Pearl Harbor Memorial Bridge (Connecticut)
Pearl Harbor Memorial Bridge [1] | |
---|---|
Construction of the new Pearl Harbor Memorial Bridge (Q-Bridge) as viewed from the Tomlinson Bridge. | |
Carries | Ten lanes of I-95 |
Crosses | Quinnipiac River |
Locale | New Haven, Connecticut, U.S. |
Maintained by | Connecticut Department of Transportation |
Characteristics | |
Design | Extradosed bridge |
Total length | 1,443.2 metres (4,735 ft) |
Width | 55.4 metres (182 ft) |
Height | 45.7 metres (150 ft) |
Longest span | 157.0 metres (515.1 ft) |
Clearance below | 18.3 metres (60 ft) |
History | |
Opened |
June 22, 2012 (NB Span), July 26, 2013 (SB lanes on NB Span), November 2015 (SB Span) |
The Pearl Harbor Memorial Bridge, more commonly referred to as the Q Bridge (the "Q" referring to "Quinnipiac") by locals, is a partially completed extradosed bridge that carries Interstate 95 (Connecticut Turnpike) over the mouth of the Quinnipiac River in New Haven, in the U.S. state of Connecticut. Currently, the northbound span of the new extradosed bridge carries both northbound and southbound traffic, while the original girder-and-floorbeam bridge that opened in 1958, is demolished and the new southbound span is built in its place. The original 1,300 m (0.8 mi) span – which opened on January 2, 1958 – was a girder and floorbeam design where steel beams support the concrete bridge deck. The bridge carried three lanes of traffic in each direction with no inside or outside shoulders. The bridge was officially dedicated as the Pearl Harbor Memorial Bridge in 1995 to commemorate the attack on Pearl Harbor.[2]
The Pearl Harbor Memorial Bridge is being replaced by a $554 million 10-lane extradosed bridge; the northbound span of which opened to traffic on June 22, 2012. Southbound traffic was shifted onto the new bridge, sharing the northbound span with northbound traffic until the new southbound span is completed in late 2015. Since the Gibbs Street Bridge in Portland, Oregon was redesigned from an extradosed span to a box girder bridge, the Pearl Harbor Memorial bridge is on track to be the first extradosed bridge in the United States when it fully opens in 2016.[3] The new bridge is the centerpiece of a $2 billion megaproject to reconstruct and widen 13 miles (21 km) of I-95 between West Haven and Branford.
History
This bridge was created as part of a project to build the Connecticut Turnpike, a toll road stretching from Greenwich to Killingly in the 1950s. By 1993 the Quinnipiac River bridge was considered outdated, and traffic bottlenecks had been a chronic problem over the Q bridge.[4]
(Old) Pearl Harbor Memorial Bridge | |
---|---|
Q Bridge with the Tomlinson Lift Bridge behind it | |
Coordinates | 41°17′55″N 72°54′14″W / 41.29861°N 72.90389°WCoordinates: 41°17′55″N 72°54′14″W / 41.29861°N 72.90389°W |
Carries | Six lanes of I-95 |
Crosses | Quinnipiac River |
Locale | New Haven, Connecticut |
Maintained by | Connecticut Department of Transportation |
Characteristics | |
Design | Girder and floorbeam |
Total length | 1,443.2 metres (4,735 ft) |
Width | 25.6 metres (84 ft) |
Clearance below | 18.3 metres (60 ft) |
History | |
Opened | January 2, 1958 |
Closed | July 26, 2013 |
Signature span replacement
Bridge plans bring controversy
The existing Q-Bridge opened with a design capacity of 90,000 vehicles per day (VPD), but as of 2006 more than 150,000 vehicles cross the span daily. In 1989 the Connecticut Department of Transportation (CONNDOT) and the Federal Highway Administration (FHWA) initiated a study to improve I-95 between Branford and West Haven, including replacing the existing Pearl Harbor Memorial Bridge. The study that included the replacement of the Q-Bridge accounts for seven miles (12 km) of the Connecticut Turnpike from the I-91/Route 34 interchange in New Haven to Cedar Street in Branford. The remaining 6 miles (10 km) of the corridor from the I-91/Route 34 interchange to Route 162 (Sawmill Road) will be rebuilt as three separate projects with their own EISs.
In 1992, the FHWA and CONNDOT released the draft environmental impact statement, which presented a number of alternatives to improve eastern seven miles (12 km) of the 13-mile (22 km) corridor:
- Ten-lane bridge; eight lanes to Branford
- Eight-lane bridge; six lanes to Branford with a light-rail line (utilizing the median of I-95) from New Haven Union Station to Branford.
- Construction of a new bridge parallel to the existing bridge, which would carry four northbound lanes of the Connecticut Turnpike; the existing bridge would then be rehabilitated and reconfigured to carry four lanes of southbound traffic.
All of the corridor alternatives presented in the 1992 DEIS were subsequently rejected by local officials, mass-transit advocates, business organizations, and environmental groups.
Returning to the drawing board
In response to the controversy over the design of the new bridge, CONNDOT organized the Intermodal Concept Development Committee (ICDC), which included representatives from New Haven, East Haven, and Branford, environmental groups, local business associations, the FHWA, the Army Corps of Engineers, and the Coast Guard.
The ICDC examined over 100 alternatives before narrowing the list to seven in the Supplemental DEIS, presented in April 1997. The final EIS was issued in March 1999, which called for a 10-lane Q-Bridge; eight lanes to East Haven and six lanes to Branford, and a new Metro-North/Shore Line East train station at State Street in New Haven. The FHWA issued a Record of Decision, approving the FEIS in August 1999.[5] CONNDOT is preparing two separate studies to reconstruct the remainder of the corridor through the Long Wharf section of New Haven and West Haven.
In 2001, New Haven Mayor John DeStefano, Jr. pressed CONNDOT and the FHWA to design the new Q-Bridge as a signature span. A cable-stayed design was originally considered, but the Federal Aviation Administration raised concerns over the height of the towers interfering with the approach into Tweed-New Haven Airport compelled CONNDOT to consider an extradosed bridge, which retains the aesthetic qualities of a cable-stayed structure, with shorter towers.
Construction on the eastern approach to the bridge in Branford and East Haven began in 2001; while work began in 2004 on the earthworks for the western approach around the I-91/Route 34 interchange. The United Illuminating Company erected new pylons and rerouted its 115 kilovolt transmission lines away from the bridge in 2003, to make way for the larger bridge to be built.
More construction delays
Construction on the bridge itself was originally set to begin in 2005 and be completed in 2012. However, two historically significant structures—the former Yale Boathouse and the Fitch Foundry—sat directly in the path of the new bridge. The City of New Haven demanded that these two structures be preserved.[6] Mayor DeStefano further argued that CONNDOT should include the expansion of I-95 through Long Wharf and West Haven into the overall plan instead of pursuing these projects separately. Given the impasse between CONNDOT and the City of New Haven over these two issues, the FHWA threatened to pull funding for the project unless the city and state could come to a consensus on how to proceed while keeping the project's costs under control.[7][8] Realizing that such a move would effectively void the already-approved EIS and require a new one to be developed, CONNDOT and the city of New Haven made a compromise in late 2005 that called for CONNDOT to build a $32 million replica of the Yale Boathouse at Long Wharf Park. In exchange, the City of New Haven agreed to allow CONNDOT to continue the environmental and design studies on the Long Wharf and West Haven sections apart from the I-91/Route 34 to Branford segment of I-95 that includes the Q-Bridge.[9]
The project was let to bid in May 2006, but there were no bids received by the December 27, 2006 deadline. Two construction firms interested in the project cited—among other things—the absence of an escalator clause in the project contract to cover the rising cost of fuel and raw materials for the lack of bids.[10]
Staged construction
In response, CONNDOT divided the bridge project into multiple contracts that were let in stages as construction progresses. While this makes the project more manageable for contractors and highway officials, this approach significantly added to the time required to complete the new bridge.
Eastern approach
The eastern approach to the Pearl Harbor Memorial Bridge was reconstructed and widened through two contracts, officially referred to as Contracts C1 and C2 at a total cost of $120 million. Contract C1 reconstructed the eastern approach from Lake Saltonstall through East Haven, while Contract C2 reconstructed I-95 from the East Haven/New Haven border to the eastern abutment of the Pearl Harbor Memorial Bridge. O & G Industries of Torrington, Connecticut was the primary contractor for both contracts. While a train accident, harsh weather, and several design changes delayed the completion of Contract C1 by more than a year, O & G Industries completed Contract C2 in August 2008, one year ahead of schedule. Further east, a third contract officially referred to as Contract D, reconstructed and widened I-95 from the Lake Saltonstall bridge to Exit 54 in Branford. Pittsfield, Massachusetts-based Middlesex Company was the prime contractor for the $36 million contract. Aside from resurfacing and restriping from two to three lanes, no physical construction was performed on the I-95 bridge over Lake Saltonstall as it was rebuilt and widened in 1995.
Western approach and I-91/Route 34 interchange
Reconstructing the western approach to the bridge has been divided into several contracts: E, E1 and E2. The first of which, Contract E1 was completed in late 2006. Contract E1 involved the construction of earthworks that support the western abutment of the new bridge and carry the new ramps to I-91 and Route 34. L.G. DeFelice Construction was originally awarded the $14 million contract, but the company went out of business midway through the project. The contract was picked up and completed by Hallberg Construction in 2006. Contract E2 involved building the flyover bridge that carries the new ramp from I-95 northbound to Route 34 and added a transition lane to I-95 in each direction through Long Wharf. This contract was completed on June 6, 2011 by Walsh Construction Company of Canton, Massachusetts at a cost of $90 million. Contract E will complete the remainder of the interchange ramps, bridges, and new Turnpike mainline roadways.
Removal of buildings and relocating sewer lines
The first bridge contract, which includes the demolition of buildings where the new bridge will stand, was let in October 2006. Work under this contract was completed in August 2007 with the demolition of the Yale Boathouse and the Fitch Foundry where the west abutment of the new bridge will be.
A second contract was let on June 1, 2007, to relocate two 42-inch (1.06 meter) diameter sanitary sewer lines that lie directly beneath where part of the new bridge will be built. Construction of the new sewer lines involved slant drilling through bedrock under New Haven Harbor. The Middlesex Company, a construction contractor based in Littleton, Massachusetts, was the prime contractor on the $20 million project.[11]
Building the abutments and pier foundations
The third contract, known as Contract B1 in official documents, which covers construction of the bridge abutments and pier foundations for the northbound lanes was let on October 31, 2007. Four construction firms submitted bids for this $137 million contract February 6, 2008, according to bid results from CONNDOT.[12] The contract was awarded to a joint venture between the Middlesex Company and Pittsfield, Maine-based Cianbro Corporation in April 2008.
Completing the new bridge and removing the original span
The final contract, known as Contract B, will construct the remainder of the new bridge and demolish the existing span. Contract B was awarded to a joint venture between Walsh Construction of Chicago, Illinois and Denver, Colorado-based PCL Constructors for $417 million in July 2009. The joint venture company is also known as Walsh-PCL Joint Venture II.
West Haven to I-91/Route 34
Three separate projects will reconstruct and widen I-95 from I-91/Route 34 to Route 162 in West Haven. Reconstruction of I-95 from the West River to I-91/Route 34 including the stretch through Long Wharf is in the EIS phase. Current work on the Long Wharf section is required to enable a smooth transition from the existing 3-lane I-95 cross-section to the west into the new I-91/Route 34 interchange. Future work on the Long Wharf section would add travel lanes beyond the transition into the I-91/Route 34 interchange. Alternatives discussed in the Draft EIS included either elevating I-95 onto a viaduct or submerging the highway underground through tunnels, similar to Boston's Big Dig. Depending on the alternative selected, cost estimates for reconstructing the Long Wharf section of I-95 range from $200 million to $500 million.
To the west of Long Wharf, CONNDOT is replacing the aging bridge over the West River and Route 10 with a wider structure. Part of this reconstruction effort will be consolidating Exits 44 and 45 into a single interchange. Construction on the $200 million bridge began in November 2013 and is scheduled for completion in 2018.
The section of I-95 from Route 162 in West Haven to the West River features three narrow lanes with no shoulders, and has been the site of chronic congestion and numerous accidents. To address these issues, CONNDOT plans to reconstruct this section of roadway to three (expandable to four) lanes with full left and right shoulders, which will match the roadway profiles at either end of the segment. Construction is contingent upon funding.
How the new bridge will be built
The new Pearl Harbor Memorial Bridge will be built in three stages. The first half of the new bridge was built alongside and to the south of the existing bridge. This span will carry the northbound lanes of I-95 once the entire project is complete. On June 25, 2012, the new bridge was opened, and it carries three travel lanes in each direction while the old bridge is demolished and the remaining half of the new span is built.[13] Once complete, the southbound lanes will be shifted to the second span and the bridge will be opened to 5 lanes in each direction. Adding to the challenge of building the new bridge is that work must be coordinated with the ongoing reconstruction of the massive I-91/Route 34 interchange just west of the bridge. As a result, completion of the project is now scheduled for 2016, four years later than originally planned, although this might change as the southern half was opened six months early.
Financing the new bridge
When the EIS for rebuilding I-95 between the I-91/Route 34 interchange and Exit 54 in Branford was issued in 1997, the project's cost was projected at $800 million. Of that, replacement of the Pearl Harbor Memorial Bridge was estimated to be $360 million. Early on in the EIS process, officials considered placing a toll plaza at the east end of the bridge. The toll option would have had cars paying $4.00 to cross the bridge. Officials scrapped toll plans due to widespread opposition and legislation banning the placement of tolls on Connecticut highways. When the project's costs were reassessed in 2007, the bridge's construction cost has skyrocketed to beyond $500 million, and the total cost for rebuilding I-95 from New Haven to Branford was increased to $1.36 billion. Some officials estimate that rebuilding the seven-mile turnpike segment will balloon to over $2 billion by the time construction is completed in 2016. Regardless, construction will be financed with 90% federal funds and 10% state and local funds.
Northbound span
The Northbound section of the bridge opened to three lanes of traffic on June 25, 2012, after being completed 6 months ahead of schedule.[14] On July 26, 2013, southbound traffic was shifted from the original bridge over to the new northbound span. The northbound span will carry three lanes of both northbound and southbound traffic while the original bridge is demolished, and the new southbound span is built.
Southbound span
On July 17, 2015, construction workers held a barbecue lunch on the southern span of the new bridge to celebrate its completion. Officials expect the new southern span to partially open, with an off-ramp to I-91 northbound in September 2015, and to fully open with complete access ramps by mid-2016. [15]
On September 17, 2015, a grand-opening celebration was held on the new southbound span, and a couple days later, traffic diversions began. As of November 2015, there are two continuous lanes of I-95 traffic, as well as single-lane ramps to I-91 and CT-34. The state has partially completed elevated structures that will carry I-95 through the New Haven interchange. The structures are expected to be completed by mid-2016, and will create six continuous lanes of I-95 through New Haven with full shoulders, and also allow the Pearl Harbor Memorial Bridge to carry ten lanes of traffic (Six continuous lanes and four lanes for exits/accelerations.
References
- ↑ "Pearl Harbor Memorial Bridge Factsheet, Accessed March 10, 2010" (PDF). Retrieved August 22, 2011.
- ↑ "Connecticut General Assembly Public Act No. 95-325". Cga.ct.gov. Retrieved August 22, 2011.
- ↑ "Welcome to the Gibbs Street Pedestrian Bridge Website!". Gibbs Street Bridge. Retrieved December 8, 2008.
- ↑ MILLER, JULIE (September 5, 1993). "State Seeks to Open a Bottleneck". The New York Times (New York, New York: The New York Times Company). Retrieved February 13, 2011.
- ↑ I-95 New Haven Harbor Crossing Improvement Program History
- ↑ Future of Yale Boathouse, bridge development in question, WTNH TV Channel 8, November 15, 2004
- ↑ New Haven trying to get agreement on Q-Bridge project, WTNH TV Channel 8, November 9, 2005
- ↑ Feds may halt Q-bridge rehab Highway administration unhappy with cost overruns, New Haven Register, October 27, 2005
- ↑ Q bridge meeting is productive, New Haven Register, November 10, 2005
- ↑ Q-Bridge Construction, WTNH TV Channel 8, February 26, 2007
- ↑ Department of Transportation. "CONNDOT Bids and RFPs". Ct.gov. Retrieved August 22, 2011.
- ↑ Department of Transportation (August 9, 2011). "CONNDOT Projects Scheduled for Advertising". Ct.gov. Retrieved August 22, 2011.
- ↑ Robbins, Rebecca D. (June 21, 2012). "New Haven Highway Traffic Could Come To Crawl This Weekend". The Hartford Courant (Hartford, Connecticut). Retrieved June 21, 2012.
- ↑ http://www.i95newhaven.com/
- ↑ http://www.nhregister.com/lifestyle/20150717/party-on-new-havens-q-bridge-means-span-is-complete
External links
Wikimedia Commons has media related to Pearl Harbor Memorial Bridge (Connecticut). |
- i95newhaven.com - Official website for the highway reconstruction projects around New Haven Harbor
- Quinnipiac Bridge at Structurae (next bridge)
- Pearl Harbor Memorial Bridge at Structurae (current bridge)