Takt time
Takt time, derived from the German word Taktzeit, translated best as meter, is the average time between the start of production of one unit and the start of production of the next unit, when these production starts are set to match the rate of customer demand. For example, if the customer wants to buy 10 units per week, and the units are produced during a 40-hour work week, then the average time between the start of one unit and the next should be, which, given a steady flow through the production plant, will result in a unit being completed every 4 hours (which equates to 10 units per week). A common misconception is that takt time is related to the time it takes to actually make the product - whether it takes 4 minutes to produce the product or whether it takes 4 years to produce the product, the takt time should be 4 hours in this example (of course, the time it takes to produce the product will impact the magnitude of the number of units actually in production at any point in time).
Definition
Assuming a product is made one unit at a time at a constant rate during the net available work time, the takt time is the amount of time that must elapse between two consecutive unit completions in order to meet the demand.
Takt time can be first determined with the formula:
Where
T = Takt time, e.g. [work time between two consecutive units]
Ta = Net time available to work, e.g. [work time per period]
D = Demand (customer demand), e.g. [units required per period]
Net available time is the amount of time available for work to be done. This excludes break times and any expected stoppage time (for example scheduled maintenance, team briefings, etc.).
Example:
If there are a total of 8 hours (or 480 minutes) in a shift (gross time) less 30 minutes lunch, 30 minutes for breaks (2 × 15 mins), 10 minutes for a team briefing and 10 minutes for basic maintenance checks, then the net Available Time to Work = 480 - 30 - 30 - 10 - 10 = 400 minutes.If customer demand was, say, 400 units a day and one shift was being run, then the line would be required to output at the rate of a minimum of one part per minute in order to be able to keep up with customer demand.
In reality, over the longer term people and machines cannot maintain 100% efficiency and there may also be stoppages for other reasons. Allowances should be made for these instances and thus the line will be set up to run at a faster rate to account for this.
Also, takt time may be adjusted according to requirements within the company. For example, if one department delivers parts to several manufacturing lines, it often makes sense to use similar takt times on all lines to smooth out flow from the preceding station. Customer demand can still be met by adjusting daily working time, reducing down times on machines and so on.
Some of the early literature uses cycle time for takt time.
Implementation
Takt time is calculated on virtually every task in a business environment. It is used in manufacturing (casting of parts, drilling holes or preparing a workplace for another task), control tasks (testing of parts or adjusting machinery) or in administration (answering standard inquiries or call center operation). It is, however, most common in production lines that move a product along a line of stations that each perform a set of predefined tasks.
Once a takt system is implemented there are a number of benefits:
- The product moves along a line, so bottlenecks (stations that need more time than planned) are easily identified when the product does not move on in time.
- Correspondingly, stations that don't operate reliably (suffer frequent breakdown, etc.) are easily identified.
- The takt leaves only a certain amount of time to perform the actual value added work. Therefore there is a strong motivation to get rid of all non value-adding tasks (like machine set-up, gathering of tools, transporting products, etc.)
- Workers and machines perform sets of similar tasks, so they don't have to adapt to new processes every day, increasing their productivity.
- There is no place in the takt system for removal of a product from the assembly line at any point before completion, so opportunities for shrink and damage in transit are minimized.
Downsides of takt time organization include:
- When customer demand rises so much that takt time has to come down, quite a few tasks have to be either reorganized to take even less time to fit into the shorter takt time, or they have to be split up between two stations (which means another station has to be squeezed into the line and workers have to adapt to the new setup)
- When one station in the line breaks down for whatever reason the whole line comes to a grinding halt, unless there are buffer capacities for preceding stations to get rid of their products and following stations to feed from. A built-in buffer of three to five percent downtime allows needed adjustments or recovery from failures.[1]
- Short takt time can put considerable stress on the "moving parts" of a production system or subsystem. In automated systems/subsystems, increased mechanical stress increases the likelihood of breakdown, and in non-automated systems/subsystems, personnel face both increased physical stress, which increases the risk of repetitive motion (also "stress or "strain") injury, and intensified emotional stress, and lowered motivation, sometimes to the point of increased absenteeism.
- Tasks have to be leveled to make sure tasks don't bulk in front of certain stations due to peaks in workload. This decreases the flexibility of the system as a whole.
See also
References
External links
- Lean Manufacturing site about Takt time
- Six Sigma site about Takt time
- Takt Time Simulator On Line
- On Line business processes simulator
Further reading
- Monden, Yasuhiro (2011). Toyota Production System: An Integrated Approach to Just-In-Time. New York: Productivity Press. p. 566. ISBN 1-4398-2097-X.
- Ohno, Taiichi, Toyota Production System: Beyond Large-Scale Production, Productivity Press (1988). ISBN 0-915299-14-3
- Baudin, Michel, Lean Assembly: The Nuts and Bolts of Making Assembly Operations Flow, Productivity Press (2002). ISBN 1-56327-263-6
- Ortiz, Chris A., Kaizen Assembly: Designing, Constructing, and Managing a Lean Assembly Line, CRC Press. ISBN 978-0-8493-7187-5