Huangdeng Dam
Huangdeng Dam |
---|
Construction site in 2011 |
Location of Huangdeng Dam |
Country |
China |
---|
Location |
Lanping Bai and Pumi Autonomous County, Nujiang Lisu Autonomous Prefecture, Yunnan |
---|
Coordinates |
26°33′21.65″N 99°6′40.55″E / 26.5560139°N 99.1112639°E / 26.5560139; 99.1112639Coordinates: 26°33′21.65″N 99°6′40.55″E / 26.5560139°N 99.1112639°E / 26.5560139; 99.1112639 |
---|
Purpose |
Power |
---|
Status |
Under construction |
---|
Construction began |
2010 |
---|
Opening date |
2015 (est.) |
---|
Dam and spillways |
---|
Type of dam |
Gravity, roller-compacted concrete |
---|
Impounds |
Lancang (Mekong) River |
---|
Height |
203 m (666 ft) |
---|
Length |
457 m (1,499 ft) |
---|
Total capacity |
1,613,000,000 m3 (1,308,000 acre·ft) |
---|
Power station |
---|
Commission date |
2015 (est.) |
---|
Type |
Conventional |
---|
Turbines |
4 x 475 MW Francis-type |
---|
Installed capacity |
1,900 MW |
---|
The Huangdeng Dam is a gravity dam currently under construction on the Lancang (Mekong) River in Lanping Bai and Pumi Autonomous County of Yunnan Province, China. Construction on the dam began in 2010 and its 1,900 MW hydroelectric power station is expected to be operational in 2015 with the entire project complete in 2016.[1][2]