Cincinnati Subway
Overview | |
---|---|
Owner | SORTA |
Locale | Cincinnati, Ohio |
Transit type | Rapid transit |
Number of lines | 1 |
Number of stations | 4 |
Operation | |
Began operation | Never used |
Technical | |
System length | 2.2 mi (3.5 km) |
The Cincinnati Subway is a set of incomplete, derelict tunnels and stations for a rapid transit system beneath the streets of Cincinnati, Ohio. It is recognized as the largest abandoned subway tunnel in the United States. It was built in the early twentieth century as an upgrade to the Cincinnati streetcar system, but was abandoned due to escalating costs and collapse of funding amidst political bickering during the 1920s.
History
Rapid transit was seen as the solution for downtown congestion during the first quarter of the 20th century. Six million dollars were allocated for the project, but construction was delayed due to World War I. Unexpected post-war inflation doubled the cost of construction, so the project could not be finished at the original estimated price. Various attempts to use the subway tunnels for mass transit have been unsuccessful. Political squabbling, the Great Depression, World War II, and the rise in popularity of the automobile have contributed to the failure of the proposals.[1] Today, many Cincinnatians are unaware of the tunnels underneath them.[2]
Context
From 1825 to 1920 the Miami and Erie Canal divided Cincinnati's residential neighborhood of Over-the-Rhine from the business district of downtown.[3]:17[4] The canal was used to transport goods and people from the Great Lakes to the Ohio River and subsequently the Mississippi River via Cincinnati, until the popularity of railroads caused it to become disused.[3]:17 The canal became unprofitable by 1856[3]:17 and was abandoned by the city in 1877.[1] On September 27, 1884 a weekly Cincinnati magazine called The Graphic proposed that the "dead old ditch" be used to provide an unobstructed route for a subway system, with a large boulevard above.[3]:18
In 1888, Cincinnati began adopting electric streetcars,[3]:18 which soon became the main form of public transportation.[3]:19 During this period Cincinnati was one of the seven most populous US cities[3]:17and had a rate of growth and economic importance that was similar to that of New York City and Chicago.[1] The slow streetcars shared the crowded streets with horse-drawn carriages, people, and collided with the first automobiles on an almost daily basis.[3]:19 It was not unusual for trips between downtown and the surrounding suburbs to take 45 minutes to an hour.[3]:46 Despite having 222 miles (357 km) of streetcar tracks, the city found itself in a growing traffic nightmare.[3]:19 In 1910, Henry Thomas Hunt spearheaded plans for a new rapid transit system.[3]:35
Planning
The next year City Council convinced the Ohio State Legislature to lease the city's portion of the canal for use as a boulevard and subway system.[3]:35 The city hired experts that worked on Boston's and Chicago's rapid transit systems to research the best possible implementation for Cincinnati's rapid transit system.[3]:36 The result were four "Schemes," or proposed routes. The chosen plan, Scheme IV, modification H, looped around the city hitting the central suburbs of St. Bernard and Norwood, the eastern suburbs of Oakley and Hyde Park, and then returned into downtown.[3]:36
In 1916 City Council authorized a bond issue of $6 million with an interest rate of 4.25 percent,[5] and then held a plebiscite on the rapid transit plan.[4] On April 17, 1917, Cincinnati citizens voted in favor of using the bond for a Rapid Transit system, 30,165-14,286.[4] However, just 11 days earlier, the United States entered World War I,[1] so construction was halted because no capital issues of bonds were permitted during the war.[4][3]:45
War conditions have prompted the opinion in certain official quarters that it would be unwise to proceed with the construction of the loop until after the war. High costs of materials and the difficulty in obtaining deliveries are cited as arguments in favor of the temporary abandonment of the project.— Cincinnati Enquirer, "Subway Again May Meet Delay: Postponement Of Plans Until After War Is Considered," April 5, 1918 (p. 9)
Construction and failure
When the war ended in 1918, costs had increased. By 1919 the cost of construction had doubled,[3]:71 increasing the original price to complete the loop from $12 million to $13 million.[4] Regardless, the city began work on January 28, 1920,[6] and planned to raise the money to complete the loop later. When bonds ran out in 1927, construction ended with seven miles (11 km) of subway dug or graded, but no track had been laid.
New estimates to complete the loop ranged from an additional $6 million to $12 million.[1] The boulevard that ran on top of the subway, called "Central Parkway," officially opened to traffic on October 1, 1928, and was followed by a week of public celebration.[3]:47
Once it became apparent that the original rapid transit plan had failed, political infighting in City Hall stalled any new progress,[1][3]:73 and any hope of raising the money to complete the subway was further delayed with the stock market crash of 1929.[3]:81 Though few citizens owned automobiles when Mayor Hunt first planned rapid transit in 1910, their increasing popularity and convenience helped fuel critics' arguments against a subway system. They began referring to the project as "Cincinnati's White Elephant."[3]:71, 81
Attempts at revival
In 1936 the city commissioned the Engineers' Club of Cincinnati to produce a report on how to use the unfinished rapid transit property.[3]:82 The report could not find any use for the tunnels other than what they had been designed for. Because the city's needs had changed from twenty years earlier, the report suggested that the subway "should be forgotten".[3]:82
In 1939 the tunnels were researched for possible automobile traffic, but were found to be unsuitable for that use.[3]:82 In 1940 the city sought the advice of several experts to settle once and for all the fate of the subway. The report recommended placing all streetcar and trolley transportation underground (i.e., a subway), but Cincinnati already had too many other expensive public projects underway.[3]:82, 92 The plan was put on hold yet again when the United States entered World War II in 1941.
During World War II, the city was focused on war-time rationing, so completing the subway was not a high priority.[3]:82 The tunnels were suggested as possible air raid shelters, but the idea was never implemented.[3]:92 Underground storage of commercial and military supplies was also proposed as a use for the tunnels, or as a pathway to bring freight into the heart of the city, but both ideas were rejected because they would delay bringing mass transit to Cincinnati.[3]:92 After the war ended the City Planning Commission decided to not include the subway in its plans. Instead, the commission would use the loop's right-of-way as pathways for Interstate 75 and the Norwood Lateral.[3]:98, 103
In the 1950s a massive 52-inch (1.3 m)[7] water main was laid in the north-bound tunnel to save $300,000[3]:102 in construction costs.[8]According to the engineering firm Parsons Brinckerhoff, a redundant water main was installed during the construction of Fort Washington Way so the water main in the subway could easily be removed.[9] There is also an escape clause in Ordinance No. 154-1956 that states, "in the event said section of the rapid transit subway is, at some future date, needed for rapid transit purposes, the Water Works shall remove said main at its sole cost."[3]:102
The subway bonds were paid off in 1966 at a total cost of $13,019,982.45.[1] Around that time Meier's Wine Cellars Inc. wanted to use the subway tunnels to store wine, as well as install a bottling operation to draw tourists, but it fell through due to a lack of proper building codes.[3]:110 In the 1970s Nick Clooney wanted to turn parts of the tunnel into an underground mall and a night club, but that fell through early on due to insurance issues.[10][3]:110 In the 1980s the city pitched the tunnels to Hollywood filmmakers as a location to shoot subway scenes.[3]:110 In particular, the location was presented to the makers of Batman Forever, but as of 2008 the tunnels had not been used in any feature films.[3]:110
In 2002 the subway tunnels were proposed as a route for a regional light rail system that would cost $2.6 billion and take thirty years to build.[9] The tunnels were favored because they were in an ideal location, they could easily be used to connect the east side and the west sides of Cincinnati, and they would have saved the city at least $100 million in construction costs at the time.[9] The light rail plan, called MetroMoves, proposed a tax levy that would have raised sales tax in Hamilton county by a half-cent.[11] The plan was voted down by more than a 2-to-1 ratio.[11]
The uncompleted subway tunnels and stations have been described as "strikingly well preserved"[8] and "in good shape."[9] This is partially credited to the original construction quality,[10] and partially because Cincinnati must use tax revenues to maintain the tunnel because Central Parkway is situated on top of it.[7][9]
In 2008 it was estimated that it would cost $2.6 million for current maintenance on the tunnels, $19 million to fill the tunnels with dirt, and $100.5 million to revive the tunnels for modern subway use. Relocating the 52-inch (1.3 m) water main would cost $14 million.[7]
Stations and route
Seven stations were completed along Central Parkway. Underground locations are at Race Street, Liberty Street, Linn Street, and Brighton Place. Above-ground locations were at Marshall Street, Ludlow Avenue, and Clifton Avenue. The underground stations remain intact, but the above-ground stations were demolished when I-75 was built in the 1960s.
The first station was the Race Street Station, which was to serve as the main hub. It was configured with the platform in the center, with the subway running along the north and south side. Next was Liberty Street, which was a through-station. It was a simple design with a platform on each side of the track. Third was Linn Street, also a through station. Laid out similarly to Liberty Street, this station has been sealed up, and can be easily missed when walking through. Fourth was Brighton Place, another through-station. Marshall Street was the most grand of the above-ground stations, located to the west near the Mill Creek Valley. Ludlow Avenue Station was constructed under the south side of the Ludlow Viaduct and was also a through-station. The last to be completed was Clifton Avenue, which was located where the street passes under present day I-75. There were additional stations in the plan; however, funding ran out as the project reached Norwood.[12]
Engineering
The subway tunnels run north and south. Each of the two halves of the tube has a minimum width of 13 feet (4.0 m) and a height of 15 feet 6 inches (4.72 m). Each tunnel has parallel wooden stringers which are bolted to the floor, and are intended to support steel rails that were never laid. They are 59 inches (1.5 m) from center to center, which is 6 inches (150 mm) wider than most railway lines. All curves in the tunnel are gradual, and on those curves the outside stringer was raised higher than the inner stringer to accommodate trains traveling at speeds of more than 40 miles per hour (64 km/h).[13]
There were many details of the unfinished subway system, such as a provision for a station at Mohawk Corner, where the wall has been set back. At Walnut Street the lines begin to curve south to go into downtown, but they are stopped short by a bricked up wall. The subway tunnel is double-tracked throughout its entire length, with a concrete wall separating the two tracks. Openings in the wall enable persons to step from one track to another. The tunnels are well ventilated and provide much light until Liberty Street is reached.[13]
Canal-based subways
A similar construction can also be found at the Newark City Subway, which actively uses the former bed of the Morris Canal, and the Rochester Industrial and Rapid Transit Railway, which once used the bed of the previously abandoned Erie Canal.
See also
Notes and references
Notes
- 1 2 3 4 5 6 7 Radel, Cliff (May 24, 2003). "Life under the city: Subway legend has never left the station". Cincinnati Enquirer. pp. 12–27. Retrieved 2008-06-08.
- ↑ "City of Cincinnati — The Cincinnati Subway". Retrieved 2008-12-07.
- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Singer, Allen J. (May 26, 2003). The Cincinnati subway: history of rapid transit. Images of America Series. Mount Pleasant, SC: Arcadia Publishing. ISBN 978-0-7385-2314-9. Retrieved July 23, 2011.
- 1 2 3 4 5 Body in Charge of Transit System (April 3, 1926). "Progress of Work Reviewed". Cincinnati Enquirer. pp. 14–15.
- ↑ "... Bonds To Pay 41⁄4% Interest". Cincinnati Post. June 17, 1916. p. 12.
- ↑ "The Cincinnati Subway System". Ohio Exploration. Retrieved January 28, 2010.
- 1 2 3 "Cincinnati Considers Options For Decades-Old Unfinished Subway". Retrieved 2008-05-12.
- 1 2 "Cincinnati's Subway" (video). YouTube. February 4, 2008. Retrieved 2008-05-12.
- 1 2 3 4 5 Pilcher, James (July 29, 2002). "Abandoned subway could save light rail plan". Cincinnati Enquirer. Retrieved 2008-07-03.
- 1 2 Krewedl, Derek. (October 22, 2002) "New life for old subway?", Downtowner. pp.1,14.
- 1 2 Pilcher, James (November 6, 2002). "Metro plan hits wall of resistance". Cincinnati Enquirer. Retrieved 2008-07-03.
- ↑ Cincinnati's Abandoned Subway, (2010). Pro. Paige E. Malott. Dir. Leland Schuler. DVD. Time Bonus Productions, LLC, Cincinnati, OH.
- 1 2 Stimson, George P. (April 24, 1936). "Unused Subway System is in Almost Perfect Condition". The Cincinnati Times-Star. p. 2.
References
- Cincinnati's Abandoned Subway, (2010). Pro. Paige E. Malott. Dir. Leland Schuler. DVD. Time Bonus Productions, LLC, Cincinnati, OH. A documentary film about the history, failure, and present condition of the subway. Features commentary from local historians and city engineers, as well as original construction photographs from the 1920s.
External links
Wikimedia Commons has media related to Cincinnati Subway. |
- Geographic data related to Cincinnati Subway at OpenStreetMap
- Queen City Discovery: Subway 2010 Current photographs of the stations.
- The Cincinnati Subway Additional current photographs of the stations.
- Images of Cincinnati Subway Construction
- Metro|Cincinnati A 2010 vision for rapid transit in the Greater Cincinnati and Northern Kentucky region.
- Cincinnati Subway Revival Study A 2008 study by URS Corporation shows that light rail could be implemented in the original tunnels.
- A detailed account of the Cincinnati Subway story.
- UrbanAdventure.org's tour of the subway in 2002.
- Forgotten Ohio - Cincinnati Subway
- City of Cincinnati - The Cincinnati Subway