The Town and Country Planning (General Permitted Development) (England) Order 2015 (the "GPDO 2015") is a Statutory Instrument, applying in England, that grants planning permission for certain types of development (such development is then referred to as permitted development). Schedule 2 of the GPDO 2015 specifies the classes of development for which planning permission is granted, and specifies the exceptions, limitations, and conditions that apply to some of these classes. The GPDO 2015 was made by the Secretary of State under authority granted by sections 59, 60, and 333 of the Town and Country Planning Act 1990.

History of the GPDO

The GPDO 2015 came into force on 15 April 2015, and was introduced by Statutory Instrument 2015 No. 596. The GPDO 2015 revoked The Town and Country Planning (General Permitted Development) Order 1995 (the "GPDO 1995"), which was the previous version of the legislation.

The website www.legislation.gov.uk, which is delivered by the National Archives, provides the original ("as made") version of the GPDO 2015, but states that UK Statutory Instruments are not carried in their "revised" form on the website.

The previous version of the legislation, the GPDO 1995, came into force on 3 June 1995, and was introduced by Statutory Instrument 1995 No. 418. During the time it was in force (i.e. from 3 June 1995 until 14 April 2015), the GPDO 1995 was amended by a number of subsequent Statutory Instruments. With respect to England, the Planning Jungle website states that the GPDO 1995 was amended by a total of 37 subsequent Statutory Instruments.[1]

The following list shows all of the versions of the GPDO from 1948 to present:

Operation of the GPDO 2015

Schedule 2 of the GPDO 2015

Schedule 2 specifies the classes of development for which planning permission is granted, and specifies the exceptions, limitations, and conditions that apply to some of these classes. These classes are contained within the following 19 "Parts":

Householder Permitted Development

The phrase "permitted development" is often used to refer to Schedule 2 Part 1, which relates to "Development within the curtilage of a dwellinghouse".[2]

Householder Permitted Development in England

With respect to England, householder permitted development is set out by Schedule 2 Part 1 of the GPDO 2015, as introduced on 15 April 2015 by Statutory Instrument 2015 No. 596.

In September 2008, the Department for Communities and Local Government ("DCLG") published a document titled Guidance on the permeable surfacing of front gardens, which provides advice about how to interpret Part 1 Class F. This document was subsequently updated in May 2009.

In August 2010, DCLG published a document titled Permitted development for householders: Technical Guidance, which provides advice about how to interpret Part 1. This document was subsequently updated in January 2013, October 2013, and April 2014.

In May 2013, DCLG published a document titled Larger Home Extensions - Neighbour Consultation Scheme, which provides advice about the system of larger rear extensions under Part 1 Class A. This document was subsequently updated in June 2013 and June 2015.

In May 2014, DCLG published the Planning Practice Guidance website, which includes a section titled What are permitted development rights. This website is updated on an ongoing basis.

In the above "Permitted development for householders: Technical Guidance" document, the 8 classes of Schedule 2 Part 1 are described as follows:

For the above legislation, public consultations were undertaken from 21 May 2007 to 17 August 2007,[3] from 12 November 2012 to 24 December 2012, [4] and from 31 July 2014 to 26 September 2014.[5]

Householder Permitted Development in Wales

With respect to Wales, householder permitted development is set out by Schedule 2 Part 1 of the GPDO 1995, as amended on 30 September 2013 by Statutory Instrument 2013 No. 1776.

In July 2013, the Welsh Government published a document titled Technical Guidance: Permitted development for householders, which provides advice about how to interpret Part 1. This document was subsequently updated in April 2014.

For the above legislation, a public consultation was undertaken from 23 November 2010 to 15 February 2011.[6]

2013-2015 Amendments

With respect to England, Schedule 2 Parts 1, 2, 3, 4, 7, and 16 were amended on 30 May 2013 by Statutory Instrument 2013 No. 1101, Part 16 was amended on 21 August 2013 by Statutory Instrument 2013 No. 1868, Part 11 was amended on 1 October 2013 by Statutory Instrument 2013 No. 2147 and by Statutory Instrument 2013 No. 2435, Parts 1, 2, 3, 6, and 7 were amended on 6 April 2014 by Statutory Instrument 2014 No. 564, Parts 3, 4, and 11 were amended on 6 April 2015 by Statutory Instrument 2015 No. 659, and all Parts were amended on 15 April 2015 by Statutory Instrument 2015 No. 596.

For the above changes, public consultations were undertaken from 8 April 2011 to 30 June 2011,[7] from 3 July 2012 to 11 September 2012,[8] from 12 November 2012 to 24 December 2012,[9] from 3 May 2013 to 14 June 2013,[10] from 6 August 2013 to 15 October 2013, [11] and from 31 July 2014 to 26 September 2014.[5] For further changes that are currently proposed, public consultations were undertaken from 5 March 2015 to 16 April 2015,[12] and from 13 August 2015 to 24 September 2015.[13]

Part 3 Class O excluded areas

These rights do not apply to certain areas within the following local authorities:[14]

See also

References

External links

This article is issued from Wikipedia - version of the Tuesday, August 25, 2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.