Gujarat Solar Park
Gujarat Solar Park | |
---|---|
Canal top solar plant | |
Location of Gujarat Solar Park in India | |
Country | India |
Location | Gujarat |
Coordinates | 23°54′11″N 71°12′06″E / 23.903056°N 71.201667°ECoordinates: 23°54′11″N 71°12′06″E / 23.903056°N 71.201667°E |
Status | Operational |
Commission date | 2011, 2012 |
Solar farm | |
Type | Flat-panel PV |
Site area | 2,000 ha (4,942 acres) |
Power generation | |
Nameplate capacity |
856.81 MW Planned: 968 MW |
Gujarat Solar Park is the name used for a group of solar parks being constructed in Gujarat, India. This makes Gujarat as Asia's largest solar park hub.[1] Certificates of completion were issued on 19 April 2012, for a total of 605 MW, which included some sections that were already operational, and 856.81 MW had been completed by 31 March 2013. One is the Charanka Solar Park, a group of 17 thin-film photovoltaic (PV) power systems, on a 2,000-hectare (4,900-acre) site in the district of Patan.[2]
The solar park is expected to save around 8 million tonnes of carbon dioxide from being released into the atmosphere and save around 900,000 tonnes of natural gas per year.[3][4][5][6][7]
A total of 84 developers have registered to build a total of 968.5 MW,[8] from 1 to 40 MW. An increase to 1,000 MW is expected to be completed by 2013.[9]
Power purchase agreement
Rs 15 (about USD 0.29) per kWh for the first 12 years and Rs 5 (about USD 0.10) per kWh from the 13th to 25th year.[10] The national solar policy has fixed tariffs of Rs17 for photovoltaic and Rs15 for solar thermal for 25 years.[8]
About 600 MW were completed prior to the deadline of 28 January 2012 to receive the above tariff. Systems completed after that date are subject to a lower tariff.[11]
Solar park locations
Location | District | Site co-ordinates | Nominal Power (MWp) | Production (Annual GW·h) |
Developer | Notes |
---|---|---|---|---|---|---|
Jafrabad | Amreli | 20°52′34″N 71°16′57″E / 20.87611°N 71.28250°E | 5 | 8.322 | Sunkon Energy | [14] |
Wadgam | Anand | 22°19′12″N 72°25′48″E / 22.32000°N 72.43000°E | 15 | 25.846 | Acme Tele Power | |
Isanpur | Anand | 22°28′51″N 72°31′25″E / 22.48083°N 72.52361°E | 1 | 1.533 | Harsha Engineers | |
Gunthawada[10][15][16][17] | Banaskantha | 23°55′07″N 71°56′28″E / 23.91861°N 71.94111°E[18] | 15.2 | 26.28 | Precious (Moser Baer) | Commissioned 11 October 2011 |
Gunthawada[10][15][16][17] | Banaskantha | 23°54′40″N 71°55′52″E / 23.91111°N 71.93111°E[18] | 15 | 25.9 | Solitaire (Moser Baer) | Commissioned 11 October 2011, with Precious cost Rs 465 crore, area 305 acre, 236,000 Thin Film modules[19] |
Dhanera | Banaskantha | 24°31′27″N 72°12′12″E / 24.52417°N 72.20333°E | 25 | 45.377 | Sand Land Real Estate | |
Bharuch | 1 | MBH Power | ||||
Gandhinagar | 1 | GSEC-TPS | ||||
Gandhinagar | 1 | PDPU-GPCL-GEDA | ||||
Mithapur | Jamnagar | 22°36′N 72°07′E / 22.600°N 72.117°E | 25.0 | Tata Power | Commissioned 25 January 2012 | |
Shiloj | Junagadh | 22°49′09″N 71°00′32″E / 22.81917°N 71.00889°E[20] | 10 | 19.585 | Mono Steel Solar | Output decreases 0.7%/year from 20 GWh |
Bitta[21] | Kutch | 23°15′46″N 69°01′27″E / 23.26278°N 69.02417°E[22] | 40.0 | 66.576 | Adani Power | Completed January 2012 using 400,000 modules.[23] Completed in 150 days at a cost of Rs 400 crore.[24] (6760 million INR) 100 MW planned |
Shivlakha | Kutch | 5 | Backbone | |||
Bhuj | Kutch | 1 | Essar Power | |||
Panandhro | Kutch | 5 | GMDC | |||
Pratapgarh | Kutch | 23°21′59″N 70°44′41″E / 23.36639°N 70.74472°E[25] | 9 | 13.451 | Integrated Coal Mining (ICML) | 0.5 MW Amorphous Si, 0.5 MW CdTe, 8 MW Crystalline Si |
Shivlakha | Kutch | 23°21′54″N 70°37′26″E / 23.36500°N 70.62389°E[26] | 5 | 8.87 | Konark Gujarat | Vikram Solar |
Shivlakha | Kutch | 23°19′28″N 70°24′01″E / 23.32444°N 70.40028°E[27] | 20 | 30.835 | Solar Semiconductor | |
Karmaria | Kutch | 23°12′34″N 70°13′56″E / 23.20944°N 70.23222°E[28] | 15.401 | 21.108 | Sun Borne | Solar World SW-230, cost 2102 million Rs, output is derated 1%/year |
Khirsara | Kutch | 23°21′32″N 70°03′14″E / 23.35889°N 70.05389°E[29] | 5 | 8.147 | Unity Power | SF-145-L 145Wp Copper Indium Selenide |
Khirsara | Kutch | 23°21′37″N 70°03′15″E / 23.36028°N 70.05417°E | 15 | Welspun Urja Gujarat | ||
Narmada Canal - Chandrasan | Mehsana | 1 | GSEC-Canal | |||
Charanka | Patan | 213.9 | Consists of 17 projects | Commissioned 19 April 2012 | ||
Patan | 5 | Jaihind Projects | ||||
Bhadrada | Patan | 23°40′57″N 71°46′30″E / 23.68250°N 71.77500°E | 5.001 | 7.963 | Lanco Solar | 21,740 230 Wp Poly Si panels |
Chadiyana | Patan | 23°41′32″N 71°34′01″E / 23.69222°N 71.56694°E | 15 | 23.955 | Lanco Solar | 5 MW from 20,647 230W Poly Silicon and 2,464 102W thin film; 10 MW from multi crystalline Si 230W and 235W panels[30] |
Dahisar | Patan | 20 | PLG Photovoltaic | |||
Hilabeli | Porbandar | 21°57′24″N 71°19′44″E / 21.95667°N 71.32889°E | 10 | 17 | GHI Energy | fixed tilt mounted at 20° angle[31] |
Kerala & Bapodar | Porbandar | 21°37′39″N 69°49′57″E / 21.62750°N 69.83250°E[32] | 20 | 35.425 | Hiraco Renewable Energy | |
Bapodar | Porbandar | 21°37′39″N 69°49′57″E / 21.62750°N 69.83250°E | 15 | 27.265 | Moser Baer | 125,100 80W First Solar and 13,490 370W MBSL panels, 18 880 kW Sunny Central SMA-800 inverters |
Dhank | Rajkot | 21°46′17″N 70°05′04″E / 21.77139°N 70.08444°E | 5 | 8.699 | APCA Power | |
Dhank | Rajkot | 21°46′35″N 70°04′47″E / 21.77639°N 70.07972°E[33] | 5 | 8.02 | Aravali Infrapower | |
Dhank | Rajkot | 21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E[34] | 10 | 17.678 | CBC Solar | |
Dhank | Rajkot | 21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E[35] | 5 | 8.839 | Ganeshvani Merchandise | |
Mervadar and Dhank | Rajkot | 21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E | 15 | Ganges Entertainment | ||
Mervadar | Rajkot | 21°44′11″N 70°07′12″E / 21.73639°N 70.12000°E[36] | 10 | 17.835 | GreenInfra[37] | Cost Rs 130 crore, First Solar thin film |
Bhatkota | Sabarkantha | 23°33′35″N 73°17′08″E / 23.55972°N 73.28556°E | 3 | Abellon Cleanenergy | Constructed by Waaree Energies | |
Khadoda | Sabarkantha | 22°52′39″N 72°04′13″E / 22.87750°N 72.07028°E | 10.2 | Azure Power (Haryana) | ||
Nani Naroli | Surat | 21°25′20″N 73°07′30″E / 21.42222°N 73.12500°E | 5 | 7.53 | GIPCL | |
Dhama | Surendranagar | 23°12′N 71°24′E / 23.200°N 71.400°E | 5 | 8.537 | Azure Power | |
Fatepur | Surendranagar | 23°23′57″N 71°38′20″E / 23.39917°N 71.63889°E | 5 | 8 | EMCO | output declines 0.7%/year |
Fatepur | Surendranagar | 23°25′05″N 71°37′20″E / 23.41806°N 71.62222°E | 15 | 24.873 | Mi My | [38] |
Dhama | Surendranagar | 23°24′N 71°42′E / 23.400°N 71.700°E | 5 | Environmental System | ||
Sujangadh | Surendranagar | 22°43′35.77″N 71°25′58.16″E / 22.7266028°N 71.4328222°E | 25 | Louroux Bio Energies | ||
Dhama | Surendranagar | 23°30′N 71°42′E / 23.500°N 71.700°E | 9.27 | 20.498 | Millennium Synergy | output declines 0.5%/year |
Patdi | Surendranagar | 23°09′N 71°45′E / 23.150°N 71.750°E | 1 | 1.815 | Rajesh Power Services | |
Patdi | Surendranagar | 1 | Rasna Marketing Services | |||
Surendranagar | 1 | Som Shiva | ||||
Surel | Surendranagar | 23°28′12″N 71°35′06″E / 23.47000°N 71.58500°E | 25 | 35.41 | Visual Percept Solar Projects | Commissioned 31 December 2011, cost 138 million INR/MW |
Tikar[39] | Surendranagar | 23°09′N 71°06′E / 23.150°N 71.100°E | 10.22 | 16.82 | Waa Solar (Madhav Power) | First Solar Thin Film CdTe Solar Modules, Commissioned December 2011 |
Total | 702.30[40][41][42] | 1095 (est) |
Charanka Solar Park
Charanka Solar Park | |
---|---|
Location of Charanka Solar Park in Gujarat | |
Country | India |
Location | Patan district |
Coordinates | 23°54′N 71°12′E / 23.900°N 71.200°E[43] |
Status | Operational |
Construction began | 2010 |
Commission date | 2012 |
Solar farm | |
Type | Flat-panel PV |
Site area | 2,000 ha (4,900 acres) Site plan |
Power generation | |
Nameplate capacity |
221 Planned: 500 |
The largest site within the Gujarat Solar Park is being built on a 2,000-hectare (4,900-acre) plot of land near Charanka village in Patan district, northern Gujarat. This hosts about 19 different projects by different developers. On 19 April 2012, a total of 214 megawatts (287,000 hp) had been commissioned.[44] It also became the world's second largest photovoltaic power station. When fully built out, the Charanka Solar Park will host 500 MW of solar power systems using state-of-the-art thin film technology, and should be finished by the end of 2014.[4] The investment cost for the Charanka solar park amounts to some US$280 million.[4] Construction began on 3 December 2010.
Developer | MWp |
---|---|
AES Solar Energy Gujarat Pvt. Ltd. | 15 |
Alex Asatral Power Pvt. Ltd. | 25 |
Avatar | 5 |
Emami Cement Ltd. | 10 |
GMR Gujarat Solar Power Pvt. Ltd. | 25 |
GPCL | 5 |
GPPC Pipavav Power Company Ltd. | 5 |
Kiran Energy Solar Power Pvt. Ltd.(Solar Field) | 20 |
Lanco Solar Pvt. Ltd., | 15 |
NKG Infrastructure Ltd. | 10 |
Palace Solar Energy Pvt. Ltd. | 15 |
Roha Dyechem Pvt. Ltd. | 25 |
Sun Clean Renewable Power Pvt. Ltd. | 6 |
Sun Edison Energy India Pvt. Ltd. | 25 |
Surana Telecom & Power Ltd. | 5 |
Yantra | 5 |
ZF Steering Gear (India) Ltd. | 5 |
EIT | 1 |
Universal Solar | 2 |
GSECL | 10 |
GPCL NEW | 10 |
Kindle Eng and Construction | 50 |
Torrent Solargen | 51 |
Total | 345 |
Gujarat Solar Park generation report
Month | Power (MWp) |
Production (MW·h) |
kWh/kWp/day (hrs/day) |
Notes |
---|---|---|---|---|
2010-12 | 5 | 363.746 | Lanco | |
2010 | 5 | 363.746 | ||
2011-01 | 5 | 657.910 | ||
2011-02 | 5 | 689.590 | ||
2011-03 | 5 | 847.320 | ||
2011-04 | 5 | 776.140 | ||
2011-05 | 5 | 639.800 | ||
2011-06 | 10 | 844.350 | Azure added | |
2011-07 | 10 | 1,053.002 | ||
2011-08 | 10 | 848.378 | ||
2011-09 | 10 | 1,078.100 | ||
2011-10 | 40 | 4,144.470 | Solitaire and Precious added (Moser Baer) | |
2011-11 | 120 | 8,774.701 | Welspun Urja, Green Infra, Azure, ESP, Visual, Millenium, and Emco added | |
2011-12 | 160 | 16,687.297 | Adani Power added | |
2011 | 160 | 37,041.058 | ||
2012-01 | 234 | 23,392.344 | Sun Edison, Konark, Backbone, Mithapur, GHI, Patdi, and MBH solar added | |
2012-02 | 280 | 35,606.103 | 4.31 | GIPCL, Kanyabe, Louroux, and Charanka added hrs/day=4.80 if the 40 MW not operating the full month is excluded |
2012-03 | 521 | 71,181.352 | 4.95 | Aravali infra, ICML, Waa Solar, PLG, Charanka expanded, Jaihind, ACME Solar, Harsha, PDPU, Abellon Cleanenergy, and Universal Solar added |
2012-04 | 604.89 | 86,191.200 | 4.75 | Mono Steel and Solar Semi added |
2012-05 | 669.4 | 93,300.790 | 4.50 | Moser Baer, Sunkon, and Hiraco added; Rasana, Rajesh, MBH solar, Essar, Sun Edison, Harsha, PDPU, Abellon, and Universal Solar consolidated into others or not reported |
2012-06 | 689.81 | 85,207.413 | 4.14 | SunBorne added |
2012-07 | 690.4 | 63,348.654 | 2.96 | |
2012-08 | 690.4 | 58,642.394 | 2.74 | |
2012-09 | 690.4 | 71,719.094 | 3.46 | |
2012-10 | 690.4 | 97,507.692 | 4.56 | |
2012-11 | 695.4 | 89,028.179 | 4.27 | APCA added |
2012-12 | 702.3 | 91,649.723 | 4.21 | Astonfield, Euro, S J Green Park, Chattel Construction, and Aatash Power added |
2012 | 702.3 | 867,715.627 | ||
2013-01 | 823.9 | 108,706.728 | 4.26 | Mi My, Responsive added |
2013-02 | 823.9 | 108,077.418 | 4.68 | |
2013-03 | 856.81 | 127,788.259 | 4.81 | |
2013-04 | 856.81 | 123,634.094 | 4.81 | Taxus, Ujjwala added |
2013-05 | 856.81 | 128,752.498 | 4.85 | |
2013-06 | 856.81 | 97,134.946 | 3.78 | |
Total | 1,599,214.374 |
Source: SLDC Gujarat[45]
2011 Generation detail
January | February | March | April | May | June | July | August | September | October | November | December | Total | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Lanco | 657.910 | 689.590 | 847.320 | 776.140 | 639.800 | 514.800 | 551.900 | 471.200 | 568.100 | 929.090 | 1,773.710 | 2,135.960 | 10,555.520 |
Azure Power | 329.550 | 501.102 | 377.178 | 510.000 | 1,060.180 | 1,550.400 | 1,664.400 | 5,992.810 | |||||
Solitaire | 1,018.600 | 1,879.000 | 2,059.200 | 4,956.800 | |||||||||
Precious | 1,136.600 | 1,644.800 | 1,921.200 | 4,702.600 | |||||||||
Welspun Urja | 1,054.600 | 2,013.300 | 3,067.900 | ||||||||||
Green infra | 819.500 | 1,313.400 | 2,132.900 | ||||||||||
Azure, ESP, Visual, Millenium, Emco | 52.691 | 4,284.809 | 4,337.500 | ||||||||||
Adani Power | 1,295.028 | 1,295.028 | |||||||||||
Total | 657.910 | 689.590 | 847.320 | 776.140 | 639.800 | 844.350 | 1,053.002 | 848.378 | 1,078.100 | 4,144.470 | 8,774.701 | 16,687.297 | 37,041.058 |
2012 Generation detail
January | February | March | April | May | June | July | August | September | October | November | December | Total | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Lanco | 2,596.660 | 2,596.340 | 2,516.950 | 2,281.050 | 2,176.470 | 1,962.510 | 1,471.960 | 1,268.850 | 1,846.360 | 2,619.510 | 2,379.280 | 2,563.480 | 26,279.420 |
Solitaire | 1,983.200 | 2,189.200 | 2,365.000 | 2,385.400 | 2,373.000 | 1,860.200 | 1,428.800 | 1,252.000 | 1,637.600 | 2,238.600 | 2,059.200 | 2,068.000 | 23,840.200 |
Precious | 1,888.200 | 2,006.200 | 2,349.200 | 2,397.400 | 2,398.600 | 1,983.400 | 1,490.800 | 1,326.400 | 1,708.800 | 2,340.800 | 2,080.400 | 2,113.400 | 24,083.600 |
Azure Power | 1,722.000 | 1,742.000 | 1,848.000 | 1,601.800 | 1,622.000 | 1,317.000 | 944.400 | 829.400 | 1,040.800 | 1,670.000 | 1,599.800 | 1,697.800 | 17,635.000 |
Sun Edison | 1.320 | 10.600 | 102.980 | 149.420 | 264.320 | ||||||||
Welspun Urja | 2,096.300 | 2,489.900 | 3,034.500 | 3,050.900 | 3,188.972 | 2,911.465 | 2,255.990 | 2,171.306 | 2,436.420 | 3,320.359 | 2,917.886 | 2,956.633 | 32,830.631 |
Green infra | 1,405.400 | 1,481.800 | 1,704.700 | 1,701.900 | 1,682.100 | 1,441.600 | 1,110.100 | 971.300 | 1,180.200 | 1,592.900 | 1,355.100 | 1,326.200 | 16,953.300 |
Aravali infra | 427.800 | 573.100 | 69.900 | 0.000 | 297.000 | 322.600 | 341.000 | 431.400 | 630.600 | 623.900 | 649.900 | 4,367.200 | |
Mono Steel | 1,557.183 | 1,885.503 | 1,500.318 | 1,338.950 | 1,056.212 | 1,259.749 | 1,633.977 | 1,670.961 | 1,660.436 | 13,563.289 | |||
Azure, ESP, Visual, Millenium, Emco | 4,126.000 | 6,302.000 | 7,232.000 | 7,214.000 | 7,594.000 | 6,414.000 | 4,398.000 | 4,082.000 | 5,267.736 | 7,008.000 | 6,528.000 | 7,866.000 | 74,031.736 |
Adani Power | 4,607.640 | 5,687.388 | 6,657.102 | 6,605.460 | 6,683.436 | 4,890.078 | 3,856.392 | 3,756.816 | 4,211.694 | 6,287.148 | 5,343.984 | 5,291.172 | 63,878.310 |
Konark | 453.460 | 902.680 | 926.800 | 915.060 | 941.920 | 781.940 | 563.760 | 500.750 | 628.360 | 825.570 | 766.499 | 780.832 | 8,987.631 |
Backbone | 504.225 | 580.050 | 829.050 | 879.300 | 1,085.400 | 659.700 | 561.600 | 451.650 | 599.115 | 776.850 | 635.400 | 602.790 | 8,165.130 |
ICML | 1,228.095 | 1,352.313 | 1,340.190 | 1,205.289 | 896.436 | 848.817 | 1,022.130 | 1,116.200 | 1,227.105 | 1,265.706 | 11,502.281 | ||
Solar Semi | 1.003 | 1,124.337 | 1,450.400 | 2,094.500 | 2,215.000 | 2,521.250 | 3,267.000 | 2,795.000 | 2,761.000 | 18,229.490 | |||
SunBorne | 2,233.700 | 3,248.100 | 1,432.200 | 1,531.900 | 2,258.700 | 2,255.000 | 2,237.700 | 15,197.300 | |||||
TATA (Mithapur) | 845.973 | 3,937.725 | 4,259.303 | 3,693.544 | 4,137.313 | 3,488.215 | 2,766.184 | 2,611.696 | 3,087.262 | 4,023.187 | 3,662.223 | 3,651.992 | 40,164.615 |
GHI | 1,150.860 | 1,603.300 | 1,735.700 | 1,648.400 | 1,572.200 | 1,305.400 | 988.600 | 907.100 | 788.300 | 1,355.700 | 1,410.300 | 1,478.200 | 15,944.060 |
Moser Baer | 2,476.327 | 1,964.846 | 1,613.092 | 1,578.320 | 1,185.669 | 2,327.351 | 2,170.408 | 2,211.727 | 15,527.739 | ||||
Hiraco | 3,013.224 | 2,094.320 | 1,524.580 | 1,377.873 | 2,024.915 | 3,011.783 | 2,822.013 | 2,944.690 | 18,813.399 | ||||
Rasana | 0.202 | 287.300 | 296.480 | 260.990 | 844.972 | ||||||||
Rajesh | 135.550 | 155.470 | 128.540 | 419.560 | |||||||||
MBH | 10.904 | 95.644 | 87.709 | 67.065 | 261.322 | ||||||||
GIPCL | 794.808 | 731.484 | 677.628 | 630.990 | 596.592 | 418.536 | 409.626 | 421.182 | 427.950 | 730.944 | 702.432 | 6,542.172 | |
Essar | 90.703 | 152.447 | 150.693 | 393.843 | |||||||||
Louroux | 1,322.750 | 2,125.200 | 3,870.000 | 4,115.400 | 3,580.660 | 2,608.940 | 2,499.260 | 2,985.780 | 3,204.400 | 2,717.280 | 2,640.280 | 31,669.950 | |
Waa Solar | 1,880.000 | 1816.000 | 1,829.000 | 1,505.000 | 1,132.000 | 1,085.000 | 1,335.000 | 1,661.000 | 1,510.000 | 1,497.000 | 15,250.000 | ||
PLG | 2,836.000 | 2,926.800 | 3,191.300 | 2,684.900 | 2,006.100 | 1,818.600 | 2,135.300 | 3,019.400 | 2,788.300 | 2,875.100 | 26,281.800 | ||
Thavar | 560.496 | 3,035.170 | 3,597.010 | 3,507.550 | 2,665.090 | 2,441.580 | 2,804.940 | 3,813.250 | 3,314.760 | 3,451.260 | 29,191.106 | ||
Charanka Solar Park | 922.366 | 21,866.910 | 31,621.590 | 31,497.000 | 30,249.000 | 19,250.000 | 19,125.000 | 24,758.000 | 33,242.000 | 30,150.000 | 30,565.000 | 273,246.866 | |
Jai Hind | 401.790 | 693.910 | 562.640 | 491.090 | 411.880 | 354.840 | 564.270 | 804.050 | 615.090 | 608.990 | 5,508.550 | ||
ACME | 1346.800 | 2,385.000 | 2,432.800 | 2,157.800 | 1,487.200 | 1,425.600 | 1,675.400 | 2,227.400 | 2,119.200 | 2,085.400 | 19,342.600 | ||
Sunkon | 149.658 | 673.440 | 494.064 | 504.198 | 629.562 | 804.006 | 764.250 | 893.436 | 4,912.614 | ||||
Harsha | 440.460 | 156.040 | 596.500 | ||||||||||
PDPU | 161.850 | 150.465 | 312.315 | ||||||||||
Abellon Cleanenergy | 440.540 | 449.110 | 889.650 | ||||||||||
Universal Solar | 335.237 | 298.173 | 633.410 | ||||||||||
APCA | 15.896 | 203.167 | 219.063 | ||||||||||
Astonfield | 264.190 | 264.190 | |||||||||||
Euro | 221.547 | 221.547 | |||||||||||
S J Green | 358.800 | 358.800 | |||||||||||
Chattel | 27.264 | 27.264 | |||||||||||
Aatash | 68.892 | 68.892 | |||||||||||
Total | 23,392.344 | 35,606.103 | 71,181.352 | 86,191.200 | 93,300.790 | 85,207.413 | 63,348.654 | 58,642.394 | 71,719.094 | 97,507.692 | 89,028.179 | 91,649.723 | 867,715.627 |
2013 Generation detail
January | February | March | April | May | June | July | August | September | October | November | December | Total | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Lanco | 2,853 | 2,672 | 3,039 | 1,890 | 2,251 | 2,135 | 14,839 | ||||||
Jai Hind | 693 | 678 | 820 | 762 | 741 | 573 | 4,266 | ||||||
Astonfield | 1,086 | 1,486 | 1,869 | 1,650 | 1,920 | 1,039 | 9,051 | ||||||
Precious | 2,257 | 2,075 | 2,597 | 2,454 | 2,513 | 1,935 | 13,830 | ||||||
Solitaire | 2,210 | 2,053 | 2,534 | 2,392 | 2,379 | 1,865 | 13,434 | ||||||
Azure Power Khadoda | 1,743 | 1,604 | 1,843 | 1,739 | 1,862 | 1,198 | 9,989 | ||||||
Aatash | 691 | 680 | 801 | 770 | 657 | 615 | 4,214 | ||||||
Green Infra | 1,469 | 1,461 | 1,737 | 1,647 | 1,644 | 1,202 | 9,160 | ||||||
Aravali Infra | 653 | 707 | 801 | 764 | 701 | 506 | 4,131 | ||||||
Mono Steel | 1,798 | 1,691 | 1,880 | 1,833 | 1,921 | 1,281 | 10,404 | ||||||
Mamu | 2,981 | 2,984 | 3,566 | 3,384 | 3,518 | 2,764 | 19,197 | ||||||
Taxus | 638 | 774 | 550 | 1,963 | |||||||||
Adani Power | 5,370 | 5,511 | 6,619 | 6,324 | 6,520 | 5,126 | 35,470 | ||||||
Konark | 844 | 800 | 945 | 895 | 936 | 761 | 5,181 | ||||||
Backbone | 660 | 664 | 906 | 966 | 1,077 | 842 | 5,113 | ||||||
ICML | 1,355 | 1,278 | 1,461 | 1,392 | 1,413 | 1,148 | 8,047 | ||||||
Solar Semi | 2,843 | 2,798 | 3,328 | 3,166 | 3,318 | 2,716 | 18,169 | ||||||
SunBorne | 2,431 | 2,256 | 2,373 | 1,624 | 2,064 | 1,968 | 12,716 | ||||||
Euro | 796 | 714 | 843 | 779 | 827 | 671 | 4,629 | ||||||
TATA (Mithapur) | 3,940 | 3,739 | 4,328 | 4,110 | 4,239 | 3,283 | 23,639 | ||||||
GHI | 1,592 | 1,522 | 1,766 | 1,596 | 1,636 | 969 | 9,081 | ||||||
Moser Baer | 2,330 | 2,249 | 2,625 | 2,453 | 2,438 | 1,613 | 13,708 | ||||||
Hiraco | 3,127 | 2,880 | 3,426 | 3,155 | 3,162 | 2,216 | 17,966 | ||||||
APCA | 384 | 550 | 689 | 658 | 771 | 554 | 3,605 | ||||||
GIPCL | 790 | 696 | 618 | 793 | 800 | 474 | 4,171 | ||||||
Mi My Solar | 4,025 | 4,495 | 5,334 | 4,976 | 4,625 | 3,854 | 27,310 | ||||||
EMCO | 759 | 721 | 845 | 784 | 768 | 590 | 4,466 | ||||||
Azure Power Dhama | 731 | 704 | 843 | 805 | 787 | 624 | 4,495 | ||||||
ESP | 759 | 747 | 913 | 894 | 870 | 702 | 4,886 | ||||||
Millenium | 1,700 | 1,609 | 1,922 | 1,842 | 1,936 | 1,476 | 10,484 | ||||||
Visual | 3,687 | 3,403 | 3,951 | 3,650 | 3,630 | 2,887 | 21,208 | ||||||
Chattel | 1,824 | 3,274 | 4,003 | 3,663 | 3,929 | 3,022 | 19,714 | ||||||
Responsive | 2,246 | 3,304 | 4,004 | 3,800 | 3,858 | 2,470 | 19,682 | ||||||
Ujjwala | 1,684 | 2,780 | 2,090 | 6,554 | |||||||||
Louroux | 3,044 | 3,077 | 3,699 | 3,526 | 3,495 | 2,534 | 19,374 | ||||||
Waa Solar | 1,620 | 1,564 | 1,869 | 1,777 | 1,818 | 1,376 | 10,024 | ||||||
S J Green | 543 | 731 | 903 | 698 | 780 | 623 | 4,278 | ||||||
PLG | 3,062 | 2,899 | 3,408 | 3,181 | 3,204 | 2,462 | 18,216 | ||||||
Thavar | 3,611 | 3,681 | 4,337 | 4,212 | 4,250 | 3,262 | 23,353 | ||||||
Charanka Solar Park | 32,397 | 30,486 | 36,087 | 36,236 | 37,977 | 28,328 | 201,511 | ||||||
ACME | 2,167 | 2,088 | 2,436 | 2,324 | 2,288 | 1,706 | 13,010 | ||||||
Sunkon | 1,637 | 1,548 | 1,825 | 1,748 | 1,674 | 1,127 | 9,558 | ||||||
Total | 108,707 | 108,077 | 127,788 | 123,634 | 128,752 | 97,135 | 694,094 |
Project list
Developer | Location | Size (MWp) |
Commissioned | Notes |
---|---|---|---|---|
Aatash Power Pvt Ltd | 5 | |||
Abellon Cleanenergy Limited | Sabarkantha[46] | 3 | 2012-03 | EPCM by Waaree Energies Private Limited |
ACME Tele power Ltd | Anand[47] | 15 | 2012-03 | |
Adani Power Ltd | Kutch[48] | 40 | 2012-01-05 | Netra substation |
AES Solar Energy Gujarat Pvt Ltd | Charanka (Patan) | 15 | ||
Alex Astral Power Pvt Ltd | Charanka (Patan)[49] | 25 | ||
Ambit Advisory Services Pvt Ltd | 5 | |||
APCA Power Private Limited | Dhank (Rajkot)[50] | 5 | ||
Aravali Infrapower Limited | Dhank (Rajkot)[33] | 5 | 2012-02 | |
Astonfield Renewable Resources | (Patan)[51] | 12.3 | ||
Avatar Solar | 5 | thin film[52] | ||
Azure Power (Gujarat) Pvt Ltd | Dhama (Surendranagar)[49] | 5 | 2011 | |
Azure Power (Haryana) Pvt Ltd | Khadoda (Sabarkantha)[49] | 10 | 2011-10 | 5 MW June 2011 |
Backbone Enterprises Limited | Shiv Lakhashin Kachchh[53] | 5 | 2012-01 | |
Cargo Motors (Tata)[54] | Mithapur (Jamnagar) | 25 | 2012-01-25 | |
Claris LifeScience Ltd | Ahmedabad[55] | 2 | ||
Common Wealth Business Technologies | 10 | |||
Corner Stone Energy Pvt Ltd | Charanka (Patan)[56] | 5 | ||
Driesatz My Solar | 15 | |||
EI Technologies Pvt. Ltd | Charanka (Patan)[49] | 1 | ||
Emami Cement Limited | Charanka (Patan)[49] | 10 | ||
EMCO Limited | Surendranagar[57] | 5 | ||
ESP Urja | Surendranagar[58] | 5 | ||
Essar Power Limited | Bhuj (Kutch)[59] | 1 | 2012-02 | |
Euro Solar Private Ltd | 5 | (CPEC Ltd.) | ||
Ganeshvani Merchandise Private Limited | (Rajkot) | 5 | ||
Ganges Green Energy Private Limited | Rajkot[60] | 25 | ||
GHI Energy Private Limited | Porbandar[61] | 10 | 2012-01 | constructed by Lanco[62] |
GMR Gujarat Solar Power Pvt. Ltd | Charanka (Patan)[49] | 25 | ||
Green Infra Solar Energy Limited | Mervadar (Rajkot)[49] | 10 | 2011-11 | |
GSPC Pipavav Power Company Limited | Charanka (Patan)[49] | 5 | constructed by Lanco[62] | |
Gujarat Industries Power Company Limited | Vastan (Surat)[63] | 5 | 2012-02 | |
Gujarat Mineral Development Corporation Limited | Panandhro (Kutch)[64] | 5 | ||
Gujarat Power Corporation Limited | Charanka (Patan)[49] | 5 | constructed by Lanco[62] | |
Harsha Engineers Limited | Khanpur (Ahmedabad) | 1 | 2012-03 | |
Hiraco Renewable Energy Pvt Ltd | (Porbandar)[65] | 20 | ||
India Solar Ray Power Private Limited | (Kutch)[66] | 10 | ||
Industrial Power Infrastructure Limited | (Jamnagar)[67] | 25 | ||
Inspira Solar (Palace) | Ambaliyara [49] | 15 | ||
Integrated Coal Mining Limited | (Kutch)[68] | 9 | 2012-03 | |
Jaihind Projects Limited | Radhanpur (Patan)[69] | 5 | 2012-03-03 | |
Kemrock Industries and Exports Limited | (Vadodara)[70] | 10 | ||
Kiran Energy Solar Power Private Limited | Charanka (Patan)[49] | 20 | ||
Konark Gujarat PV Pvt. Limited | (Kutch)[71] | 5 | 2012-01 | |
Lanco Infratech Ltd | Bhadrada (Patan)[49] | 5 | 2010-12 | area - 27 acres[72] |
Lanco Infratech Ltd | Chadiyana (Patan)[49] | 15 | 2011 | |
Lanco Infratech Ltd | Charanka (Patan)[49] | 15 | 5 MW January 2011 | |
Louroux Bio Energies Limited[73] | Dheduki (Surendranagar)[74][75] | 25 | 2012-02 | |
MBH Power Private Limited | Chitra (Bharuch)[76] | 1 | 2012-01 | |
Mi My Solar | Surendranagar | 15 | ||
Millenium Synergy (Gujarat) Private Limited | (Surendranagar)[77] | 10 | ||
Monnet Ispat & Energy Limited | 25 | |||
Mono Steel (India) Ltd. | Una (Junagadh)[78] | 10 | 2012-04-12 | EPCM by Waaree Energies Private Limited |
Moser Baer Energy & Development Ltd | (Porbandar)[79] | 15 | ||
NKG Infrastructure Limited | Charanka (Patan)[49] | 10 | ||
PLG Power Ltd | (Patan)[80] | 40 | 2012-01 | 20 MW completed |
Precious Energy Services Pvt Ltd | Dalpatpura (Banaskantha)[49] | 15 | 2011-10 | Moser Baer |
Rajesh Power Services Private Limited | Patdi (Surendranagar) | 1 | 2012-02 | |
Rasna Marketing Services LLP | Patdi {Surendranagar}[81] | 1 | 2012-01 | |
Responsive Sutip Limited | (Surendranagar)[82] | 25 | ||
Roha Energy Private Limited | Charanka (Patan)[49] | 25 | ||
S J Green Park Energy Private Limited | Shivlakha (Kutch)[83] | 5 | 23°23′05″N 70°36′01″E / 23.38472°N 70.60028°E (CPEC Ltd.) | |
Sand Land Real Estates Pvt Ltd | (Banaskantha)[84] | 25 | ||
Saumya Construction Pvt Ltd | 2 | |||
Solar Semiconductor Pvt Ltd | (Kutch) | 20 | ||
Solitaire Energies Pvt Ltd | Dalpatpura (Banaskantha)[49] | 15 | 2011-10 | Moser Baer |
Som Shiva Impex Limited | (Surendranagar)[85] | 1 | ||
Sun Edison Energy India Private Limited | Charanka (Patan)[86] | 25 | 2012-04-19[87] | 89,000 modules |
SunBorne Energy[88] | Karmaria (Rajkot)[89] | 15 | 2011-12-31 | Suntech panels |
SunClean Renewable Power Pvt. Ltd. | Charanka (Patan)[49] | 25 | ||
Sunkon Energy Pvt Ltd | (Surendranagar) | 10 | ||
Surana Telecom & Power Limited | Charanka (Patan)[49] | 5 | ||
Tatith Energy | 5 | SolarWorld panels | ||
Taxus infrastructure & Power Project Pvt Ltd | Raparkhokhara (Kutch) | 5 | ||
Toss Financial Services Pvt Ltd | 2 | |||
Ujjawala Power Pvt Ltd | (Surendranagar)[90] | 25 | ||
Unity Power Pvt Ltd | 5 | |||
Universal Solar System | Charanka (Patan)[49] | 2 | 2012-01 | |
Visual Percept Solar Projects Private Limited | (Surendranagar)[91] | 25 | ||
WAA Solar Pvt Ltd | (Surendranagar)[49] | 10 | 2012-03 | |
Welspun Urja India Limited | Khirsara (Kutch)[49] | 15 | 2011-11 | |
Yantra eSolarIndia Private Limited | (Patan)[92] | 5 | ||
Zeba Solar Gujarat Pvt Ltd | (Vadodara)[93] | 10 | ||
ZF Steering Gear (India) Limited | Charanka (Patan)[49] | 5 | ||
Total | 968.5 |
Source: GEDA[94]
See also
- Concentrated solar power
- List of photovoltaic power stations
- Photovoltaic power station
- Solar power in India
- Eurosolar
References
- ↑ http://www.theguardian.com/environment/picture/2012/may/02/gujarat-solar-power-park-india
- ↑ Solar boom faces challenges
- ↑ Gujarat Solar Park: Asia's largest solar power park opens
- 1 2 3 "India’s Gujarat bares 500-MW solar park to businessmen". ecoseed.org. 2011-01-03. Retrieved 2011-01-14.
- ↑ Preparations in full swing for opening of ‘Gujarat Solar Park’
- ↑ Gujarat Solar Park to be developed
- ↑ Asia's largest solar park functional in Gujarat state
- 1 2 Gujarat solar park likely to produce 300MW by the end of December
- ↑ Gujarat setting up 8,000-crore solar power park
- 1 2 3 Solar power plant in Ahmedabad Asia's biggest
- ↑ Proposed Gujarat Solar Policy Tariffs for period 29 Jan 2012 to 31 March 2015
- ↑ Gujarat Solar Power Plants
- ↑ Solar PV Plants Commissioned in Gujarat
- ↑ Solar power project in Gujarat, India
- 1 2 Moser Baer Clean Energy Limited commissions largest solar power capacity
- 1 2 Gunthawada, India
- 1 2 15MWp Solar PV Power Project in Village Gunthavada (Dalpatpura), Taluk Kankarej, District-Banaskantha, Gujarat State, India
- 1 2 PDD
- ↑ Moser Baer commissions 30-MW solar farm in Gujarat
- ↑ PDD
- ↑ Adani Power to invest Rs 3,000 cr in solar power
- ↑ PDD
- ↑ Adani Group commissions largest solar power project
- ↑ Adani commissions Rs 400 cr 40 mw solar unit in Gujarat
- ↑ PDD
- ↑ PDD
- ↑ PDD
- ↑ PDD
- ↑ PDD
- ↑ PDD Chadiyana
- ↑ GHI PDD
- ↑ Hiraco PDD
- 1 2 PDD
- ↑ PDD
- ↑ PDD
- ↑ PDD
- ↑ Operational Projects
- ↑ Solar PV Power Project by MMPL in Fatepur, Gujarat
- ↑ Surendranagar Solar Farm
- ↑ Installed Capacity
- ↑ Solar Park Day 1 Highlights
- ↑ Installed Capacity
- ↑ "Site plan of Charanka Solar Park, Gujarat, India". Wiki-Solar. Retrieved 5 March 2015.
- ↑ "Gujarat’s 214MW solar park named as Asia’s largest single PV plant". PV Tech. 23 April 2012. Retrieved Apr 2012.
- ↑ Energy Account
- ↑ New Solar Project by Abellon Clean Energy Ltd
- ↑ New Solar Project by Acme Solar Technologies (Gujarat) Pvt. Ltd
- ↑ Adani Group commissions 40mw solar power plant in Gujarat
- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 PV India Map
- ↑ PDD
- ↑ Project Portfolio
- ↑ Avatar Solar Receives 5 MW Indian Project Contract
- ↑ Solar Power (shiv Lakhash) by Backbone Enterprises Ltd
- ↑ Tata Power commissions 25 MW solar project in Gujarat
- ↑ New Solar Project by Claris Lifesciences Ltd
- ↑ Proposal for construction
- ↑ New Solar Power Project by Emco Ltd
- ↑ New Solar Project by Esp Urja Pvt Ltd
- ↑ Essar Power commissions 1MW solar photovoltaic plant in Bhuj
- ↑ New Solar Power Project by Ganges Green Energy Pvt Ltd
- ↑ New Solar Project by Ghi Energy Pvt. Ltd
- 1 2 3 Lanco Infra completes 56 MW grid connected solar photovoltaic power plants in Gujarat
- ↑ Dedication of 5 MW Solar Power Plant to the Nation
- ↑ GMDC to set up 5MW solar plant
- ↑ New Solar Project by Hiraco Renewable Energy Pvt Ltd
- ↑ New Solar Project by India Solar Ray Power Pvt Ltd
- ↑ New Solar Power Project by Industrial Power Infrastructure Ltd
- ↑ New Solar Project by Integrated Coal Mining Ltd
- ↑ Project Overview
- ↑ New Solar Project by Kemrock Renewable Energy Ltd
- ↑ New Solar Project by Konark Gujarat Pv Pvt Ltd
- ↑ Towards 25 years of carbon-free power
- ↑ PDD
- ↑ Martifer Solar, Louroux Bio Energies to collaborate on 25MW of solar projects in Gujarat, India
- ↑ Solar Photovoltaic Power Project by Louroux Bio Energies Ltd
- ↑ Electricity Projects
- ↑ New Solar Project by Millenium Synergy Gujrat Pvt Ltd
- ↑ Solar Power (una) by Mono Steel India Ltd
- ↑ New Solar Project by Moser Baer Energy And Development Ltd
- ↑ New Solar Power Project by Plg Photovoltaic Ltd
- ↑ Solar Power (patdi) by Rasna Marketing Services LLP
- ↑ New Solar Power Project by Responsive Sutip Ltd
- ↑ Our Projects
- ↑ New Solar Project by Sandland Real Estates Pvt Ltd
- ↑ New Solar Project by Som Shiva (Impex) Ltd
- ↑ SunEdison Announces Activation of 25MW Solar Power Plant in Asia’s Largest Solar Park in Gujarat, India
- ↑ 25MW Solar Plant Opens in Asia's Largest Solar Park
- ↑ SunBorne Energy pools funds for Gujarat solar plant
- ↑ SunBorne Energy achieves financial closure for 15-MW solar plant
- ↑ New Solar Power Project by Ujjawala Power Pvt Ltd
- ↑ New Solar Project by Visual Percept Solar Projects Pvt Ltd
- ↑ New Solar Power Project by Yantra E Solar India Pvt Ltd
- ↑ New Solar Project by Zeba Solar North Pvt Ltd
- ↑ Details of Solar Power Project Project Developers