Tokuyama Dam

Tokuyama Dam

Tokuyama Dam
Location of Tokuyama Dam in Japan
Location Ibigawa, Ibi District, Gifu Prefecture, Japan
Coordinates 35°39′55″N 136°30′08″E / 35.66528°N 136.50222°E / 35.66528; 136.50222Coordinates: 35°39′55″N 136°30′08″E / 35.66528°N 136.50222°E / 35.66528; 136.50222
Construction began 2000
Opening date 2008
Construction cost $360 million USD
Owner(s) Japan Water Agency
Dam and spillways
Type of dam Embankment, rock-fill
Impounds Ibi River
Height 161 m (528 ft)
Length 427.1 m (1,401 ft)
Dam volume 13,700,000 m3 (480,000,000 cu ft)
Spillway type Service, gate-controlled
Reservoir
Creates Tokuyama Reservoir
Total capacity 660,000,000 m3 (540,000 acre·ft)
Catchment area 254.5 km2 (98.3 sq mi)
Surface area 13 km2 (5.0 sq mi)
Power station
Coordinates 35°38′3.18″N 136°28′35.10″E / 35.6342167°N 136.4764167°E / 35.6342167; 136.4764167
Operator(s) Chubu Electric
Commission date 2014-2015
Type Conventional
Turbines 1 x 23 MW, 1 x 130 MW Francis-type
Installed capacity 153 MW

The Tokuyama Dam (徳山ダム Tokuyama damu) is an embankment dam near Ibigawa, Ibi District, Gifu Prefecture in Japan. The dam was completed in 2008 and will support a 153 MW hydroelectric power station that is expected to be fully operational in 2015. Currently, Unit 1 at 23 MW was commissioned in May 2014. The dam was originally intended to withhold the upper reservoir of a 400 MW pumped-storage power station until a design change in 2004. The dam is also intended for flood control and water supply. It is the largest dam by structural volume in Japan and withholds the country's largest reservoir by volume as well.[1]

History

In December 1957, Electric Power Development Company (J-Power) selected the Ibi River for study at the 23rd Electric Power Development Coordinating Meeting. By May 1976, the Ministry of Construction released their bulletin "Policy on Tokuyama Dam Construction Project". In December 1982, the project was incorporated into the Electric Power Development Basic Plan.[2] It was approved by the government in 1998.[3] The original project was a pumped-storage hydroelectric scheme which consisted of the Tokuyama Dam as the upper reservoir, the Sugihara Dam as the lower and the 400 MW Sugihara Power Plant.[4]

Construction on the dam started in May 2000 but by May 2004 J-Power and Chubu Electric announced they had changed the design of the project due to the concerns and protests of locals and groups. Instead of the pumped-storage hydroelectric scheme, only the Tokuyama Dam would be constructed with a 153 MW conventional power station. Subsequently, the Sugihara Dam and Sugihara Power Plant were scrapped from the project.[4] During construction, the 503 m (1,650 ft) long Tokunoyama Hattoku Bridge was constructed upstream. With improved techniques and equipment, fill for the dam was laid at a pace of 6,200,000 m3 (220,000,000 cu ft) per year, enabling the dam to be constructed in 26 months. Sediment from the Yokoyama Dam's reservoir was used as fill as well.[1] In September 2006 initial filling of the reservoir behind the Tokuyama Dam began and by June 2008, the dam was complete. Filling was complete in September. In October of the same year, J-Power passed oversight of the power station construction to Chubu.[2][4] The first generator, Unit 1, was commissioned on 15 May 2014. Unit 2 should be commissioned by June 2015.[5]

Design

The Tokuyama Dam is a 427.1 m (1,401 ft) long and 161 m (528 ft) high rock-fill embankment dam with a clay core. The total structural volume of the dam is 13,700,000 m3 (480,000,000 cu ft). The dam creates a reservoir with a 660,000,000 m3 (2.3×1010 cu ft) capacity, surface area of 13 km2 (5.0 sq mi) and catchment area of 254.5 km2 (98.3 sq mi).[1] The dam will support two Francis turbine-generators, one with a 130 MW capacity which will be located in an underground power station downstream. The second is an operational 23 MW generator and is located at the base of the dam. The installed capacity of both will be 153 MW. The power station will process a maximum of 100 m3/s (3,500 cu ft/s) for power production.[2]

References

  1. 1 2 3 "The Tokuyama Dam" (PDF). Japan Water Agency. Retrieved 3 October 2010.
  2. 1 2 3 "Change of Oversight of Tokuyama Power Station Plan". CHUBU Electric. October 14, 2008. Retrieved 3 October 2010.
  3. "Appeal fails; largest dam, in works since '57, can be built". The Japan Times. July 7, 2006. Retrieved 3 October 2010.
  4. 1 2 3 "Press Release Changes to the development project for the Tokuyama Power Plant and Sugihara Power Plant". CHUBU Electric. Retrieved 3 October 2010.
  5. "20 000 kW or more of the hydroelectric power plant in the dam, the start of operation in Gifu Prefecture of underground" (in Japanese). ITmedia. 20 May 2015. Retrieved 24 January 2015.

External links

Media related to Tokuyama Dam at Wikimedia Commons

This article is issued from Wikipedia - version of the Tuesday, September 29, 2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.