graham Gersdorff, Val Dodge and Reiner Kravis (Don and Humber) of Toronto for submitting the winning names!
- ↑ Brandon Leal (June 5, 2013). "Eglinton Crosstown TBMs get a Personality and a Send-Off". Urban Toronto. Retrieved February 12, 2017.
In October 2012 Metrolinx announced a near month long contest public contest to name the tunnel boring machines (TBM).
- 1 2 3 4 Winsa, Patty (March 21, 2014). "Metrolinx begins its big eastern dig on the Eglinton Crosstown LRT: Get ready for traffic". Toronto Star. Archived from the original on March 23, 2014.
Parts for the next two tunnel-boring machines to work on digging underground parts of the line — nicknamed Don and Humber — will arrive this summer and be assembled in the shaft, before they start drilling the 3.25-kilometre section west to Yonge St.
- ↑ Alcoba, Natalie (November 9, 2011). "Ford, McGuinty get up-close look at Eglinton LRT construction". National Post. Retrieved August 4, 2014.
- ↑ Chu, Showwei (May 29, 2012). "Eglinton LRT unlikely to meet 2020 completion date: TTC report". Citytv News. Toronto. Archived from the original on September 9, 2012.
- ↑ "Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines". Infrastructure Ontario. January 22, 2013. Retrieved March 10, 2013.
- ↑ Kalinowski, Tess (February 22, 2013). "Eglinton Crosstown LRT tunneling a step closer". Toronto Star. Toronto Star Newspapers Ltd. Retrieved August 4, 2014.
- ↑ "Machines begin tunnelling for Eglinton Crosstown LRT". CBC News. June 5, 2013. Retrieved July 5, 2013.
- ↑ Jack Landau (November 12, 2013). "Metrolinx Awards Contract for Crosstown LRT East Tunnel Section". Urban Toronto. Archived from the original on September 3, 2014. Retrieved October 12, 2014.
As tunnel boring machines continue to etch their path eastbound underneath Eglinton Avenue from Keele Street for the western leg of the Eglinton Crosstown LRT project, a winning bidder has been announced for the eastern section of tunnel, which will run from Brentciffe Road to Yonge Street, starting just east of the easternmost underground station at Laird Drive.
- ↑ Tim Alamenciak (April 30, 2014). "Eglinton Crosstown LRT back on schedule, engineer says". Toronto Star. Archived from the original on August 3, 2014. Retrieved January 22, 2015.
“It’s a seemingly simple process that’s actually very high tech,” said Kramer. The first of the two tunneling machines (dubbed Dennis) entered the ground June of 2013 and has made it to Caledonia Rd. from its starting point at Black Creek Dr. The other machine, Lea, is just behind.
- ↑ Oliver Moore (April 29, 2014). "Underground for now, construction proceeds on Eglinton LRT". The Globe and Mail. Archived from the original on December 21, 2014. Retrieved January 22, 2015.
Headwalls that will form the box of the stations have been installed at Keele Street and Caledonia Road, and work is under way on one at Dufferin Street. The TBMs go right through headwalls after they have been built, in order to ensure a tight seal, and the two at work in this area are now on either side of what will eventually be the Caledonia LRT station.
- ↑ Rahul Gupta (May 9, 2014). "Eglinton LRT: Construction activity well underway on both sides of Allen Road". Inside Toronto. Archived from the original on January 23, 2015. Retrieved January 22, 2015.
Digging 50 feet below street level, the 81-metre long TBMs nicknamed Dennis and Lea are located in the vicinity of Caledonia Road, one of 12 underground Crosstown stations planned for the route. They are expected to reach the Allen later this year, when they will be redeployed beyond Eglinton West subway station to continue the dig east towards Yonge Street.
- ↑ Eglinton Crosstown TBM Tracker
- ↑ Olivia Carville (April 19, 2015). "An exciting glimpse at boring machines on Eglinton". Toronto Star.
- ↑ Lauren Pelley (April 19, 2015). "Eglinton businesses feeling sting of Crosstown construction". Toronto Star.
- ↑ Collins, Jack (May 19, 2010). "Achieving 5 in 10 - A Revised Plan for the Big 5 Transit Projects" (PDF). Metrolinx. Retrieved September 27, 2015.
Complete and in-service by 2020
- ↑ "Launch of tunnel boring machines and tunnelling work in the east". Metrolinx. October 1, 2015. Retrieved October 13, 2015.
- 1 2 3 Tess Kalinowski (November 3, 2015). "$9.1B Crosstown LRT mega-contract comes in under estimates". Toronto Star. Retrieved November 3, 2015.
- ↑ "Crews break ground on 1st of 25 Eglinton Crosstown stations". CBC News. March 10, 2016. Retrieved March 22, 2016.
- ↑ "Temporary Closure of Holly Street at Eglinton Avenue East". Metrolinx. February 24, 2016. Retrieved February 12, 2017.
The extraction shaft is required to be completed in advance of receiving the two TBMs (Don and Humber), which are currently tunnelling westward from their start-point, just east of Brentcliffe Road.
- ↑ "Crosstown Tunnelling Reaches Yonge Street". Ontario Ministry of Transportation. May 10, 2016. Retrieved February 12, 2017.
Today Tunnel Boring Machines (TBMs) Dennis and Lea, boring the western segment tunnels, arrived at Yonge Street having travelled 6,419 metres from where they started at Black Creek Drive in spring 2013.
- 1 2 Ben Spurr (November 3, 2016). "Metrolinx says it intends to cancel Bombardier LRV contract". Toronto Star. Retrieved February 12, 2017.
The ministry of transportation confirmed to the Star on Thursday that Metrolinx, the provincial transit agency, has issued a formal notice of intent to terminate its $770-million contract for up to 182 Bombardier LRVs.
- 1 2 3 Shaun Jeff (February 10, 2017). "Bombardier taking Metrolinx to court over threats to scrap light-rail vehicle deal". Toronto Sun. Retrieved February 12, 2017.
Bombardier filed an injunction Friday with Ontario’s Superior Court in response to what the company calls “unjustified threats” to kill a $770-million contract signed in 2010.
- 1 2 Ben Spurr (February 10, 2017). "Bombardier taking Metrolinx to court". Toronto Star. Retrieved February 12, 2017.
Bombardier’s legal gambit comes three months after Metrolinx issued the company a notice of intention to cancel its contract for up to 182 light rail vehicles.
- ↑ "Transport minister fires back at Bombardier for court injunction against Metrolinx". CBC News. February 10, 2017. Retrieved February 12, 2017.
In a statement, Bombardier says the goal of the injunction application is to encourage Metrolinx to 'resume good faith discussions.'
- ↑ Oliver Moore (February 14, 2017). "Metrolinx rejects Bombardier’s claims of laxity in wake of court filing". The Globe and Mail. Retrieved February 15, 2017.
A senior person at Bombardier familiar with the process says the company had to go to court after months of behind-the-scenes talks with Metrolinx hit an impasse.
- ↑ "Join us March 13 to say farewell to the Crosstown’s TBM". Metrolinx. October 3, 2017. Retrieved March 13, 2017.
Metrolinx invites you to join us throughout the week of March 13, 2017 to watch the pieces of being lifted and transported offsite. We will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber. The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four oversized sections over four days. ... Each piece will be lifted from the extraction shaft in the morning, and placed on the ground within the construction zone. Later, after 9 p.m. that night, the piece will be loaded onto a large truck and hauled away. TBM Don, the machine that bored the north tunnel, will be removed first.
- ↑ Dolski, Megan (March 13, 2017). "Work starts on stations, tracks for Eglinton-Crosstown LRT". Toronto Star. Retrieved March 14, 2017.
- 1 2 "Eglinton Crosstown LRT Updates - July 2017". Metrolinx. July 14, 2017. Retrieved July 14, 2017.
- 1 2 "Eglinton Crosstown LRT Updates - August 2017". Metrolinx. August 11, 2017. Retrieved August 11, 2017.
- ↑ "Eglinton Crosstown > Project > FAQs". thecrosstown.ca. Metrolinx. Retrieved March 13, 2017.
- ↑ Oliver Moore (November 3, 2015). "Ontario government shaves $2-billion off Eglinton Crosstown LRT price tag". The Globe and Mail. Retrieved November 3, 2015.
- ↑ "Stations and Stops". Metrolinx. Retrieved November 17, 2013.
- ↑ "Eglinton Crosstown Line Station and Stop Names". Metrolinx. October 2, 2015. Retrieved October 2, 2015.
- ↑ "Line 5 Eglinton Station Names" (PDF). Board Presentation. Toronto Transit Commission. November 23, 2015. Retrieved November 23, 2015.
TTC staff evaluated the initial report and the proposed names and provided feedback and recommendations. A primary TTC concern was to avoid replication and redundancy with existing TTC station names. The proposed names are unique and are not likely to be confused with existing station names.
- ↑ Kalinowski, Tess (November 24, 2015). "Eglinton West station to become ‘Cedarvale’ because of Crosstown LRT". Toronto Star. Retrieved November 24, 2015.
- ↑ "Leslie Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Ferrand Stop". Eglinton Crosstown. January 14, 2016. Retrieved October 22, 2016.
- ↑ "Wynford Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Bermondsey Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Victoria Park Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Pharmacy Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Lebovic Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Warden Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Birchmount Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ "Ionview Stop". Eglinton Crosstown. Retrieved October 22, 2016.
- ↑ Munro, Steve. "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Archived from the original on March 4, 2015. Retrieved June 17, 2013.
- ↑ "Light Rail Transit Facts". Metrolinx. May 31, 2015. Retrieved May 31, 2015.
- ↑ Ben Spurr (July 20, 2016). "Metrolinx threatens legal action over late delivery of light rail vehicles". Toronto Star. Retrieved July 20, 2016.
- ↑ "Metrolinx statement on Alstom/Bombardier". Metrolinx. Retrieved May 12, 2017.
- ↑ Spurr, Ben (May 13, 2017). "How do TTC’s streetcar options compare? It’s Bombardier versus Alstom". Toronto Star. Retrieved May 13, 2017.
- ↑ Ben Spurr; Jennifer Pagliaro (October 31, 2016). "Report outlines steep costs of running new Toronto transit lines". Toronto Star. Retrieved October 31, 2016.
- ↑ "Keele Street to Jane Section and Black Creek Maintenance & Storage Facility Environmental Project Report Addendum Online Consultation". Crosstown. 2016. Archived from the original on July 25, 2016.
Ultimate storage yard capacity of 162 vehicles;
- ↑ John Lorinc (November 23, 2012). "Down (but not out) Mount Dennis area pins hopes on Metrolinx". The Globe and Mail. Archived from the original on March 4, 2016. Retrieved March 28, 2013.
A sprawling storage and maintenance facility for the light-rail vehicles will be built on the Kodak site within a few years.
- ↑ Rahul Gupta (December 12, 2012). "Meeting to provide details on LRT station in Mount Dennis". York Guardian. Archived from the original on March 29, 2013.
The Mount Dennis underground stop at Weston Road would serve as the line’s western terminus point, said Metrolinx spokesperson Jamie Robinson on Friday, Dec. 7.
- ↑ Steve Munro (February 17, 2010). "Eglinton LRT: Trouble Brewing in Mt. Dennis (Update 2)". Archived from the original on March 4, 2015.
Some speakers addressed the use of the Kodak lands for the proposed carhouse, and asked that alternative schemes be considered. Part of this relates to a proposed “big box” development on the land. However, Council approved the acquisition of this property, by expropriation if necessary, in December.
- ↑ Roy Murray (July 9, 2012). "Feedback on maintenance yard needed". Weston Web. Archived from the original on March 29, 2013.
- ↑ Tess Kalinowski (February 16, 2010). "Residents ask TTC for LRT tunnel through Mount Dennis". Toronto Star. Archived from the original on March 29, 2013.
In addition to the $4.6 billion the province has committed to the Eglinton LRT, the centrepiece of Toronto's Transit City plan, the TTC also wants to build a carhouse on the old Kodak lands in Mount Dennis.
External links
Wikimedia Commons has media related to Eglinton Crosstown LRT. |
- Official Crosstown project website
- Toronto Light Rail Transit projects (Metrolinx)
- Videos published by the Eglinton Crosstown LRT Project:
- Tunnelling for The Crosstown on YouTube - Video with animation published on June 29, 2012.
- End to End - Eglinton Crosstown on YouTube - Video with animation published on July 13, 2015 (several stations mentioned in the video have since been renamed)
- Flyover video - Eglinton Crosstown Stations on YouTube - Video with animation published on December 3, 2015 (several stations mentioned in the video have since been renamed)
- Eglinton Crosstown Station Flyover on YouTube - Video published on May 2, 2017, showing aerial views of construction in progress along the line.
- TTC report that contains proposed re-routes after the Eglinton Crosstown opens