Duration (project management)

Duration of a project's terminal element is the number of calendar periods it takes from the time the execution of element starts to the moment it is completed.

Duration should not be confused with work. E.g. it takes three days for a snail-mail letter to arrive at point B from point A, whereas the work put into mailing it may be 0.5 hours.

Strictly speaking, the phrase Duration of terminal element X is 5 days is incomplete. It fails to specify the following:

So the improved statement could read:

I, Marek Kowalczyk, as of 27 March 2005 strongly believe that if I fully applied myself to competing terminal element X and worked 8 hours a day every day, including holidays, and had all the materials at hand, then I would have completed it in 5 calendar days.' See metamodeling.

It may seem unwieldy to use such complicated statements, but lack of detail often leads to misunderstanding.

See also

This article is issued from Wikipedia - version of the Tuesday, April 01, 2014. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.