Sydney Metro Northwest
Sydney Metro Northwest | |
---|---|
Sydney metropolitan rail area, with Sydney Metro Northwest alignment highlighted in green | |
Overview | |
Type | Rapid transit line |
System | Sydney Metro |
Status | Under construction |
Locale | Sydney, Australia |
Stations | 13 (8 new stations)[1] |
Operation | |
Opened | 2019 (projected) |
Owner | Transport for NSW |
Events | |
Announced | November 1998 |
Cancelled | October 2008 |
Re-announced | February 2010 |
Technical | |
Line length | 36 km (22 mi)[2] |
Sydney Metro Northwest is a current project by the Government of New South Wales for a rapid transit link to the north-western suburbs of Sydney, Australia. It is being managed by Transport for New South Wales and is proposed to connect Rouse Hill to Chatswood via Castle Hill and Epping.
Prior to June 2015, the project was known as the North West Rail Link (NWRL). Originally, North West Rail Link was meant to cover the section between Epping and Rouse Hill. By June 2015, the "North West Rail Link" covered the route of the original NWRL and the Epping to Chatswood railway line between Epping and Chatswood, which will be converted to rapid transit standards. In June 2015, it was announced that entire project would be renamed the Sydney Metro Northwest, the first stage of the forthcoming Sydney Metro system.[2]
History of the original North West Rail Link
Planning for the original North West Rail Link was a long and complex affair. The line was announced, cancelled and re-announced several times beginning in the 1990s. There were differing plans as to how the line would integrate into the rest of Sydney's transport system. The following proposals were endorsed at one time or another by the government:
- Main line rail connecting to the Main Northern line near Beecroft, with trains accessing the city via either Rhodes (using the Main Northern line) or Macquarie Park (using the Epping to Chatswood line).
- Main line rail connecting directly to the Epping to Chatswood line at Epping, with trains accessing the city via Macquarie Park.
- Rapid transit line from the north west to the city via the Inner West, dubbed the North West Metro.
- Rapid transit line connecting to a modified Epping to Chatswood line at Epping. Trains terminate at Chatswood, with an extension to the city proposed for the future. This was the design which was ultimately selected.
1998 (original) proposal
The North West Rail Link was originally announced on 23 November 1998 by the then-Transport Minister in the Carr Government, Carl Scully, and was part of an $2.6 billion package of eight major rail projects due for construction by 2010 dubbed the Action for Transport 2010.[3] At the time, the proposal was for a $360 million heavy rail connection from Epping to Castle Hill, with potential extension to Mungerie Park and Rouse Hill after 2010.
Delays in 2000 by the Carr Government in releasing a draft report on the proposal led to concern about the viability of the proposed route.[4] This led to a deadlock between the State Government and Baulkham Hills Shire Council regarding construction of the $200 million Mungerie Park industrial and residential development at Kellyville. On 5 June 2000 the Council voted to defer planning approval for the Mungerie Park development until the State Government demonstrated a commitment to improve local transport infrastructure, which included building the North West rail link. In response, the State Government threatened to remove the Council's planning powers for the Rouse Hill Development Area if planning approval was not granted.[5] Member for the then-State electorate of The Hills, Michael Richardson, submitted a Freedom of Information request for the draft report on 3 November 2000. The State Government had not responded to the request by 13 December 2000, well beyond the 21-day response limit, leading to accusations that the Government was trying to hide something.[6] The State Government formally rejected the Freedom of Information request on 9 January 2001, despite acknowledging that release of the report would be in the public interest.[7][8] As a result, the NSW Ombudsman began an investigation into NSW Transport's refusal to release the report.
News reports from March 2001 suggested that cost estimates for the Action for Transport 2010 plan had blown out so much that the scope of the plan was now reduced to an Epping to Chatswood rail link due for completion in 2008. The completion date for the Parramatta to Epping section of the original Parramatta to Chatswood link was unspecified, which meant that the North West rail link proposal was effectively deferred indefinitely—it would not be built until the Parramatta to Chatswood link was completed.[9] The Action for Transport 2010 cost blowout was seen as the reason for the State Government's refusal to release the draft report into the North West rail link route.[10] According to Member for The Hills, Michael Richardson, the then-Premier Bob Carr effectively confirmed that the Epping to Castle Hill rail link was dead during a session of Parliament on 27 March 2001 when he refused to answer a specific question about the details of the proposed rail link.[11] There was no mention of the rail link in the 2001 budget, released the week of 30 May.[12]
A 2002 NSW Treasury report mentioned the North West rail link, and that it was "under development or investigation", but no estimate of cost or start date were provided.[13] On 10 March 2002, Transport Minister Carl Scully released a report detailing the preferred route alignment.[14] The 19 km (12 mi) route was proposed to run from Epping to Mungerie Park at Rouse Hill via Castle Hill. The cost of construction was estimated at $1.4 billion. Public consultation on the proposal was conducted over eight weeks from 10 March to 3 May 2002.[15][16] The consultation received 118 written submissions, 73% of which were in favour of the project proceeding, and only 5% strongly opposed the project. On 3 October 2002, the Minister announced a feasibility study for an extension of the proposed route beyond Rouse Hill to meet the existing Richmond Line.[15] Various studies in support of the Epping to Castle Hill link were made during 2003; most of this work related to the proposed alignment of the route.[17] It was revealed on 12 August 2003 that Railcorp was considering a new $6 billion rail link that would connect Hornsby with Campbelltown via the Sydney CBD and that the North West rail link could form an extension to this route.[18]
On 9 June 2005 the State Government announced the Metropolitan Rail Expansion Plan (MREP), an $8 billion plan to add three new railway lines to the Sydney Trains network over the following 15 years. The North West Rail Link was one of the proposed railway lines, the other two being the South West Rail Link and the CBD Rail Link.[19] In 2005 the schedule was revised and a new completion date of 2017 was set.[20] In 2006 the construction schedule was revised with a new completion date of 2017. In April 2006, the NSW Transport Infrastructure Development Corporation released the North West Rail Link Project Application and Preliminary Environmental Assessment in support of the planning approval process.[19] On 20 November 2006, the government announced a staged plan for the North West Rail Link with train services to Castle Hill and Hills Centre in 2015, two years ahead of the original completion date of 2017.
Cancellation and North West Metro
In March 2008, the Government changed the project to a metro line dubbed the North West Metro and expanded the line to run all the way to the Sydney CBD via the suburbs of Ryde, Gladesville, Drummoyne and Pyrmont. On 23 October 2008, the NSW Government announced the CBD Metro instead, a shortened version of the North West Metro which would run from Rozelle to Central station, and the project was submitted to Infrastructure Australia for funding. It was announced that North West Metro may be extended to link from Rozelle Station to Epping and Macquarie Park in the future if the CBD Metro was built. Then, on 31 October 2008, the NSW Government announced that the North West Metro would be indefinitely deferred due to budgetary cuts.[21]
Resumption of original proposal
On 21 February 2010, two and a half months after Kristina Keneally had become Premier, the NSW Government revealed the cancellation of the Sydney Metro project in its Metropolitan Transport Plan[22][23] and returned to the North West Rail Link proposal. At the time, construction was anticipated to begin in 2017. In August 2010 the State Government applied to Infrastructure Australia for funding to accelerate the delivery of the project, but no funding was granted.[20]
2011 proposal
Following his victory in the NSW state election on 26 March 2011, newly elected Premier Barry O'Farrell announced that his first order of business would be to start construction on the North West Rail Link.[24] On 6 April 2011, Premier O'Farrell and newly installed Transport Minister Gladys Berejiklian announced the project team that will be responsible for construction and delivery of the North West Rail Link.[25] It is expected that initial planning and geotechnical investigation of the route corridor will begin by the end of 2011,[26][27] with construction beginning before the 2015 state election. Hills Labor Councillor Raymond Harty doubted these estimates and stated his belief that a construction start date in 2017 was more realistic.[28]
Call for tenders
On 15 May 2011, Transport Minister Gladys Berejiklian announced that a tender had been called for engineering, rail systems and architecture services.[29][30] A tender was called on 6 June 2011 for a financial and commercial services specialist.[31] The tender documents indicate the Government's desire to appoint a financial adviser to examine the possibility of securing funding from private sources.[32] As of July 2011, the preferred financial model (public-private partnership or otherwise) is unknown, but it is anticipated that the Government will finalise the funding plan by the end of 2011. As of 5 July 2011, no application for federal funding had been made to Infrastructure Australia, despite the need for federal funds for the project to proceed.[33]
Tenders were called on 10 June 2011 for a range of services including geotechnical work, master planning and urban design, scheduling and planning support, integrated transport and land use services, and legal services.[26][27][34] Applications for the first six of twelve tenders closed the week of 8 July 2011 with 44 proposals having been received from a range of Australian and international companies.[35][36] The first six tenders were for financial services, geotechnical investigations, integrated transport and land use studies, scheduling and program support, legal services, and master planning and urban design.[35] As part of the tender process, applicants were asked to demonstrate how they would design station precincts at the Rouse Hill, Samantha Riley Drive and Cudgegong Road sites.[36] The geotechnical information is required to determine the best method of tunnelling through the Hawkesbury sandstone that underlies much of the Sydney basin.[27]
Gladys Berejiklian announced on 14 July 2011 that the first major tender—for design services—had been awarded to a consortium led by AECOM Australia Pty. Ltd.[37][38][39][40] AECOM will be supported by Cox Architects Pty. Ltd., Grimshaw Architects and Parsons Brinckerhoff Australia Pty. Ltd. The consortium will be tasked with investigating route alignment options, rail systems, tunnel design, station locations and infrastructure planning.[38][39] AECOM also lodged applications for the master plan and integrated transport tenders.[40] Consulting firm Turner & Townsend were awarded the tender for cost planning services on 22 July 2011.[41][42][43] According to Turner & Townsend, the company's role will be to "manage the project budget and demonstrate to the taxpayer that they are receiving maximum value for money".[42]
Impasse over Federal funding
The Gillard Federal Government refused to commit any funding to the North West Rail Link because it favoured completion of the Parramatta to Epping section of the Parramatta to Chatswood route.[44] The refusal dates back to a promise made during the 2010 Federal election campaign, when Gillard's Australian Labor Party announced the federal government would fund 80 per cent ($2.1 billion) of the construction of the Parramatta to Epping rail link if it were re-elected at the 2010 Federal election.[45][46][47]
NSW Premier Barry O'Farrell asked Prime Minister Gillard in his first official meeting with her after becoming Premier in April 2011 to divert the Federal funds allocated to the Parramatta to Epping rail link to the North West Rail Link project.[48] Despite this, the Federal Government did not allocate any funds to the North West Rail Link in the 2011 Budget.[49] At least part of the reason for the snub, apart from the Federal Government's transport priorities, is the fact that the O'Farrell State Government did not submit a project proposal for the North West Rail Link to Infrastructure Australia.[50]
Results of a cost-benefit analysis released in November 2011 indicate that the North West Rail Link will be three times more beneficial to New South Wales than the Parramatta to Epping extension.[51] The report also indicated that the cost of constructing the Parramatta–Epping line would cost $1.78 billion more than initially expected.
Infrastructure Australia formally rejected Infrastructure NSW's request for $2.1 billion in funding in May 2012, saying the project is "not the highest priority" transport project for Sydney. Instead, Infrastructure Australia suggested an expansion of the bus network and better transport links with Parramatta.[52] Infrastructure Australia cited the lack of a completed proposal and lack of information on cost, infrastructure and development as reasons for the rejection.[53] The State Government vowed to build the line with or without federal funding.[53][54]
History of Epping to Chatswood railway line
The Epping to Chatswood railway line opened in 2009 as a heavy rail line, initially as a shuttle service between Chatswood and Epping. The line was later integrated into the Northern Line. During O'Farrell time as premier, the government announced that the line will be closed and converted to rapid transit standards.
History of current project
By June 2015, media releases from Transport for NSW used the name "North West Rail Link" to address the whole section between Rouse Hill and Chatswood and not just the unbuilt part.[55] On 4 June 2015, Premier Mike Baird and Minister for Transport & Infrastructure Andrew Constance announced the rebranding of the Sydney Rapid Transit to the Sydney Metro. In conjunction with the rebranding, the North West Rail Link was renamed Sydney Metro Northwest, the first stage of the Sydney Metro.[56] It is to link to the rest of Sydney Metro at Chatswood.
Construction
2011-12 State Budget
The NSW Government allocated $314 million towards the North West Rail Link in the 2011-12 State Budget. $222 million of this will go towards buying land along the proposed route alignment.[57] $2.5 billion was provisionally allocated to the North West Rail Link over the next four years.[58]
Commencement of geotechnical work
Coffey Geotechnics supported by AECOM were awarded the tender for geotechnical drilling services in August 2011, and drilling began on 7 September 2011. A drilling rig was set up in a park opposite the Castle Towers shopping centre at Castle Hill, where one of the underground stations will be built.[59] At least 150 boreholes with a diameter of up to 15 centimetres (5.9 in) will be drilled up to 75 metres (246 ft) deep along the proposed alignment between Epping and Rouse Hill in order to develop an understanding of the geological profile.[58] The drilling is anticipated to take about 9 weeks to complete.[60]
Dirt from the tunnelling process will be recycled and distributed across Sydney.[61]
Major contracts awarded
There are three major contracts for the construction of the North West Rail Link. In June 2013, the tunnelling contract was awarded to a joint venture involving Leighton Holdings owned Thiess and John Holland Group, and Dragados.[62] In December 2013, the skytrain and surface construction contract was awarded to a joint venture between Italian firms Impregilo and Salini. The $340 million contract includes a 270-metre cable-stayed bridge over Windsor Road at Rouse Hill.[63] A third and final major contract to build the stations, operate the rail link and build single deck trains will be announced by the end of 2014.[63]
Closure of the Epping to Chatswood railway line
The Epping to Chatswood railway line will be closed in 2018 for around seven months and converted to rapid transit standards. More than 300 bus services on five temporary bus routes will replace trains during the closure.[64]
Operation of the line
As of December 2011, the State Government had not ruled out the possibility of contracting the operation, rolling stock and signalling on the North West Rail Link to private operators as part of a public-private partnership.[65]
We are focused on the longer term rail options. It's got to work as a single network, the whole network, but we are looking at private sector involvement in those as well. And we've got an open mind.— Les Wielinga, Director-General, Transport NSW
In May 2013 it was announced that two consortium had been shortlisted to operate the line:[66]
- Northwest Rapid Transit consisting of John Holland Group, Leighton Contractors, MTR Corporation, Plenary Group and UGL Rail
- TransForm consisting of Bombardier Transportation, John Laing Investments, Macquarie Capital, McConnell Dowell, Serco and SNC-Lavalin Capital
On 24 June 2014, the Northwest Rapid Transit consortium was selected as the preferred operator to deliver the North West Rail Link operations contract.[67]
Places serviced
- Chatswood-Chatswood (West)
- North Ryde-North Ryde
- Macquarie Park-Macquarie Park
- Macquarie University-Macquarie Centre, Macquarie University, Marsfield
- Epping-Epping, North Epping, Marsfield, Carlingford
- Cherrybrook-Cherrybrook, Koala Park, West Pennant Hills, Dural
- Castle Hill-Castle Hill, Castle Towers, Baulkham Hills
- Showground-Showground, Glenhaven, Dural, Baulkham Hills
- Norwest-Norwest Business Park, Seven Hills
- Bella Vista-Bella Vista, Glenwood, Kings Langley
- Kellyville-Kellyville, Stanhope Gardens, Beaumont Hills
- Rouse Hill-Rouse Hill, Rouse Hill Town Centre, Box Hill, Vineyard, Riverstone
- Cudgegong Road-The Ponds
Proposed route
Original proposal (original North West Rail Link)
The original North West Rail Link route proposal was planned to be 22 km (14 mi) in length, consisting of a 16 km (9.9 mi) tunnel (underground) section from Epping to the proposed Burns Road Station, followed by a 4 km (2.5 mi) section above ground from Burns Road Station (now Kellyville Station) to Rouse Hill. A train stabling facility was proposed to the north west of Rouse Hill Town Centre.
The latest version of the original proposal proposed to connect the North West Rail Link alignment to the Epping to Chatswood Rail Link via a tunnel between Epping and Franklin Road (now Cherrybrook) stations, whereas the earliest version of the original proposal had the route alignment connect with the existing Northern Line north of Cheltenham.[68] The direct route proposed using the stub tunnels originally built for the deferred Parramatta Rail Link between Parramatta and Epping.[68] New stub tunnels for the Parramatta Rail Link were to be constructed so that if the Epping to Parramatta line were completed, trains from Parramatta would have also been able to link into the Epping-Chatswood Line.[68]
Six new stations were proposed along the North West Rail Link:
- Epping
- Cherrybrook (Franklin Road)
- Castle Hill
- Hills Centre
- Norwest
- Kellyville (Burns Road)
- Rouse Hill
The line was scheduled to open in two stages: the first stage from Epping to Hills Centre Station was scheduled for completion by 2015 (originally 2017), and the second stage from Hills Centre to Rouse Hill Station was scheduled for completion by 2017. Construction was scheduled to begin in 2010. The original proposal called for off-peak rail service of four trains per hour, with six to eight trains per hour in peak periods. The route was expected to carry six to eight million passengers per year.
The line was originally part of the Metropolitan Rail Expansion Program (MREP) proposed by the Carr Government in 2005.[69] The MREP included the South West Rail Link, North West Rail Link and the CBD Rail Link and was intended to augment transport links between the major new growth and employment areas of the Sydney metropolitan region. The route proposal was abandoned in 2008 by the Iemma Government in favour of the development of a metro-style rapid transit system.[69][70]
-
Original proposed station at Castle Hill
-
Franklin Road station proposal in the original North West Rail Link
2011 proposal (original North West Rail Link)
When the O'Farrell Government took office, it proposed that the line would form part of the mainline network and would be served by double deck rolling stock, like other rail lines in Sydney. A report released in July 2011 indicated that upon opening of the line, four to six trains per hour would connect Rouse Hill station with Chatswood station via Epping.[71][72] Of these, only as few as 2 trains per hour would be able to continue from Chatswood to the CBD due to capacity constraints on the North Shore line.[73]
The design was changed to a driverless rapid transit line, featuring more frequent, lower capacity single deck trains.[74] All trains will terminate at Chatswood, with passengers required to change to North Shore line trains to continue to the city.
The route proposal put forward in May 2011 by the State Government is a new 23-kilometre (14 mi) rail route that calls for six new stations, and the possibility of two more at some point in the future.[20][75] The proposed stations are:
- (connection with existing Sydney Trains system at Epping)
- Cherrybrook
- Castle Hill
- Hills Centre
- Norwest 1
- Norwest 2[76]
-
Kellyville (Burns Road)[76] - Samantha Riley Drive (possible)
- Rouse Hill
- Cudgegong Road (possible)
Current proposal
By 2013, the confirmed stations for the North West Rail Link were listed below, but were separated from the possible line extension to the city.
After the rebranding of the project as Sydney Metro NorthWest, the current proposed stations are listed below:[77]
- (connection with future Sydney Metro City & South West sections)
- Chatswood (currently part of existing Sydney Trains system)
- North Ryde (currently part of existing Sydney Trains system)
- Macquarie Park (currently part of existing Sydney Trains system)
- Macquarie University (currently part of existing Sydney Trains system)
- Epping (currently part of existing Sydney Trains system)
- Cherrybrook
- Castle Hill
- Showground
- Norwest
- Bella Vista
- Kellyville
- Rouse Hill
- Cudgegong Road
Cherrybrook Station is being built as a station in a cutting, open to the sky, but below ground level while Castle Hill, Showground, Norwest and Cudgegong Road stations will be underground, whereas Kellyville and Rouse Hill will be above ground. The twin tunnels between Epping and Kellyville, at 15.5 km (9.6 mi) long,[20] will be the longest rail tunnels in Sydney when they are built.[26] They will also be the deepest tunnels in Sydney: 67 m (220 ft) below ground at the deepest point below the intersection of Pennant Hills Road and Castle Hill Road—deeper than the floor of Sydney Harbour (about 50 m (160 ft)), and much deeper than the deepest point of the City Circle tunnels at St James (about 11 m (36 ft)).[78] Most of the tunnel will be bored, although the section at Kellyville will be constructed using cut-and-cover techniques.[78][79] Major tunnelling began in 2014.[80]
A new train stabling yard will be constructed at Tallawong Road in Rouse Hill, with room for 16 train sets.
3,000 new parking spaces will be provided across proposed carparks at Cherrybrook, Hills Centre and Kellyville stations.[20]
Possible future extensions
Previously there were long term plans to extend the proposed heavy-rail North West Rail Link to meet the existing Richmond railway line near Vineyard.[81] However, the location of the alignments were never finalised and further investigation and studies would have been required.
A possible extension from Castle Hill towards Oak Hill Drive via Dural and Galston to Hornsby Heights. Another plausible one is Chatswood, Lane Cove, Gladesville, Top Ryde, Putney, Meadowbank. Carlingford, North Rocks, Castle Hill.
State Government documents, dated 13 May 2011, suggest an intention to eventually extend the line to meet the Richmond line near Schofields, two stations south of Vineyard.[75] A Transport Department report dated 9 June 2011 shed more light on such plans, suggesting an extension of the North West Rail Link beyond Rouse Hill to meet the Richmond line at Schofields, Riverstone, or beyond.[82] If the extension is built, it would likely service the planned Sydney Business Park at Marsden Park.
In 2013, a new proposal was raised to extend the North West Rail Link, by building a metro-style tunnel from just south of Chatswood Station via St Leonards and North Sydney and under the Sydney Harbour towards Central and Redfern, before joining the newly converted metro lines towards Hurstville, Bankstown and Liverpool.[83] This proposed extension to Bankstown was named the Sydney Metro City & Southwest in June 2015 when it was grouped together with the entire North West Rail Link to form the newly announced Sydney Metro system. The proposal is still under planning at the time of the naming.
It has also been discussed that a train line may run up the Northern Beaches from Chatswood, Frenches Forest, Dee Why, Mona Vale, Manly, Mosman, St Leonards[84][85][86]
Criticism
- Transport experts suggest that unless a second heavy rail link is built across Sydney Harbour from the North Shore to the CBD, the North West Rail Link will only increase congestion on the existing North Shore Line, which crosses the Sydney Harbour Bridge.[87] The fact that a second harbour crossing is necessary has been known for some time.[14][88][89] This is because the Sydney Harbour Bridge can only accommodate 20 trains per hour, and currently already sees 18 services per hour during peak periods.[73] In addition, it is expected that passenger congestion on existing North Shore line services will increase because CBD-bound passengers on North West Rail Link services that terminate at Chatswood will be forced to transfer to the North Shore line services to continue their journeys.
- Concern has been expressed that the proposed configuration of the North West Rail Link will not allow eastbound trains coming off the new alignment at Epping to continue south on the existing Northern Line to Strathfield station.[72] This will affect the number of trains per hour that the North West Rail Link can accommodate.
- E-mails originating within the NSW Treasury by Principal Financial Analyst, Rodney Forrest to Rail Corporation Manager of Finance, Peter Crimp were released as part of a Parliamentary Standing Order 52 in October 2011 indicating that the North West Rail Link would have to be subsidised by the state government by about $80 per passenger based on predictions of population and passenger volumes in 2021.[90][91][92] Across the Sydney Trains network this equates to about $30 per passenger in 2021, compared to $10 per passenger in 2010. The modelling by NSW Treasury estimates that the North West Rail Link would generate only 9 million new passengers annually, or 2.15% of all CityRail trips. A Hills Shire councillor questioned the size of these estimates based on the projected population increase in the region over the next 8 years.[28]
- The government has decided to use a type of train on the NWRL that is quite different from existing trains[93] and has contracted to bore tunnels slightly too small to ever be used by existing Sydney double-deck trains.[94] Reviews by independent experts unsurprisingly show that serious constraints on future expansion of the system will result.[95][96]
- There has been no estimate of how long it will take to convert existing tracks for the new trains however the conversion will certainly be disruptive.[97]
- The type of train chosen (single-deck with limited seating) is optimised for short trips with closely spaced stations and is not appropriate for 40 km trips with stations spaced about 3 km apart.[94] Expert analysis shows that double-deck trains permit more seats to be carried per hour; passengers on long trips prefer to be comfortably seated.[98] A rebuttal to this claim stated that longitudinal seating, which is actually the standard form of seating on most metro trains around the world, allows for ease of access particularly for those with prams or trolleys. In the instance of journeys in which many people will be hoping on and off, longitudinal seating allows for people to stand and exit from their seat easily, as well as providing more standing or walking room along the carriage.[99]
- Planned eventual expansion of the single-deck system will prevent or delay necessary expansion of services to the western suburbs of Sydney.[94]
- The government has announced that the popular bus services which connect the Sydney CBD with the north-west using the M2 motorway will be withdrawn when the NWRL opens and be replaced by rail feeder services to stations on the NWRL.[100] Research has shown that trips from most of the north-west will take longer on bus-train combination than on bus alone.[101]
- Critics have noticed that public submissions on the disadvantages of the proposal have been dismissed.[102] Meanwhile, the government member chiefly responsible for the NWRL has twice resorted to personal abuse in Parliament when asked about the project.[103][104] Further, she has been criticised for not explaining and justifying government decisions.[105]
- The O'Farrell government was told it would save $200 million from building the north-west rail link with smaller tunnels - a decision that will mean the new line will never be able to run double-deck trains with more seats. Documents obtained after a Freedom of Information (FoI) request revealed the lengthy effort inside parts of the transport bureaucracy to warn the government about the major inconvenience to northern suburbs commuters from terminating the $8.3 billion north-west rail link at Chatswood[106]
- Worry about buses replacing trains[107]
- Controversy about changes and extensions to Strathfield line and further alterations that involve changes which were from Carlingford to Epping or Eastwood of Parramatta.[108]
- The discomfort of standing until arrival in the city with commuters possibly needing to stand for up to 37 km (50 minutes) of their journey.[109]
See also
- Sydney Metro City & Southwest
- Sydney Metro (2008 proposal)
- Original railway to the Hills District
- Proposed railways in Sydney
- Rapid transit
- Transport in Australia
References
- ↑ "Project Overview". Sydney Metro. Transport for NSW. Retrieved 13 July 2015.
- 1 2 "Funding secured: Sydney Metro to be a reality". Transport for NSW. 4 June 2015. Retrieved 13 July 2015.
- ↑ "Eight major rail projects for Sydney" (Press release). Carl Scully MP. 23 November 1998. Retrieved 8 July 2011.
- ↑ "Does study give rail link the thumbs down?" (PDF) (Press release). Michael Richardson MP. 26 October 2000. Retrieved 8 July 2011.
- ↑ "Thumbs up for Council stance on Mungerie Park" (PDF) (Press release). Michael Richardson MP. 5 July 2000. Retrieved 8 July 2011.
- ↑ "Government prevaricates on rail link report" (PDF) (Press release). Michael Richardson MP. 13 December 2000. Retrieved 8 July 2011.
- ↑ "Castle Hill rail link's viability in doubt" (PDF) (Press release). Michael Richardson MP. 9 January 2001. Retrieved 8 July 2011.
- ↑ "Ombudsman begins investigation into rail study" (PDF) (Press release). Michael Richardson MP. 14 March 2001. Retrieved 8 July 2011.
- ↑ "Castle Hill rail line becomes the missing link" (PDF) (Press release). Michael Richardson MP. 6 March 2001. Retrieved 8 July 2011.
- ↑ "Castle Hill rail link may never be built" (PDF) (Press release). Michael Richardson MP. 22 March 2001. Retrieved 8 July 2011.
- ↑ "Carr confirms Castle Hill rail link is dead" (PDF) (Press release). Michael Richardson MP. 27 March 2001. Retrieved 8 July 2011.
- ↑ "Budget delivers $47 million for Windsor Road" (PDF) (Press release). Michael Richardson MP. 30 May 2011. Retrieved 8 July 2011.
- ↑ State Infrastructure Strategic Plan: Emerging PFP Opportunities and Major Project Proposals Over $100 million (PDF) (Report). New South Wales Government. 2002. Retrieved 9 July 2011.
- 1 2 "Release of preferred route for the proposed rail link for Sydney's north west" (Press release). Carl Scully MP. 10 March 2002. Retrieved 8 July 2011.
- 1 2 "New studies to progress North West rail link" (Press release). Carl Scully MP. 3 October 2002. Retrieved 8 July 2011.
- ↑ Transport NSW Annual Report 2002 (PDF) (Report). Transport NSW. 2002. Retrieved 8 July 2011.
- ↑ Minstry of Transport Annual Report 2003 (PDF) (Report). NSW Ministry of Transport. 2003. Retrieved 8 July 2011.
- ↑ Kerr, Joseph (12 August 2003). "The fast track - $6bn plan to unlock the rail grid". The Sydney Morning Herald. Archived from the original on 8 December 2005. Retrieved 9 July 2011.
- 1 2 Sinclair Knight Merz (April 2006). North West Rail Link Project Application and Preliminary Environmental Assessment (PDF) (Report). Transport Infrastructure Development Corporation. Retrieved 22 July 2011.
- 1 2 3 4 5 North West Rail Link Project Overview (Report). NSW Transport. 2011. Retrieved 22 July 2011.
- ↑ Benson, Simon (31 October 2008). "Northwest Metro rail link officially shelved". The Daily Telegraph (Sydney, New South Wales). Retrieved 6 April 2011.
- ↑ NSW Government. "Metropolitan Transport Plan: Connecting the City of Cities". Retrieved 7 April 2011.
- ↑ Sydney Metro (2010). 2010 Annual Report (PDF). NSW Government. Retrieved 7 April 2011.
- ↑ ABC News (27 March 2011). "O'Farrell hails new political landscape". Australian Broadcasting Corporation. Retrieved 6 April 2011.
- ↑ Saulwick, Jacob (6 April 2011). "Former CBD Metro chief to drive north-west rail link". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 6 April 2011.
- 1 2 3 "Drillers called for Northwest Rail Link". Hills Shire Times (Castle Hill, New South Wales). 10 June 2011. Retrieved 13 June 2011.
- 1 2 3 "Test drilling tenders called for North West Rail Link" (PDF) (Press release). Gladys Berejiklian MP. 10 June 2011. Retrieved 21 July 2011.
- 1 2 Petrinic, Isabell (8 November 2011). "North West Rail Link: Don't give false expectations". Hills News (Castle Hill, New South Wales). Retrieved 21 January 2015.
- ↑ Trieste, Laura (19 May 2011). "Tenders called for northwest rail link design". Rouse Hill Times (Rouse Hill, New South Wales). Retrieved 26 May 2011.
- ↑ "Tender called for major design works for north west rail link" (PDF) (Press release). Gladys Berejiklian MP. 15 May 2011. Retrieved 26 May 2011.
- ↑ Murray, Therese (6 June 2011). "Key tender called on northwest rail link today". Hills Shire Times (Castle Hill, New South Wales). Retrieved 22 July 2011.
- ↑ Saulwick, Jacob (7 June 2011). "All aboard O'Farrell's rail funding express". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 8 June 2011.
- ↑ "No funding deal for north-west rail link". ABC News. 5 July 2011. Retrieved 10 July 2011.
- ↑ "Drillers called for Northwest Rail Link". Hills Shire Times (Castle Hill, New South Wales). 10 June 2011. Retrieved 22 July 2011.
- 1 2 "Strong response to North West Rail Link tenders" (PDF) (Press release). Gladys Berejiklian MP. 8 July 2011. Retrieved 21 July 2011.
- 1 2 Butson, Tyron (12 July 2011). "Searching far and wide for rail tenders". Hills Shire Times (Castle Hill, New South Wales). Retrieved 21 July 2011.
- ↑ Saulwick, Jacob (14 July 2011). "Spot on: light rail plan links Anzac Parade and Randwick". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 21 July 2011.
- 1 2 "First major tender awarded for North West Rail Link design works" (Press release). AECOM. 14 July 2011. Retrieved 21 July 2011.
- 1 2 "First major tender awarded for North West Rail Link design works" (PDF) (Press release). Gladys Berejiklian MP. 14 July 2011. Retrieved 21 July 2011.
- 1 2 Butson, Tyron (19 July 2011). "Global giants fight to get on board North West Rail Link". Hills Shire Times (Castle Hill, New South Wales). Retrieved 21 July 2011.
- ↑ Butson, Tyron (22 July 2011). "Company to oversee North West Rail Link costings". Hills Shire Times (Castle Hill, New South Wales). Retrieved 3 August 2011.
- 1 2 "Turner & Townsend wins North West Rail Link contract" (Press release). Turner & Townsend. 1 August 2011. Retrieved 3 August 2011.
- ↑ "O'Farrell Govt pressing ahead with North West Rail Link" (PDF) (Press release). Gladys Berejiklian MP. 22 July 2011. Retrieved 5 August 2011.
- ↑ Clennell, Andrew (8 July 2011). "Barry O'Farrell offers Julia Gillard a rail switch". The Daily Telegraph (Sydney, New South Wales). Retrieved 25 July 2011.
- ↑ Jordan, Bev (11 August 2010). "Epping-Parramatta link panned". Rouse Hill Times (Rouse Hill, New South Wales). Retrieved 25 July 2011.
- ↑ Coorey, Phillip (11 August 2010). "Gillard's $2b transport fix". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 25 July 2011.
- ↑ Farr, Malcolm (11 August 2010). "All aboard the PM's Parramatta express". The Daily Telegraph (Sydney, New South Wales). Retrieved 25 July 2011.
- ↑ Sikora, Kate (11 April 2011). "Barry O'Farrell ready to rail at Julia Gillard for the North West Rail Link". The Daily Telegraph (Sydney, New South Wales). Retrieved 26 July 2011.
- ↑ Haynes, Rhys (16 May 2011). "Alternate route to North West Rail Link has been rejected by the State Government". The Daily Telegraph (Sydney, New South Wales). Retrieved 26 July 2011.
- ↑ Benson, Simon (5 July 2011). "Northwest link plan misses first stop". The Daily Telegraph (Sydney, New South Wales). Retrieved 26 July 2011.
- ↑ Willoughby, Sally (29 November 2011). "North West Rail Link: Transport Study". Hills News (Castle Hill, New South Wales). Retrieved 2 December 2011.
- ↑ Clennell, Andrew; Yamine, Evelyne (7 May 2012). "North West told to Link up with a bus instead". The Daily Telegraph (Sydney, New South Wales). Retrieved 7 May 2012.
- 1 2 Butson, Tyron (8 May 2012). "End of line for North West Rail Link says Treasurer Wayne Swan". Express Advocate (Gosford, New South Wales). Retrieved 9 May 2012.
- ↑ "NW Rail Link to be built despite funding rejection". ABC News. 8 May 2012. Retrieved 9 May 2012.
- ↑ Breaking new ground on Sydney's mega-project as new station design revealed, Transport for NSW, Retrieved 6 August 2015
- ↑ Funding secured: Sydney Metro to be a reality, Transport for NSW, Retrieved 6 August 2015
- ↑ "NSW Government Backs Key Sydney Rail Links" (Press release). Gladys Berejiklian MP. 6 September 2011. Retrieved 7 September 2011.
- 1 2 "Full Steam Ahead on North West Rail Link" (Press release). Barry O'Farrell MP. 7 September 2011. Retrieved 7 September 2011.
- ↑ "Work begins on North West Rail Link". The Sydney Morning Herald (Sydney, New South Wales). 7 September 2011. Retrieved 10 September 2011.
- ↑ Willoughby, Sally (13 September 2011). "Budget: Costings of North West Rail Link". Hills News (Castle Hill, New South Wales). Retrieved 13 September 2011.
- ↑ Ranke, Angela (18 March 2015). "3.8 million tonnes of dirt from North West Rail Link to be recycled far and wide across Sydney". The Daily Telegraph. Retrieved 29 March 2015.
- ↑ "Getting on with the job: $1.5 billion Tunnelling Contract on North West Rail Link" (Press release). Transport for NSW. 2013-06-25. Retrieved 2013-06-26.
- 1 2 "North West Rail Link $340 million skytrain contract awarded" (Press release). Transport for NSW. 2013-12-18. Retrieved 2014-01-02.
- ↑ Epping to Chatswood upgrade overview, Sydney Metro Northwest, Retrieved 5 August 2015
- ↑ Saulwick, Jacob (3 December 2011). "Private operators in the mix for north-west rail link". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 2 December 2011.
- ↑ Detention company could run new rail link Sydney Morning Herald 2 May 2013
- ↑ Major milestones reached on North West Rail Link as preferred operator selected, Transport for New South Wales, Retrieved 24 June 2014
- 1 2 3 New South Wales Government, TIDC North West Rail Link - Preferred Project Report Volume 1 May 2007. Retrieved 18 March 2008.
- 1 2 Besser, Linton (26 February 2008). "Bye heavy rail, now for a north-west metro". The Sydney Morning Herald. Retrieved 7 June 2011.
- ↑ Besser, Linton (19 March 2008). "Great idea, but white elephants trumpet". The Sydney Morning Herald. Retrieved 7 June 2011.
- ↑ Haynes, Rhys (6 July 2011). "New northwest rail link more a shuttle". The Daily Telegraph. Retrieved 7 July 2011.
- 1 2 Saulwick, Jacob (8 July 2011). "Fears of too few services on north-west rail link". The Sydney Morning Herald. Retrieved 8 July 2011.
- 1 2 Saulwick, Jacob (16 February 2011). "New north-west line might cause cuts to others, says advice". The Sydney Morning Herald. Retrieved 8 July 2011.
- ↑ "Trains on new Sydney line to be driverless". ABC News. 7 June 2013. Retrieved 30 August 2013.
- 1 2 Rhys Haynes; Andrew Clennell (27 May 2011). "Let's go forth by North West rail". The Daily Telegraph. Retrieved 26 May 2011.
- 1 2 Saulwick, Jacob (22 August 2011). "Rail link team considers adding three more stations". The Sydney Morning Herald. Retrieved 22 August 2011.
- ↑ "North West Rail Link". Transport for New South Wales. Retrieved 2013-06-07.
- 1 2 Butson, Tyron (6 July 2011). "Northwest rail link tunnel deeper than harbour". Northern District Times. Retrieved 10 July 2011.
- ↑ "Rail link takes shape in Sydney's north-west". ABC News. 27 May 2011. Retrieved 13 June 2011.
- ↑ North-west rail link tunnel carved out by boring Elizabeth, Sydney Morning Herald, Published 18 November 2014, Retrieved 5 August 2015
- ↑ North West Metro Stakeholder Engagement Briefing and Consultation Forum Outcomes Report. 15 August 2008
- ↑ Haynes, Rhys (20 June 2011). "Plans to extend North West rail link". The Daily Telegraph. Retrieved 7 July 2011.
- ↑ Clennell, Andrew (6 December 2013). "Second Sydney Harbour crossing to follow North West Rail". The Telegraph News. Retrieved 20 January 2014.
- ↑ http://www.dailytelegraph.com.au/newslocal/northern-beaches/early-planning-under-way-for-possible-northern-beaches-rail-line/story-fngr8hax-1227451373044
- ↑ http://www.smh.com.au/nsw/sydney-traffic/sydneys-northern-beaches-look-to-be-major-beneficiaries-of-state-budget-transport-plans-20140611-zs4cs.html
- ↑ http://www.pedestrian.tv/news/arts-and-culture/sydneys-northern-beaches-may-finally-be-getting-a-/40e0fb59-0949-4cb9-a287-fbfc8e6c24cd.htm
- ↑ Chang, Charis (24 June 2011). "Ease or squeeze: Northwest rail link will transform North Shore". North Shore Times. Retrieved 7 July 2011.
- ↑ West, Andrew (31 May 2010). "Second harbour crossing - or chaos". The Sydney Morning Herald. Retrieved 7 July 2011.
- ↑ Haynes, Andrew (27 October 2010). "Harbour underwater rail option to combat gridlock". The Daily Telegraph. Retrieved 7 July 2011.
- ↑ Saulwick, Jacob (26 October 2011). "North-west rail line costs revealed in emails". The Sydney Morning Herald (Sydney, New South Wales). Retrieved 2 December 2011.
- ↑ Butson, Tyron (31 October 2011). "North West Rail Link passengers could prove costly". Rouse Hill Times (Rouse Hill, New South Wales). Retrieved 2 December 2011.
- ↑ Willoughby, Sally; Saulwick, Jacob (22 November 2011). "North West Rail Link funded by the private sector?". Hills News (Castle Hill, New South Wales). Retrieved 2 December 2011.
- ↑ , Sydney's Rail Future, Transport for NSW, June 2012
- 1 2 3 , Fixing the trains in Sydney - 1885 revisited, Sandy Thomas, February 2013
- ↑ Day, Dick (29 June 2012). "Railroaded? Metro rail alternatives for western Sydney". The Sydney Morning Herald. Retrieved 16 July 2013.
- ↑ Saulwick, Jacob (4 July 2012). "Tunnel too small could make rail link a bridge too far". The Sydney Morning Herald. Retrieved 17 July 2013.
- ↑ , State-of-the-art North West Rail Link, NWRL website as at 17 July 2013
- ↑ , Independent Public Inquiry, Appendix 3 by Alex Wardrop, Fitness for Duty: The Capabilities of double and single deck rolling stock
- ↑ [sydneymetro.info/home/documents/29348/download "Early community consultation"] Check
value (help). Transport for NSW. July 2015.|url=
- ↑ Saulwick, Jacob (30 October 2012). "Bus services to go when rail link opens". The Sydney Morning Herald. Retrieved 16 July 2013.
- ↑ , The North West Rail Link: winners and losers in the locality of the North West area, by Clifton, Hensher and Mulley - ATRF2012.
- ↑ Submissions report at Chapter 7 e.g. 7.5.5 issue d (suitability of single-deck trains) on page 7-75 and response on page 7-76
- ↑ , NSW L.A. Hansard 6 September 2012
- ↑ , NSW L.A. Hansard 20 June 2013
- ↑ Saulwick, Jacob (13 July 2013). "Share with us, minister, we are listening". The Sydney Morning Herald. Retrieved 16 July 2013.
- ↑ http://www.smh.com.au/nsw/warnings-on-northwest-rail-link-plan-ignored-20140129-31mvw.html
- ↑ http://www.rousehillcourier.com.au/story/3026038/bus-service-will-match-trains-north-west-rail-link-team/
- ↑ http://www.smh.com.au/nsw/secret-rail-plan-for-sydney-would-create-massive-and-costly-upheaval-to-existing-network-20150219-13jzvt.html
- ↑ http://www.dailytelegraph.com.au/news/nsw/mumbai-express-is-a-standing-joke-number-of-seats-on-sydneys-north-west-rail-link-could-be-drastically-cut/story-fni0cx12-1227073324575
External links
|