Tunnelling shield

Diagram of the tunnelling shield used to construct the Thames Tunnel
The tunnelling shield used for the construction of the Xinyi Line on the Taipei Metro system in Taiwan.

A tunnelling shield is a protective structure used in the excavation of tunnels through soil that is too soft or fluid to remain stable during the time it takes to line the tunnel with a support structure of concrete, cast iron or steel. In effect, the shield serves as a temporary support structure for the tunnel while it is being excavated.

History

The first successful tunnelling shield was developed by Sir Marc Isambard Brunel, and patented by him and Lord Cochrane in January 1818.[1] Brunel and his son Isambard Kingdom Brunel used it to excavate the Thames Tunnel, beginning in 1825 (though the tunnel would not be opened until 1843).[2] Brunel is said to have been inspired in his design by the shell of the shipworm Teredo navalis, a mollusc whose efficiency at boring through submerged timber he observed while working in a shipyard.[2] The shield was built by Maudslay, Sons & Field, of Lambeth, London, who also built the steam pumps for de-watering the tunnel.

Brunel's original design was substantially improved by Peter W. Barlow in the course of the construction of the Tower Subway under the River Thames in central London in 1870. Probably the most crucial innovation of Barlow's design was that it had a circular cross-section (unlike Brunel's, which was of rectangular cross-section), which at once made it simpler in construction and better able to support the weight of the surrounding soil.

The Barlow design was enlarged and further improved by James Henry Greathead for the construction of the City & South London Railway (today part of London Underground's Northern line) in 1884.

His system was also used in the driving of the tunnels for the Waterloo & City Railway which opened in 1898; he was joint Engineer to the project until his death. The station tunnels at the City station (now known as Bank) were the largest diameter tunnelling shields in the world at the time.

To this day, most tunnelling shields are still loosely based on the Greathead shield.[3]

An original Greathead Shield, used in the excavation of the deep London Underground lines, remains in place in disused tunnels beneath Moorgate station.[4]

Manual shield tunnelling

The Greathead tunnelling shield in use on the Waterloo & City Railway

In early shield tunnelling, the shield functioned as a way to protect labourers who performed the digging, and moved the shield forward, progressively replacing it with pre-built sections of tunnel wall. The early deep tunnels for the London Underground were built in this way. The shield divided the workface into overlapping portions that each worker could excavate.

Modern tunnel boring machines

Main article: Tunnel boring machine

A tunnel boring machine (TBM), consists of a shield (a large metal cylinder) and trailing support mechanisms.

At the front end of the shield a rotating cutting wheel is located. Behind the cutting wheel there is a chamber where, depending on the type of the TBM, the excavated soil is either mixed with slurry (so-called slurry TBM) or left as-is (earth pressure balance or EPB shield). The choice for a certain type of TBM depends on the soil conditions. Systems for removal of the soil (or the soil mixed with slurry) are also present.

Behind the chamber there is a set of hydraulic jacks supported by the finished part of the tunnel which are used to push the TBM forward. Once a certain distance has been excavated (roughly 1.5-2 meters), a new tunnel ring is built using the erector. The erector is a rotating system which picks up precast concrete segments and places them in the desired position.

Behind the shield, inside the finished part of the tunnel, several support mechanisms which are part of the TBM can be found: dirt removal, slurry pipelines if applicable, control rooms, rails for transport of the precast segments, etc.

Lining

The tunnel lining is the wall of the tunnel. It usually consists of precast concrete segments which form rings. Cast iron linings were traditionally used in the London Underground tunnels, while steel liners were sometimes used elsewhere.

Shields in Japan

In Japan there are several innovative approaches to shield tunnelling, e.g. the Double-O-Tube or DOT-tunnel. This tunnel looks like two overlapping circles. There are also shields with computerized arms which can be used to dig a tunnel in virtually any shape.[5]

References

  1. Bagust, Harold (2006). The greater genius?: a biography of Marc Isambard Brunel. Ian Allan Publishing. p. 65. ISBN 0-7110-3175-4.
  2. 2.0 2.1 Becket, Derrick (1980). Brunel's Britain. Newton Abbot: David & Charles. ISBN 0-7153-7973-9. Chapter 10: "Tunnels".
  3. John C Gillham, The Waterloo & City Railway, The Oakwood Press, Usk, 2001, ISBN 0 85361 525 X
  4. "The Tube: An Underground History, broadcast 16 May 2013". bbc.co.uk. 2013. Retrieved 17 May 2013.
  5. "Special Shield Tunnels". Nippon Civic Consulting Engineers Co., Ltd. Retrieved 2011-07-24.

Further Reading

A full description of the tunnelling works for the Waterloo & City Railway, including the Greathead shield work and the compressed air arrangements, is given in the periodical The Engineer for 26 July 1895 and 2 August 1895; these can be seen online at Graces Guide .

External links