Huey P. Long Bridge (Jefferson Parish)

This article is about a bridge in Jefferson Parish, Louisiana; a second Huey P. Long Bridge is in Baton Rouge, Louisiana.
Huey P. Long Bridge

Huey Long Bridge in 2007, before widening work
Coordinates 29°56′39″N 90°10′08″W / 29.94417°N 90.16889°W
Carries 6 lanes of US 90
2 tracks of the NOPB
Crosses Mississippi River
Locale Jefferson Parish, Louisiana
Maintained by New Orleans Public Belt Railroad
ID number 022600060100001
Characteristics
Design Cantilever truss bridge
Total length 8,076 feet (2,462 m) (road)
22,996 feet (7,009 m) (rail)
Longest span 790 feet (241 m)
Clearance below 153 feet (47 m)
History
Construction cost $13.4 million[1][2]
Opened December 1935
Statistics
Daily traffic 43,000 (2008)

The Huey P. Long Bridge, located in Jefferson Parish, Louisiana, is a cantilevered steel through truss bridge that carries a two-track railroad line over the Mississippi River at mile 106.1 with three lanes of US 90 on each side of the central tracks.

Opened in December 1935 to replace the Walnut Street Ferry, the bridge was named for the popular and notorious governor, Huey P. Long, who had just been assassinated on September 8 of that year. The bridge was the first Mississippi River span built in Louisiana and the 29th along the length of the river. It is a few miles upriver from the city of New Orleans. The East Bank entrance is at Elmwood, Louisiana and the West Bank at Bridge City. It was designed by Polish-American engineer Ralph Modjeski.

On June 16, 2013, a $1.2 billion widening project by the Louisiana Department of Transportation and Development was completed and opened to motorists. The bridge now consists of three 11-foot lanes in each direction, with inside and outside shoulders. Prior to the expansion, there were two 9-foot lanes in each direction with no shoulders.

in 2014, a writer in The New Yorker described the bridge as "a structure so vaulting and high that it seems to extend from one white, towering Gulf Coast cloud to the next."[3]

Structure

USS New Orleans passes under the bridge, March 2007

The widest clean span is 790 feet (240 m) long and sits 135 feet (41 m) above the water. There are three navigation channels below the bridge, the widest being 750 feet (230 m). The distinctive rail structure is 22,996 feet (7,009 m) long and extends as a rail viaduct well into the city. It has sometimes been described as the longest rail bridge in the US, but the nearby Norfolk Southern Lake Pontchartrain Bridge, at 5.8 miles (9.3 km), is considerably longer. The highway structure is 8,076 feet (2,462 m) long with extremely steep grades on both sides. As originally constructed, each roadway deck was a precarious 18 feet (5.5 m) wide, with two nine-foot lanes; but because of the railroad component, it is unusually flat. Normally, bridges its height have a hump, but this bridge was designed flat to facilitate rail traffic.[4]

The bridge is a favorite railfan location. It is owned by the New Orleans Public Belt Railroad, which is owned by the City of New Orleans and managed by the Public Belt Railroad Commission. The bridge was hated by many drivers in the New Orleans area due to the narrow 9-foot (2.7 m) wide lanes without shoulders before it was widened. Additionally, where the East Bank approach met the superstructure of the bridge, the two vehicular roadways "jogged" or shifted inwards towards the bridge centerline about 1 12 feet (0.46 m) since the through-truss portion of the superstructure was 3 feet (0.91 m) wider than the deck truss portion of the east approach.

The foundation of the bridge is also unique. The land in and around New Orleans was formed by silt deposits brought down the Mississippi River. The clay topsoil (notorious for its role in the Hurricane Katrina levee failures) is compressible and unsuitable for foundation loads. However, bedrock is around 1,000 feet (300 m) below the surface, making it too deep for normal bridge foundation construction. So, the main piers are seated on a layer of fine sand 160 to 170 feet (52 m) below Mean Gulf Level and rely on their massive weight and girth to hold them in place.

The bridge dates from an era when the construction of large works presented significant engineering challenges and the needs of rail and auto travel were more matched than they are today. Large bridges mixing rail tracks and highways were common, as typified by the MacArthur Bridge and McKinley Bridge in St. Louis, Missouri and the Harahan Bridge in Memphis, Tennessee. A second Huey P. Long Bridge, which is very similar to the design of this bridge before its renovation, was built further upstream in 1940 in Baton Rouge, Louisiana and was mainly the last of its kind. While both of the Long bridges still carry both types of traffic, most of the others have been converted either to entirely rail use (Harahan since 1949, MacArthur since 1981) or entirely auto use (McKinley since 1978), sometimes with bicycle and/or pedestrian use added (McKinley in 2007, Harahan by mid-2014), and new large bridges are always devoted exclusively to meeting increasing vehicular traffic needs. Current rail demands are well met by existing bridges that are a testament to the care and craftsmanship of early 20th-century bridge builders.

History

The history of the Huey P. Long bridge is almost as complex as the bridge structure itself. As early as 1892 the Southern Pacific Railway proposed a high level bridge, but a depression that year prevented further work on a project that would have been an overwhelming challenge for the engineers of the time due to soil conditions and extremely high clearances needed to clear river navigation. With the development of the Public Belt Railroad, interest in a river rail crossing grew and lead to passage of a constitutional amendment in 1916 granting the city exclusive power to build and operate a crossing. Three general ideas emerged from the planning process: a low-level drawbridge, a tunnel and a high-level bridge. The tunnel idea died first because it would have provided limited capacity and the War Department (after years of wrangling) ultimately rejected the idea of a drawbridge as too problematic for such a significant concentration of vital transportation infrastructure.

Work on the design of the bridge began in earnest in 1925 by the engineering firm of Modjeski and Masters. Some pilings were actually driven that year to prevent expiration of congressional authority and provide further information for the design. As the magnitude of the project became apparent and projected costs ballooned, financing difficulties compounded by the Great Depression delayed the project. Finally, on November 5, 1932, the bonds of the Public Belt Railroad Commission were guaranteed by a complex agreement between the Southern Pacific Railroad, the City of New Orleans and the State of Louisiana. Main construction contracts were signed on December 30, 1932 and work formally started the following day. Construction of the bridge proceeded smoothly over a three-year period with only minor interruptions due to high water and a one-month strike in September 1933.

Expansion

The Huey P. Long Bridge Widening Project is a TIMED (Transportation Infrastructure Model for Economic Development) Program project. The TIMED Program was created by Act 16 of the 1989 Louisiana Legislature, was voted for by the people and is the single largest transportation program in state history. The Program is designed to enhance economic development in Louisiana through an investment in transportation projects.

The $1.2 billion widening project started in April 2006 and is the first change to the structure since it opened in 1935. The project expanded the structure from two 9-foot lanes to three 11-foot lanes with a 2-foot inside shoulder and an 8-foot outside shoulder. It also included new signalized intersections to replace the traffic circle at Jefferson Highway and Bridge City Avenue in Jefferson Parish, LA.

Project Details

This seven-year-long, four-phase project was completed in 2013. The timeline of the project was as follows:

Phase I: Main Support Widening (Piers)
In this phase, completed in May 2009, four river piers and one land pier were widened to support the additional lanes. Reinforcing framework and concrete filled the void sections of the piers to strengthen them. In addition, w-shaped metal bridge struts were anchored to the upper part of each pier to support the additional new trusses and the existing truss.

Phase II: Railroad Modifications
In October 2006, work to relocate five selected railroad supports was done to facilitate the construction of the new approaches. This phase was completed in June 2008.

Phase III: Main Bridge Widening (Truss)
Completed in 2012, this phase widened the existing truss on either side to accommodate new travel lanes and shoulders.
The bridge, which is composed of four spans, was erected one span at a time. In November 2009, construction of the West Bank Anchor Span began by using the stick-built method, meaning each element of the span was individually placed. In order to minimize the use of falsework and river closures in the navigation or auxiliary channels the three remaining spans were done through the span-by-span method. This method involved large barges transporting a pre-assembled span section, positioning it under the bridge, and lifting it into position using strand jacks. Temporary stability frames made up of floorbeams and towers were used to support the span section during the lifting process.

This phase was completed on April 29, 2012, when traffic was shifted from the original lanes (two 9-foot lanes in each direction, cantilevered on each side of the original truss) to two temporary lanes in each direction on the widened portion of the truss.[5]

Phase IV: New Approaches Construction
During this phase of the project, the two temporary lanes were widened to three 11-foot lane in each direction with 8-foot shoulders and 2-foot inside shoulders. The traffic circles at each end of the bridge were replaced with signalized intersections. Also, new roadway and elevated structures were constructed.

Four cameras were installed to view the approaches and ramps construction— two on the East Bank of Jefferson Parish and two on the West Bank of Jefferson Parish.


On February 5, 2013, Louisiana Department of Transportation and Development Secretary Sherri LeBas announced that the bridge would be fully open to drivers on June 16, 2013.[6]

See also

References and external links

Wikimedia Commons has media related to Huey P. Long Bridge, Jefferson Parish, Louisiana.

References

  1. Betsy Swanson (2003). Historic Jefferson Parish: From Shore to Shore. Pelican Publishing. p. 100.
  2. Andrea Shaw (13 June 2013), $1.2 billion Huey P. Long Bridge widening to end steering-wheel death grip, Nola, retrieved 7 August 2014
  3. Frazier, Ian, "Streetscape: Do Not Cross," The New Yorker, June 2, 2014, p. 26.
  4. http://www.johnweeks.com/lower_mississippi/pages/lmiss16.html
  5. http://www.timedla.com/bridge/long/activity/
  6. http://www.timedla.com/bridge/long/overview/