Canaport

Canaport
Location
Country Canada
Location Saint John, New Brunswick
Coordinates Coordinates: 45°12′41″N 65°59′09″W / 45.211271°N 65.985952°W / 45.211271; -65.985952
Details
Opened 1970 (crude oil terminal), 2008 (LNG terminal)
Owned by Irving Oil
Type of harbor deep-water crude oil receiving terminal

liquified natural gas terminal
Available berths 1 mono-buoy for crude oil supertankers
1 jetty for LNG tankers
Website
Canaport (crude oil) http://irvingoil.com/operations_and_partners/operations/supply/

Canaport LNG http://www.canaportlng.com

Canaport is a Canadian marine crude oil receiving terminal located on the north shore of the Bay of Fundy at Mispec Point, approximately 9 km (5.6 mi) southeast of the city of Saint John, New Brunswick.

Commissioned in 1970, Canaport was the first deep-water crude terminal in the Western Hemisphere able to receive supertankers. Canaport was built by Irving Oil, which has continuously owned and operated the facility throughout its existence. The terminal is currently configured exclusively as a crude receiving terminal in order to supply the Irving Oil Refinery, which was itself constructed in 1960.[1]

Crude terminal infrastructure

Canaport consists of the following infrastructure:

The terminal was originally designed to have 5 storage tanks measuring 200 ft (61 m) in diameter. The owner of Irving Oil, K.C. Irving modified the terminal's design to include 6 tanks so each tank could each have a single letter that when combined would spell I-R-V-I-N-G when viewed from the water.[2] Subsequent expansions of the refinery in the 1970s, 80s and 90s resulted in the construction of additional storage tanks.

NB Power

In 1976 NB Power commissioned the Coleson Cove Generating Station which is connected to Canaport by the 20 km (12 mi) Lorneville Pipeline. NB Power receives Number 6 fuel oil at Canaport where it is stored in two 1,500,000 bbl (240,000,000 l) tanks before being transported by the pipeline.

Canaport LNG

Canaport LNG
The Canaport facility viewed from the east. The LNG terminal jetty and LNG storage tanks are on the right. A supertanker carrying oil for the crude terminal is attached to the monobuoy on the left.

The Canaport LNG terminal is a liquified natural gas (LNG) receiving and regasification terminal located adjacent and immediately east of the Canaport crude receiving terminal. Commissioned in 2008, it is Canada's first LNG terminal and the first LNG terminal built in eastern North America in 30 years. It is capable of receiving the largest LNG tankers in the world.[3]

Canaport LNG has a nominal capacity of handling 1,200,000,000 cu ft (34,000,000 m3) of LNG per day, enough to heat 5 million homes. Regasified LNG from the Canaport LNG terminal is capable of supplying 20% of the natural gas demand in the northeastern United States and Canada.[3]

In 2001 Irving Oil applied for a permit to add liquified natural gas (LNG) to its Canaport deep-water crude receiving terminal. The permit was granted in April 2004 and Irving Oil entered into a partnership with Repsol S.A. to develop what is now called Canaport LNG; Irving Oil owns 25% of Canaport LNG while Repsol S.A. owns 75%. Construction of the LNG terminal started in September 2005 and the facility was commissioned in 2008 and received its first shipment of LNG in June 2009.[3]

Canaport LNG consists of the following infrastructure:

The construction of the Canaport LNG was coincident with construction of the Brunswick Pipeline which transports the natural gas from Canaport LNG to markets.

Controversy

In 2005, Irving Oil received a controversial tax break from the City of Saint John to develop the Canaport LNG terminal; it was apparently negotiated one-on-one with the city's then-mayor Norm MacFarlane. The tax concessions have cost the City of Saint John approximately $75 million over ten years, with a potential total loss of over $180 million.[5][6] Saint John Common Council’s reconsideration of this tax concession in 2015 resulted in warnings from Irving Oil, including editorials published in the Telegraph-Journal arguing against re-opening the deal.[7]

Proposed new oil export terminal

Irving Oil has announced plans to build a new $300-million terminal at Canaport to export the oil from the proposed Energy East pipeline.[8]

References

  1. "Supply". Irving Oil. Retrieved 2 August 2013.
  2. How, Douglas; Costello, Ralph (1993). K.C.: the biography of K.C. Irving.
  3. 1 2 3 "Press release June 18, 2009: Canaport LNG Terminal To Begin First Phase of Operations". Canaport LNG. Retrieved 2 August 2013.
  4. "Projects: Canaport LNG Terminal - Saint John, NB". Kiewit Corporation. Retrieved 2 August 2013.
  5. "CBC News: Mayor defends tax deal with Irving". 2005-03-16. Retrieved 2016-03-24.
  6. "CBC News: Irving made millions off deal to slash taxes on LNG property". 2015-06-12. Retrieved 2016-03-24.
  7. "Telegraph Journal Editorial: Don't rewrite history on LNG tax deal". 2015-12-09. Retrieved 2016-03-24.
  8. "Irving Oil to build new terminal for Energy East Pipeline project". The Canadian Press. Global News. 4 August 2013. Retrieved 4 August 2013.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.