Shidao Bay Nuclear Power Plant

Shidao Bay Nuclear Power Plant[1]
Location of Shidao Bay Nuclear Power Plant[2] in China
Official name 石島灣核電廠
Country People's Republic of China
Location Rongcheng, Weihai, Shandong
Coordinates 36°58′N 122°30′E / 36.967°N 122.500°E / 36.967; 122.500Coordinates: 36°58′N 122°30′E / 36.967°N 122.500°E / 36.967; 122.500
Status Under construction
Construction began March 2014 (2014-03)[3]
Construction cost US$16 billion (units 1–7)
Owner(s)

Huaneng

Shandong Shidao Bay Nuclear Power Co., Ltd (HSNPC)
Nuclear power station
Reactor type HTR-PM
CAP1400 PWR
Power generation
Units under const. 1 × 210 MW[4]
Units planned 2 × 1500 MW
9 × 210 MW

Shidao Bay Nuclear Power Plant (simplified Chinese: 石岛湾核电厂; traditional Chinese: 石島灣核電廠; pinyin: Shídǎo wān hédiàn chǎng) is a nuclear power plant in Shandong province, China. The site is located near the Xiqianjia village in the town of Ningjin subdistrict, Rongcheng, Weihai, Shandong. The plant is located about 23 kilometres (14 mi) south of Rongcheng City, 14 kilometres (8.7 mi) north-west from Shidao and 68 kilometres (42 mi) south-est from Weihai City.[5] The plant will have the first fourth generation of nuclear reactors in the world: the HTR-PM, a HTGR concept. The plant will ultimately have 10 210 megawatt (MWe) units of these type. Each unit is made of two HTR-PM reactors driving a single 210 megawatt (MWe) steam turbine. The plant will also host the construction of the two demonstration 1,500 megawatt (MWe) CAP1400 pressurized water reactor in China, a larger AP1000 design, worked together by Westinghouse and State Nuclear Power Technology Corporation (SNPTC) and other institutes.

Shidao Bay nuclear power plant is a jointly investment of China Huaneng Group, China Nuclear Engineering & Construction Group and Tsinghua University.

The total investment of 100 billion yuan (US$15.7 billion) and the 20 years construction duration makes it China largest planned nuclear project.

Construction permit was issued by the National Nuclear Safety Administration (NNSA) of the Environmental Protection Department (EPA) on 12 December 2012 and the site preparation, started in 2011, just before the Fukushima events, was resumed. Basement concrete pour was completed on 29 March 2014.[6]

See also

References

  1. "Shidao Bay nuclear power plant started at the end of 2012". Qingdao Municipal Government. 14 January 2013. Retrieved 13 November 2015.
  2. "Shidao Bay nuclear power plant started at the end of 2012". Qingdao Municipal Government. 14 January 2013. Retrieved 13 November 2015.
  3. "First-layer concrete poured on nuclear island baseboard for Shidao Bay HTR Demonstration Project". Dynabond Powertech. 26 December 2012. Retrieved 13 November 2015.
  4. "China CAP1400 Preliminary Design is Approved by NEA". State Nuclear Power Technology Company. 20 January 2014. Retrieved 21 July 2014.
  5. "Marine Works of Shidao Bay Nuclear Power Plant". CCCC-FHDI Engineering. May 5, 2014. Retrieved 2014-07-21.