Tongue River Railroad

The Tongue River Railroad is a planned rail line in Southern Montana that would connect the region around Ashland, Montana with a BNSF Railway line to the north; over the project's lifespan, various routings have been studied. The project was first proposed in the 1980s, but has yet to move out of the development and planning stages.

Early attempts 1981-1998

The first incarnation of the Tongue River Railroad began in 1981, when three companies, DS Cartage Corporation, Otter Creek Transportation Company, and Transportation Properties Inc., a Washington Energy Company subsidiary, formed a consortium to build a roughly 80 miles (130 km) railroad from Miles City, Montana, where it would connect with the Burlington Northern Railroad, to Ashland, where Billings, Montana-based coal company Montco planned to build a large surface coal mine.[1][2] The plan was approved in 1986 by the Interstate Commerce Commission, but never built.[3]

As a result of lower coal prices in the late 1980s, plans for the railroad were tabled.[4] However, as the implementation of the Clean Air Act required coal burning power plants to use low-sulfur coal of the kind in southern Montana, a revived proposal for a 177 miles (285 km) route, estimated to cost about $117 million, emerged in the early 1990s, led by developer Mike Gustafson.[4] The Surface Transportation Board (STB) approved that route, from Miles City to Birney, Montana, in 1996.[3][4]

2007 to present

The railroad was still not built, however, and by 2007 a third route had emerged, which would terminate the line at Decker, Montana, where an existing BNSF line moved trains south onto a circuitous routing to Miles City.[3] This 130 miles (210 km) alignment allowed the Tongue River line to serve both existing coal traffic as well as new mines along the route.[3] In October 2007, the STB approved the routing and granted approval to begin construction on an initial 17 miles (27 km) section of track on the southern end of the route.[3] The planned construction was halted two years later, however, when in July 2009 the Montana Department of Fish and Wildlife rejected Tongue River's request for an easement to build through a fish hatchery.[5]

In March 2010, the state of Montana agreed to lease the Otter Creek coal tracts to Arch Coal, allowing the project, now on a 106 miles (171 km) routing, to again move forward.[6] In July 2011, plans again changed when rights to the project were purchased from developer Gustofson by Arch Coal, BNSF, and Forrest Mars, ex-CEO of Mars, Inc.[7] With the ownership change, the route was once again cut back to Ashland, to avoid going through Mars' personal ranch near Birney.[7]

In late December 2011, the 9th Circuit Court of Appeals ordered the STB to conduct a new environmental impact statement for the Tongue River line, as well as review construction permits for two parts of the route.[8] The ruling came after a coalition made up of the Northern Plains Resource Council, the city of Forsyth, Montana, the United Transportation Union, and private individual Mark Fix challenged the STB's earlier approval of the route.[8]

As part of the STB's review, the board in June 2012 required the Tongue River Railroad to file a new application, in light of changing plans and routes since the 2007 approval.[9] In December 2012, Tongue River Railroad issued a new application for a shorter 42 miles (68 km) line between Ashland and the BNSF line at Colstrip, Montana, instead of Miles City.[10] According to the railroad, the route had been considered in the past, but rejected due to steep grades; however, advances in distributed power on trains had made it feasible.[10] The new alignment was estimated to cost $416 million, as opposed to $490 million for the Miles City route.[10]

The STB's latest environmental impact study was originally expected to be completed in 2013, but was delayed until April 2015, [11] when the board released the draft EIS for public comment before it issues a final decision.[12] The board studied both the proposed route, as well as five alternatives, which would transport an estimated 20 million tons of coal annually on 26 trains each way per week.[12]

References

  1. "MONTANA AREA IS IN BITTER FIGHT OVER COAL MINE AND A RAILROAD". The New York Times. 5 August 1984. Retrieved 22 December 2012.
  2. "STB completes final environmental impact statement for Tongue River Railroad". Trains Magazine. 16 October 2006. Retrieved 22 December 2012.
  3. 3.0 3.1 3.2 3.3 3.4 "Tongue River Railroad gets final okay". Trains Magazine. 10 October 2007. Retrieved 25 April 2015.
  4. 4.0 4.1 4.2 "Rail Plan Splits Scenic Montana Area". The New York Times. 13 December 1998. Retrieved 25 April 2015.
  5. "Tongue River Railroad faces setback". Trains Magazine. 13 July 2009. Retrieved 25 April 2015.
  6. "Coal land lease clears way for Tongue River Railroad". Trains Magazine. 22 March 2010. Retrieved 25 April 2015.
  7. 7.0 7.1 "Billionaire buys part of Tongue River Railroad". Billings Gazette. 20 July 2011. Archived from the original on 24 April 2015. Retrieved 25 April 2015.
  8. 8.0 8.1 "Court orders new environmental review for Tongue River Railroad". Trains Magazine. 4 January 2012. Retrieved 25 April 2015.
  9. "Tongue River Railroad Co. to file revised application with STB". Progressive Railroading. 19 June 2012. Archived from the original on 24 April 2015. Retrieved 25 April 2015.
  10. 10.0 10.1 10.2 "New route picked for Montana's Tongue River Railroad". Trains Magazine. 20 December 2012. Retrieved 25 April 2015.
  11. "Tongue River Railroad construction plagued with further delays". Trains Magazine. 21 July 2014. Retrieved 25 April 2015.
  12. 12.0 12.1 "STB issues Tongue River environmental study for public comment". Trains Magzine. 20 April 2015. Retrieved 25 April 2015.