King Albert Park MRT Station

 DT6 
King Albert Park MRT Station
阿尔柏王园地铁站
அரசன் ஆல்பர்ட் பார்க்
Stesen MRT King Albert Park
Rapid transit
Coordinates 1°20′08″N 103°47′02″E / 1.335628°N 103.783983°E
Operated by SBS Transit DTL
Line(s)
Platforms Island
Tracks 2
Connections Bus, Taxi
Construction
Structure type Underground
Platform levels 2
Disabled access Yes
Other information
Station code  DT6 
History
Opened Q1 2016
Services
Preceding station   Mass Rapid Transit   Following station
towards Bukit Panjang
Downtown Line
Stage 2 (Under Testing)
towards Expo
Downtown Line
Future service
towards Sungei Bedok
Location

King Albert Park MRT Station (DT6) is an underground Mass Rapid Transit station on the Downtown Line Stage 2 in Singapore, formerly known as the Bukit Timah Line. The station will serve the Bukit Timah corridor at the junction between Bukit Timah Road and Blackmore Drive, in an area which is largely residential; and staff and students of the nearby Ngee Ann Polytechnic[1]

History

Construction incidents

Residents of Maplewoods condominium are concerned about the safety of both drivers and pedestrians near the condominium and are hoping for better solutions to the problems resulting from the construction of the station along Upper Bukit Timah Road after a dialogue session with the Land Transport Authority and their MP for Holland-Bukit Timah Christopher de Souza.

The Authority offer to retain the footpath after pedestrian safety concerns were voiced. But keeping it meant the footpath will have to be narrowed to accommodate construction works. At the same time, proposals were also offered to re-draw the access into and out of the condominium for vehicular safety. Vehicles entering the launch shaft construction site will assemble opposite it and drive across the entrance.

The residents complained that the construction site for the tunnel boring machine is a little too close to home for residents at Maplewoods as it will be right up to their main entrance. They claimed that is an accident waiting to happen. Construction works thus ceased on 6 June 2011.[2]

The Land Transport Authority hopes to start carrying out diversion works along Upper Bukit Timah Road on 3 July 2011, after delays due to concerns expressed by residents of the condominium.[3]

After further delays, on 12 July 2011 work on the train station along Bukit Timah Road resumed and picked up pace again within three days after work was stopped by the Maplewood residents who demanded that a launch shaft for a tunnelling machine to be sited at Sixth Avenue, but authorities have studied this proposal and found it not feasible, since the shophouses there will have to make way for construction works.[4]

Soil near station sinks

About 25-metre (82 ft) of the rightmost two lanes on Bukit Timah Road has been closed off to traffic after a nearby drain embankment caved in on 17 January 2012 in the course of tunnelling works for the Downtown Line. Engineers found a 14m precast segment of the Bukit Timah canal wall near the junction of Bukit Timah Road and Clementi Road dislodged, and some gaps in the ground were formed around that segment of the canal. It then stopped its tunnelling works to ensure safety and has begun to inject cement to stabilise the ground.[5]

LTA announced that DTL2 is set to open from Q1 2016.

Station layout

L1 Street Level
B1 Concourse Faregates, Ticketing Machines, Station Control, Transitlink Counter
B2 Platform A Downtown Line (under construction) towards  DT35  CG1  Expo via  DT7  Sixth Avenue (→)
Downtown Line (under construction) towards  DT19  NE4  Chinatown via  DT7  Sixth Avenue (→)
Island platform
Platform B Downtown Line (under construction) towards  DT1  BP6  Bukit Panjang via  DT5  Beauty World (←)

Transport connections

Rail

Destination First Train Last Train
Mon – Sat Sunday &
Public Holiday
Daily
Downtown Line
to DT1 Bukit Panjang
to DT19 Chinatown

References