Ilısu Dam

Ilısu Dam

Model of the dam
Location of Ilısu Dam
Official name Ilısu Baraji
Country Turkey
Location Dargeçit, Mardin Province, Turkey
Coordinates 37°31′52.20″N 41°50′58.75″E / 37.5311667°N 41.8496528°ECoordinates: 37°31′52.20″N 41°50′58.75″E / 37.5311667°N 41.8496528°E
Purpose Power
Flood control
Irrigation
Status Under construction
Construction began August 5, 2006
Opening date 2015 (est.)
Construction cost US$1.7 billion
Owner(s) State Hydraulic Works
Dam and spillways
Type of dam Embankment, rock-fill
Impounds Tigris
Height (thalweg) 135 m (443 ft)
Length 1,820 m (5,971 ft)
Elevation at crest 530 m (1,739 ft)
Width (crest) 15 m (49 ft)
Width (base) 610 m (2,001 ft)
Dam volume 43,800,000 m3 (35,509 acre·ft)
Spillway type Service overflow, controlled-chute
Spillway capacity 18,000 m3/s (635,664 cu ft/s)
Reservoir
Creates Ilısu Reservoir
Total capacity 10,410,000,000 m3 (8,440,000 acre·ft)
Active capacity 7,460,000,000 m3 (6,050,000 acre·ft)
Inactive capacity 2,950,000,000 m3 (2,390,000 acre·ft)
Catchment area 35,517 km2 (13,713 sq mi)[1]
Surface area 313 km2 (121 sq mi)[2]
Max. length 244 km (152 mi) (combined)
Max. water depth 126.8 m (416 ft)
Normal elevation 525 m (1,722 ft)
Power station
Commission date 2015 (est.)
Hydraulic head 122.6 m (402 ft) (gross)
Turbines 6 x 200 MW Francis-type
Installed capacity 1,200 MW
Annual generation 3,833 GWh (est.)
Website
ilisuprojesi.com

The Ilısu Dam (Turkish pronunciation: [ɯɫɯˈsu]) is an embankment dam under construction on the Tigris near the village of Ilısu and along the border of Mardin and Sirnak Provinces in Turkey. It is one of the 22 dams of the Southeastern Anatolia Project and its purpose is hydroelectric power production, flood control and water storage. When complete, the dam will support a 1,200 MW power station and will form a 10.4 billion m3 reservoir. Construction of the dam began in 2006 and it is expected to be complete by 2015.[3] As part of the project, the much smaller Cizre Dam is to be constructed downstream for irrigation and power. The dam has drawn international controversy,[4] because it will flood portions of ancient Hasenkeyf and necessitate the relocation of people living in the region. Because of this, the dam lost international funding in 2008.[5]

Design

The Ilısu Dam will be a 135 m (443 ft) high and 1,820 m (5,971 ft) wide rock-fill embankment dam with a structural volume of 43,900,000 m3 (35,590 acre·ft). It will be 15 m (49 ft) wide at its crest and 610 m (2,001 ft) wide at its base. The dam will have an overflow spillway on its right bank which will be controlled by eight radial gates which will pour into four chutes before the water reaches a plunge pool. Its power station will be above ground and will contain 6 x 200 MW Francis turbine-generators with an expected annual generation of 3,833 GWh and gross hydraulic head of 122.6 m (402 ft). The dam's reservoir will have a capacity of 10,400,000,000 m3 (8,431,417 acre·ft), of which 7,460,000,000 m3 (6,050,000 acre·ft) will be active (or live, useful) storage and 2,950,000,000 m3 (2,390,000 acre·ft) will be inactive (dead) storage. At a normal elevation of 525 m (1,722 ft) above sea level, the reservoir surface area will cover 313 km2 (121 sq mi).[2][6][7][8]

Background

A study for the dam was made in 1954 and in 1997 it was added to the national plan. On August 5, 2006 the foundation stone for the dam was laid and initial construction began.[9]

Funding issues

To avoid inflation and other economic repercussions, the Turkish Government has often sought outside assistance to fund the Ilısu Dam Project. However, pressure from environmental and human rights groups have often halted this process. In 2000, the British Government declined $236 million in funding for the Ilısu Dam. Before the 2006 ground-breaking ceremony, German, Swiss and Austrian export credit agencies had agreed to fund $610 million of the project. In December 2008, the European firms suspended funds for the dam and gave Turkey a 180-day period to comply with over 150 international standards. In June 2009, after failing to meet the standards, the European firms officially cut the funding for the Ilısu Dam Project. Shortly after the announcement of the funding loss, Turkey's Environment Minister Veysel Eroğlu said “Let me tell you this, these power plants will be built. No one can stop it. This is the decision of the state and the government.” Turkey's Prime Minister Recep Tayyip Erdoğan is also committed to the Ilısu Dam Project as well and claims Turkey will use internal or other international funding. Turkey stated that construction would start again in July 2009.[10] In February 2010 it was announced that loans had been granted and the project would continue.[11] On 15 July 2010, Andritz Hydro lifted a temporary suspension on supplying parts to the project and announced it would provide the six 200 MW Francis turbines for the power plant.[12]

Construction

As part of early and ongoing construction, 52 km (32 mi) of roads are subject to raising and repairing work. A 110 m (361 ft) long temporary bridge was constructed upstream of the dam site which is supported by 30 sections of steel pipe. Additionally, a 250 m (820 ft) permanent steel-girder bridge with concrete supports was constructed just downstream of the dam.[9] Construction of new Ilısu and Koçtepe villages are currently underway as well as the relocation of major portions of Hasankeyf. Excavations for the main body of the dam began in May 2011 and the first loads of fill were laid in January 2012.[13] Diversion of the Tigris River began during a ceremony on 29 August 2012.[14] As of April 2014 the project is 60% complete while the resettlement of Hasankeyf is 73% complete. All works are expected to be completed in 2015.[15]

In January 2015 Kurdistan Workers' Party (PKK) threatened the lives of workers at the dam site. On 3 February 2015 a convoy of supplies for the dam was attacked, injuring three. Several days later a worker was killed in his home by suspected PKK militants.[16][17]

Controversy

Hasankeyf.

According to KHRP, completion of the Ilısu Dam will cause the flooding of the ancient city of Hasankeyf, whose history stretches back over 10,000 years. About 185 settlements (villages and hamlets) will be fully or partially affected by flooding. The involuntary resettlement process will involve 55,000–65,000 people (40,000 Turkish Gov't estimates). Census data is not available yet.

Alternatively, Recep Tayyip Erdoğan, at the ground-breaking ceremony, stated : "The step that we are taking today demonstrates that the south-east is no longer neglected. This dam will bring big gains to the local people." Ankara hopes that the dam - part of a long-term plan to develop the poor, mainly Kurdish region - will create up to 10,000 jobs, irrigate farmlands and attract tourists. The government has promised to compensate local people who will lose their homes and that all the valuable artifacts will be relocated before the dam's completion in 2015.[18]

See also

References

  1. "Ilısu Projesi" (PDF) (in Turkish). Ekindusu. Retrieved 10 May 2013.
  2. 2.0 2.1 "Ilısu Dam Environmental Impact Assessment" (PDF). State Hydraulic Works. 2005. pp. TABLE 2–2 (PDF Pages 110–111). Retrieved 20 May 2013.
  3. "Ilısu Project Target 2014". Haberler. 17 October 2012. Retrieved 9 May 2013.
  4. http://iraqmarshrestoration.blogspot.co.uk/2010/08/ilusu-dam.html
  5. http://iraqmarshrestoration.blogspot.co.uk/p/press-release-doga-dernegi-support-for.html
  6. "DSI X. REGIONAL OFFICE - DİYARBAKIR - Mardin Office" (in Turkish). State Hydraulic Works. Retrieved 15 January 2011.
  7. "Ilısu Dam and Hydroelectric Power Plant" (in Turkish). Nurol Construction and Trading Co. Retrieved 15 January 2011.
  8. "Ilısu Dam and Hydroelectric Power Plant be completed in 2014" (in Turkish). Construction and Building News. Retrieved 15 January 2011.
  9. 9.0 9.1 "DESCRIPTION and HISTORY". Ilisu Baraji. Retrieved 2011-01-15.
  10. Angell, Elizabeth (2009-08-19). "The Ilisu Dam's Uncertain Future". Chinadialogue.net. Retrieved 2011-05-15.
  11. "Turkey says to continue Ilisu dam project Erdogan said the construction of a dam and". World Bulletin. 12 February 2010. Retrieved 15 January 2011.
  12. "Andritz Hydro to equip Ilisu hydropower project in Turkey". Hydro World. 23 June 2010. Retrieved 10 May 2013.
  13. "Ilisu Project Status Report" (PDF) (in Turkish). State Hydraulic Works. 26 April 2013. Retrieved 20 May 2013.
  14. "Ilisu Dam Diversion was initiated.". State Hydraulic Works. 28 August 2012. Retrieved 9 May 2013.
  15. "Ilisu Projesi İş İlerleme Durum Raporu" (PDF) (in Turkish). State Hydraulic Works. 4 April 2014. Retrieved 12 May 2014.
  16. "workers threatened the PKK bloody executions" (in Turkish). Yeni Safak. 8 February 2015. Retrieved 15 February 2015.
  17. "Material Ilisu Dam moved to convoy attack: 3 injured" (in Turkish). Vatan. 3 February 2015. Retrieved 15 February 2015.
  18. Turkey begins controversial dam, August 5, 2006, BBC News