Kandadji Dam

Kandadji Dam
Location of Kandadji Dam
Location Tillabéri Department, Niger
Coordinates 14°35′24″N 1°05′00″E / 14.5900°N 1.0833°ECoordinates: 14°35′24″N 1°05′00″E / 14.5900°N 1.0833°E
Construction began 2011
Opening date 2015 (estimated)
Operator(s) Haut Commissariat à l'Aménagement de la Vallée du Niger (High Commission for Niger Valley)
Dam and spillways
Impounds Niger River
Height 28 m (92 ft)[1]
Length 8,780 metres (9,600 yd)[1]
Spillway capacity 3,150 m3 (111,000 cu ft)[1]
Reservoir
Total capacity 1,596,000 megalitres (1,294,000 acre·ft)[1]
Surface area 282 km2 (109 sq mi)[1]
Max. water depth 5.67 m (18.6 ft)[1]
Power station
Turbines 4
Installed capacity 130 MW (170,000 hp)

The Kandadji Dam, when completed, will be a large multipurpose dam on the Niger River. The site is situated near the small town of Kandadji, Tillabéri Department, Tillabéri Region, Niger, 180 km northwest of the capital Niamey.[2] Construction of the dam was begun in August 2008.[3] It is being built by the Haut Commissariat à l'Aménagement de la Vallée du Niger (High Commission for Niger Valley), a public body under the Primer Minister's Office. The dam will generate hydropower and is aimed at controlling the flow of the Niger River, holding water during the dry season to maintain a minimum flow and making downstream irrigation possible. The project is formally named the Kandadji Programme for Ecosystem Regeneration and Niger River Development (Programme Kandadji de Régénération des Ecosystèmes et de Mise en Valeur du Fleuve Niger). The dam itself was expected to be completed in 2013 as of 2008[4] and as of September 2015 in 2012.[5]

The project is a very high profile project for Niger. According to the Prime Minister at the time of initiating construction, Seyni Oumarou, "no other development project will have sparked so much long term interest or such high expectations". The first brick of the dam was laid by the President of Niger, Mamadou Tandja.[4]

History

The project was first proposed in the 1970s, when a larger dam had been considered. In 1998 the African Development Bank approved funding for a feasibility study that was conducted by the German consulting firm Lahmeyer. Under the study, an environmental and social diagnosis and an initial environmental and social assessment were conducted. The findings were presented in 2002. In August 2002 the government decided by Decree to go ahead with the project, which was from now on called the Kandadji Ecosystems Regeneration and Niger Valley Development Programme. Subsequently, a detailed environmental and social impact assessment including, a Population Resettlement Plan and a Local Development Plan, was conducted. The Local Development Plan was designed to facilitate the economic transition of displaced persons in order to restore their standard of living or even enhance it, beyond mere resettlement. The final design of the dam was prepared with financing from the Islamic Development Bank, and that of a 2,000 hectares (4,900 acres) irrigation project with financing from the West African Development Bank.[6] In 2005 and 2006 consultations were undertaken as part of the environmental and social assessment, which included participants from the World Wide Fund for Nature and International Union for Conservation of Nature.[7] According to one source, construction of the dam was begun in August 2008. In April 2009 a workshop on benefit sharing from dams in West Africa was held in Niamey organized by the Niger Basin Authority, the International Institute for Environment and Development and the International Union for Conservation of Nature. The workshop recommended to improve the communication towards the people affected by the dam and to pay particular attention to legal processes related to resettlement, and to continue to reflect on a future management structure to equitably share the benefits of the dam.[8] In November 2009 a process to select consultants to accompany the resettlement has been initiated.[9]

According to the World Bank, the entire Kandadji Program will be implemented in three phases:

Construction of the dam itself was contracted to Russian company Zarubezhvodstroy, which signed the construction contract in September 2010.[11] Construction of the dam was relaunched at a ceremony on 23 May 2011, following the election of President Mahamadou Issoufou.[12][13][14][15] The Kandaji Dam is the first object being constructed by a Russian company in Niger.[16] In May 2011, the Director General of Zarubezhvodstroy, OJSC E.V. Gudzenchuk, announced "For the first time a Russian company is involved in building such a large project in West Africa at the expense of foreign investors. Zarubezhvodstroy has vast experience in the field that would allow us to meet the challenges with confidence and with great professionalism."[16]

Plans were announced in June 2011 to relocate 5383 individuals and 770 families who will be displaced by the dam.[17]

Technical features

The earth dyke dam will be 8.4 km dam long, creating a reservoir of 1.6 billion m3 and a regulated discharge of 120 m3/s (3.8 km3/year) in Niamey. The hydroelectric plant will have a capacity of 130 megawatt, and a 132 kilovolt high voltage line will be built over 188 km to Niamey. Irrigation development will consist of a first phase of 6,000 hectares mainly for the benefit of resettled communities, with a medium-term target in 2034 of 45,000 hectares out of an irrigable potential of 122,000 hectares.[18]

Benefits

The expected benefits include increased agricultural production and hydropower generation. Niger imports almost half of its electricity consumption of 440 million kilowatt-hours (1.6×109 MJ) (2007) from neighboring Nigeria, which itself suffers frequent power cuts. The plant would increase installed capacity in Niger from 240 Megawatt (MW) in 2007 to 370 MW (+55%).[19] Other expected benefits are related to "drinking water supply, sanitation, improved flood recession cropping, grazing and fishery".[20]

Financial costs

The financial costs of the broader project, including the infrastructure for irrigation and drinking water supply, were estimated at US$670 million by one source in 2007.[21] Another source mentions US$942 million in 2011.[22] The contract to build the dam itself, however, is apparently only worth Euro 130million.[11] According to the World Bank, the Kandadji Program (Phase I and Phase II) is expected to cost US$785 million.[10]

Financing

Financing comes from ten sources: the African Development Bank, the Islamic Development Bank, the West African Development Bank, the Saudi Fund for Development, the Kuwait Fund for Arab Economic Development, the OPEC Fund for International Development, the Arab Bank for Economic Development in Africa, the Bank for Investment and Development of the Economic Community of West African States (ECOWAS) and the Government of Niger.[11]

Specific amounts are as follows, as far as known:

[20]

Financing for the hydropower station itself is due to come from a public-private partnership.[4][23]

Environmental, social and downstream impact

Negative social impacts include the resettlement of almost 35,000 people from 15 villages, loss of infrastructure (a national road, boreholes, clinics, schools, mosques, slaughterhouses, markets and grain mills) and loss of about 7,000 ha of agricultural land. According to a 2007 report by UNEP's Dams and Development Project, which itself was a follow-up activity to a report by the World Commission on Dams, the Kandadji project "serves as a useful example of the projection and estimation of social effects, which appears to have been widely encompassing, covering both negative impacts and benefits". These impacts were "projected at an early stage in project planning, enabling issues and potential impacts to be addressed in subsequent planning phases".[26]

The project is expected to improve the river's ecology, which has suffered from a 30% decline in river flows since the 1970s.[27] The dam would regulate flows. According to press reports from Nigeria, the project would reduce the river flow to Nigeria by at least 10 percent, thus jeopardizing power production from two existing dams in Nigeria and meaning a "colossal loss (...) to the agricultural capacity of (Nigerian) states that border the River Niger".[28] However, according to the 2008 environmental assessment of the project, the "modifications of the quantities of water flowing into the Niger River as a result of the Kandadji dam will be minimal in Nigeria". The average loss through evaporation and modification of the Niger River water flows in Nigeria will be low (2.3% at Jebba) and there will be positive impacts by improving the minimum water level in Nigeria.[29]

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 "Programme Kandadji de Régénération des Écosystèmes et de Mise en valeur de la vallée du Niger. Detailed Environmental and Social Impact Assessment". Tecsult Limited. November 2006. p. 5. Retrieved 29 April 2013.
  2. Kandadji, Niger Page. Falling Rain.com. Retrieved 2009-02-01
  3. Niger / AfD Bank Group President receives Niger’s Finance and Economy Minister. African Press Organization (APO). October 10, 2008/
  4. 4.0 4.1 4.2 ReutersAlertNet:Niger begins building dam for food, electricity, 4 August 2008
  5. "Niger Criticizes Russian Company Over Delays on Hydropower Dam". Bloomberg. 2 March 2012. Retrieved 29 April 2013.
  6. Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:“KANDADJI” ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 1-2
  7. Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT, EXECUTIVE SUMMARY, January 2008, p. 12
  8. IUCN:Les acteurs échangent sur le partage des bénéfices et la gestion des réservoirs, 6 May 2009
  9. Niger seeks relocation consultants for 125-MW Kandadji, 20 November 2009
  10. 10.0 10.1 10.2 "The Kandadji Program in the Sahel". World Bank. Retrieved 29 April 2013.
  11. 11.0 11.1 11.2 "News". Zarubezhvodstroy. 23 May 2011. Retrieved 29 April 2013.
  12. Le président du Niger lance la construction d’un barrage hydro-électrique. PANA Press, 2011-05-24
  13. Russian firm starts work on Niger hydro dam. Abdoulaye Massalatchi Reuters – Tue, May 24, 2011]
  14. Présentation du Barrage de Kandadji
  15. NIGER - Kandadji a free pass for Moscow - Africa Energy Intelligence
  16. 16.0 16.1 "Kandaji Dam: History". Zarubezhvodstroy» OJSC. Retrieved July 18, 2012.
  17. Les riverains du barrage de Kandadji seront déplacés et indemnisés - Afriquinfos
  18. Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:“KANDADJI” ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 3-4
  19. U.S. Energy Information Administration:http://tonto.eia.doe.gov/country/country_energy_data.cfm?fips=NG Niger Energy Profile, accessed on January 10, 2009
  20. 20.0 20.1 AfricanManager:Saudi Fund grants US$20 million to Niger for Kandadji dam, 9 January 2010
  21. Reuters:Niger says secures $236 mln Islamic funding for dam, 3 December 2007
  22. Russian firm starts work on Niger hydro dam. Abdoulaye Massalatchi Reuters – Tue, May 24, 2011]
  23. 23.0 23.1 "African bank funds Niger's 125-MW Kandadji Dam, ecosystems". HydroWorld.com. Retrieved July 19, 2012.
  24. OFID:Commitments in 2008, accessed on January 9, 2010
  25. African Development Bank:Niger: US$62 Million ADF Funding for the development of Niger Valley Ecosystems, 31 October 2008
  26. UNEP:DAMS AND DEVELOPMENT PROJECT, COMPENDIUM ON RELEVANT PRACTICES, Social Impact Assessment of Affected People, Final Report, August 2007, p. x, accessed on January 10, 2009
  27. Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:“KANDADJI” ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 2
  28. BusinessdayOnline:New dam on River Niger: Why it is crucial Nigeria responds, 8 January 2009, by Martin Ayankola
  29. Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT, EXECUTIVE SUMMARY, January 2008, p. 11

Further sources