Burj Khalifa

Burj Khalifa
برج خليفة

Burj Khalifa in October 2012
Former names Burj Dubai
Record height
Tallest in the world since 2010[I]
Preceded by Taipei 101
General information
Type Mixed-use
Architectural style Neo-Futurism
Location 1 Sheikh Mohammed bin Rashid Boulevard, Dubai, United Arab Emirates
Coordinates 25°11′49.7″N 55°16′26.8″E / 25.197139°N 55.274111°ECoordinates: 25°11′49.7″N 55°16′26.8″E / 25.197139°N 55.274111°E
Construction started 6 January 2004
Completed 30 December 2009
Opening 4 January 2010[1]
Cost USD $ 1.5 billion[2]
Height
Architectural 828 m (2,717 ft)[3]
Tip 829.8 m (2,722 ft)[3]
Roof 828 m (2,717 ft)
Top floor 584.5 m (1,918 ft)[3]
Observatory 555.7 m (1,823 ft)[3]
Technical details
Floor count

163 floors[3][4]
plus 46 maintenance levels in the spire[5] and 2 parking levels in the basement

(Total: 211 floors)
Floor area 309,473 m2 (3,331,100 sq ft)[3]
Lifts/elevators 58, made by Otis Elevator Company
Design and construction
Architect Adrian Smith at SOM
Developer Emaar Properties[3]
Structural engineer Bill Baker at SOM[6]
Main contractor Samsung Engineering and Construction Company, Besix and Arabtec
Supervision Consultant Engineer & Architect of Record Hyder Consulting
Construction Project Manager Turner Construction
Grocon[7]
Planning Bauer AG and Middle East Foundations[7]
Lift contractor Otis[7]
VT consultant Lerch Bates[7]
Website
www.burjkhalifa.ae

Burj Khalifa (Arabic: برج خليفة, "Khalifa Tower", pronounced English /ˈbɜr kəˈlfə/), known as Burj Dubai before its inauguration, is a skyscraper in Dubai, United Arab Emirates. It is the tallest man-made structure in the world, standing at 829.8 m (2,722 ft).[3][8]

Development

Construction began on 6 January 2004, with the exterior of the structure completed on 1 October 2009. The building officially opened on 4 January 2010,[1][9] and is part of the new 2 km2 (490-acre) development called Downtown Dubai at the 'First Interchange' along Sheikh Zayed Road, near Dubai's main business district. The tower's architecture and engineering were performed by Skidmore, Owings and Merrill of Chicago, with Adrian Smith as chief architect, and Bill Baker as chief structural engineer.[10][11] The primary contractor was Samsung C&T of South Korea.[12] The tower's construction was done by the construction division of Al Ghurair Investment group.[13][14]

Conception

Burj Khalifa was designed to be the centerpiece of a large-scale, mixed-use development that would include 30,000 homes, nine hotels (including The Address Downtown Dubai), 3 hectares (7.4 acres) of parkland, at least 19 residential towers, the Dubai Mall, and the 12-hectare (30-acre) man-made Burj Khalifa Lake. The decision to build Burj Khalifa is reportedly based on the government's decision to diversify from an oil based economy to one that is service and tourism based. According to officials, it is necessary for projects like Burj Khalifa to be built in the city to garner more international recognition, and hence investment. "He (Sheikh Mohammed bin Rashid Al Maktoum) wanted to put Dubai on the map with something really sensational," said Jacqui Josephson, a tourism and VIP delegations executive at Nakheel Properties.[15]

Height

Records

History of height increases

Burj Khalifa compared with some other well-known tall structures

There are unconfirmed reports of several planned height increases since its inception. Originally proposed as a virtual clone of the 560 m (1,837 ft) Grollo Tower proposal for Melbourne, Australia's Docklands waterfront development, the tower was redesigned by Skidmore, Owings and Merrill (SOM).[31] Marshall Strabala, an SOM architect who worked on the project until 2006, in late 2008 said that Burj Khalifa was designed to be 808 m (2,651 ft) tall.[32]

The design architect, Adrian Smith, felt that the uppermost section of the building did not culminate elegantly with the rest of the structure, so he sought and received approval to increase it to the current height. It has been explicitly stated that this change did not include any added floors, which is fitting with Smith's attempts to make the crown more slender.[33]

Delay

Emaar Properties announced on 9 June 2008 that construction of Burj Khalifa was delayed by upgraded finishes and would be completed only in September 2009.[34] An Emaar spokesperson said "The luxury finishes that were decided on in 2004, when the tower was initially conceptualized, is now being replaced by upgraded finishes. The design of the apartments has also been enhanced to make them more aesthetically attractive and functionally superior."[35] A revised completion date of 2 December 2009 was then announced.[36] However, Burj Khalifa was opened on 4 January 2010, more than a month later.[1][9]

Architecture and design

Cross-section comparisons of various towers. From top to bottom: Burj Khalifa, Taipei 101, Willis Tower, World Trade Center.

The tower was designed by Skidmore, Owings and Merrill (SOM), who also designed the Willis Tower (formerly the Sears Tower) in Chicago and the new One World Trade Center in New York City. Burj Khalifa uses the bundled tube design.[37][38] Proportionally, the design uses half the amount of steel used in the construction of the Empire State Building thanks to the tubular system.[37][39] Its design is reminiscent of Frank Lloyd Wright's vision for The Illinois, a mile high skyscraper designed for Chicago. According to Marshall Strabala, a SOM architect who worked on the building's design team, Burj Khalifa was designed based on the 73 floor Tower Palace Three, an all residential building in Seoul. In its early planning, Burj Khalifa was intended to be entirely residential.[32]

Subsequent to the original design by Skidmore, Owings and Merrill, Emaar Properties chose Hyder Consulting to be the supervising engineer with NORR Group Consultants International Limited chosen to supervise the architecture of the project.[40] Hyder was selected for its expertise in structural and MEP (mechanical, electrical and plumbing) engineering.[41] Hyder Consulting's role was to supervise construction, certify SOM's design, and be the engineer and architect of record to the UAE authorities.[40] NORR's role was the supervision of all architectural components including on site supervision during construction and design of a 6-storey addition to the Office Annex Building for architectural documentation. NORR was also responsible for the architectural integration drawings for the Armani Hotel included in the Tower. Emaar Properties also engaged GHD,[42] an international multidisciplinary consulting firm, to act as an independent verification and testing authority for concrete and steelwork.

The spiral minaret at the Great Mosque of Samarra

The design of Burj Khalifa is derived from patterning systems embodied in Islamic architecture.[19] According to the structural engineer, Bill Baker of SOM, the building's design incorporates cultural and historical elements particular to the region such as the spiral minaret. The spiral minaret spirals and grows slender as it rises.[43] The Y-shaped plan is ideal for residential and hotel usage, with the wings allowing maximum outward views and inward natural light.[19] As the tower rises from the flat desert base, there are 27 setbacks in a spiralling pattern, decreasing the cross section of the tower as it reaches toward the sky and creating convenient outdoor terraces. At the top, the central core emerges and is sculpted to form a finishing spire. At its tallest point, the tower sways a total of 1.5 m (4.9 ft).[44]

As part of a study which reveals the unnecessary "vanity space" added to the top of the world's tallest buildings by the Council on Tall Buildings and Urban Habitat (CTBUH), it was revealed that without its 244-metre spire, the 828-metre Burj Khalifa would drop to a substantially smaller 585-metre height without any reduction in usable space. As the report states, the spire "could be a skyscraper on its own".[17]

To support the unprecedented height of the building, the engineers developed a new structural system called the buttressed core, which consists of a hexagonal core reinforced by three buttresses that form the ‘Y' shape. This structural system enables the building to support itself laterally and keeps it from twisting.[19]

The spire of Burj Khalifa is composed of more than 4,000 tonnes (4,400 short tons; 3,900 long tons) of structural steel. The central pinnacle pipe weighing 350 tonnes (390 short tons; 340 long tons) was constructed from inside the building and jacked to its full height of over 200 m (660 ft) using a strand jack system. The spire also houses communications equipment.[45]

In 2009, architects announced that more than 1,000 pieces of art would adorn the interiors of Burj Khalifa, while the residential lobby of Burj Khalifa would display the work of Jaume Plensa, featuring 196 bronze and brass alloy cymbals representing the 196 countries of the world.[46] It was planned that the visitors in this lobby would be able to hear a distinct timbre as the cymbals, plated with 18-carat gold, are struck by dripping water, intended to mimic the sound of water falling on leaves.[47]

The cladding system is designed to withstand Dubai's extreme summer temperatures, and consists of 142,000 m2 (1,528,000 sq ft) of reflective glazing, and aluminium and textured stainless steel spandrel panels with vertical tubular fins. Over 26,000 glass panels were used in the exterior cladding of Burj Khalifa, and more than 300 cladding specialists from China were brought in for the cladding work on the tower.[45] The architectural glass provides solar and thermal performance as well as an anti-glare shield for the intense desert sun, extreme desert temperatures and strong winds. In total the glass covers more than 174,000 m2 (1,870,000 sq ft).

The exterior temperature at the top of the building is thought to be 6 °C (11 °F) cooler than at its base.[48]

A 304-room Armani Hotel, the first of four by Armani, occupies 15 of the lower 39 floors.[3][49] The hotel was supposed to open on 18 March 2010,[50][51] but after several delays, it finally opened to the public on 27 April 2010.[52] The corporate suites and offices were also supposed to open from March onwards,[53] yet the hotel and observation deck remained the only parts of the building which were open in April 2010.

The sky lobbies on the 43rd and 76th floors house swimming pools.[54] Floors through to 108 have 900 private residential apartments (which, according to the developer, sold out within eight hours of being on the market). An outdoor zero-entry swimming pool is located on the 76th floor of the tower. Corporate offices and suites fill most of the remaining floors, except for a 122nd, 123rd and 124th floor where the At.mosphere restaurant, sky lobby and an indoor and outdoor observation deck is located respectively. In January 2010, it was planned that Burj Khalifa would receive its first residents from February 2010.[54][55]

A total of 57 elevators and 8 escalators are installed.[45] The elevators have a capacity of 12 to 14 people per cabin, the fastest rising and descending at up to 10 m/s (33 ft/s) for double-deck elevators. However, the world's fastest single-deck elevator still belongs to Taipei 101 at 16.83 m/s (55.2 ft/s). Engineers had considered installing the world's first triple-deck elevators, but the final design calls for double-deck elevators.[22] The double-deck elevators are equipped with entertainment features such as LCD displays to serve visitors during their travel to the observation deck.[56] The building has 2,909 stairs from the ground floor to the 160th floor.[57]

The graphic design identity work for Burj Khalifa is the responsibility of Brash Brands, who are based in Dubai. Design of the global launch events, communications, and visitors centers[58] for Burj Khalifa have also been created by Brash Brands as well as the roadshow exhibition for the Armani Residences, which are part of the Armani Hotel within Burj Khalifa, which toured Milan, London, Jeddah, Moscow and Delhi.[59]

Plumbing systems

The Burj Khalifa's water system supplies an average of 946,000 L (250,000 US gal) of water per day through 100 km (62 mi) of pipes.[19][60] An additional 213 km (132 mi) of piping serves the fire emergency system, and 34 km (21 mi) supplies chilled water for the air conditioning system.[60] The waste water system uses gravity to discharge water from plumbing fixtures, floor drains, mechanical equipment and storm water, to the city municipal sewer.[61]

Air conditioning

The air conditioning system draws air from the upper floors where the air is cooler and cleaner than on the ground.[62] At peak cooling times, the tower's cooling is equivalent to that provided by 13,000 short tons (26,000,000 lb) of melting ice in one day,[60] or about 46 MW. The condensate collection system, which uses the hot and humid outside air, combined with the cooling requirements of the building, results in a significant amount of condensation of moisture from the air. The condensed water is collected and drained into a holding tank located in the basement car park; this water is then pumped into the site irrigation system for use on the Burj Khalifa park.[19]

Window cleaning

To wash the 24,348 windows, totaling 120,000 m2 (1,290,000 sq ft) of glass, a horizontal track has been installed on the exterior of Burj Khalifa at levels 40, 73, and 109. Each track holds a 1,500 kg (3,300 lb) bucket machine which moves horizontally and then vertically using heavy cables. Above level 109, up to tier 27 traditional cradles from davits are used. The top of the spire, however, is reserved for specialist window cleaners, who brave the heights and high winds, dangling on ropes to clean and inspect the top of the pinnacle.[63][64] Under normal conditions, when all building maintenance units will be operational, it will take 36 workers three to four months to clean the entire exterior façade.[45][65]

Unmanned machines will clean the top 27 additional tiers and the glass spire. The cleaning system was developed in Melbourne, Australia at a cost of A$8 million.[65] The contract for building the state-of-the-art machines was won by Australian company Cox Gomyl.[66]

Features

The Dubai Fountain

Main article: The Dubai Fountain

Outside, WET Enterprises designed a fountain system at a cost of Dh 800 million (US$217 million). Illuminated by 6,600 lights and 50 coloured projectors, it is 275 m (902 ft) long and shoots water 150 m (490 ft) into the air, accompanied by a range of classical to contemporary Arabic and world music.[67] On 26 October 2008, Emaar announced that based on results of a naming contest the fountain would be called the Dubai Fountain.[68]

View of Dubai Marina from the observation deck

Observation deck

View of The Dubai Fountain from the observation deck
View from the observation deck

An outdoor observation deck, named At the Top, opened on 5 January 2010 on the 124th floor. At 452 m (1,483 ft), it was the highest observation deck in the world and the highest outdoor observation deck in the world when it opened.[69] Although it was surpassed in December 2011 by Cloud Top 488 on the Canton Tower at 488 m (1,601 ft),[70] Burj Khalifa opened the 148th floor SKY level at 555 m (1,821 ft), once again giving it the highest observation deck in the world on 15 October 2014.[23][24] The 124th floor observation deck also features the Tellscope electronic telescope, an augmented reality device developed by gsmprjct° of Montréal, which allows visitors to view the surrounding landscape in real-time, and to view previously saved images such as those taken at different times of day or under different weather conditions.[71][72][73] To manage the daily rush of sightseers, visitors are able to purchase tickets in advance for a specific date and time and at a 75% discount over tickets purchased on the spot.[74]

On 8 February 2010, the observation deck was closed to the public after power-supply problems caused an elevator to become stuck between floors, trapping a group of tourists for 45 minutes.[75][76] Despite rumours of the observation deck reopening for St. Valentine's Day (14 February),[77] it remained closed until 4 April 2010.[78][79][80]

Burj Khalifa park

Burj Khalifa is surrounded by an 11 ha (27-acre) park designed by landscape architects SWA Group.[81] The design of the park is also inspired by the core design concepts of Burj Khalifa which is based on the symmetries of the desert flower, Hymenocallis.[82] The park has six water features, gardens, palm lined walkways, and flowering trees.[83] At the centre of the park and the base of Burj Khalifa is the water room, which is a series of pools and water jet fountains. In addition the railing, benches and signs incorporate images of Burj Khalifa and the Hymenocallis flower.

The plants and the shrubbery will be watered by the buildings's condensation collection system that uses water from the cooling system. The system will provide 68,000,000 L (15,000,000 imp gal) annually.[83] WET Enterprises, who also developed the Dubai Fountain, developed the park's six water features.[84]

Floor plans

The following is a breakdown of floors.[45][85]

Floors Use

Dimetric projection with floors colour-coded by function[86]

164–209 Spire
160–163 Mechanical
156–159 Communication and broadcast
155 Mechanical
149–154 Corporate suites
148 The New Deck observatory
139–147 Corporate suites
136–138 Mechanical
125–135 Corporate suites
124 At the Top observatory
123 Sky lobby
122 At.mosphere restaurant
111–121 Corporate suites
109–110 Mechanical
77–108 Residential
76 Sky lobby
73–75 Mechanical
44–72 Residential
43 Sky lobby
40–42 Mechanical
38–39 Armani Hotel suites
19–37 Residential
17–18 Mechanical
9–16 Armani Residences
1–8 Armani Hotel
Ground Armani Hotel
Concourse Armani Hotel
B1–B2 Parking, mechanical

Construction

thumbtime=0:23
Aerial closeup of Burj Khalifa under construction in March 2008

The tower was constructed by Samsung Engineering & Construction of South Korea, which also did work on the Petronas Twin Towers and Taipei 101.[87] Samsung Engineering & Construction built the tower in a joint venture with Besix from Belgium and Arabtec from UAE. Turner is the Project Manager on the main construction contract.[88]

Under UAE law, the Contractor and the Engineer of Record, Hyder Consulting, is jointly and severally liable for the performance of Burj Khalifa.

The primary structure is reinforced concrete. Putzmeister created a new, super high-pressure trailer concrete pump, the BSA 14000 SHP-D, for this project.[21] Over 45,000 m3 (58,900 cu yd) of concrete, weighing more than 110,000 tonnes (120,000 short tons; 110,000 long tons) were used to construct the concrete and steel foundation, which features 192 piles; each pile is 1.5 metre diameter x 43 m long, buried more than 50 m (164 ft) deep.[22] Burj Khalifa's construction used 330,000 m3 (431,600 cu yd) of concrete and 55,000 tonnes (61,000 short tons; 54,000 long tons) of steel rebar, and construction took 22 million man-hours.[10] A high density, low permeability concrete was used in the foundations of Burj Khalifa. A cathodic protection system under the mat is used to minimize any detrimental effects from corrosive chemicals in local ground water.[45] In May 2008 Putzmeister pumped concrete to a then world record delivery height of 606 m (1,988 ft),[21] the 156th floor. Three tower cranes were used during construction of the uppermost levels, each capable of lifting a 25-tonne load.[89] The remaining structure above is constructed of lighter steel.

Burj Khalifa is highly compartmentalised. Pressurized, air-conditioned refuge floors are located approximately every 35 floors where people can shelter on their long walk down to safety in case of an emergency or fire.[45][90]

Special mixes of concrete are made to withstand the extreme pressures of the massive building weight; as is typical with reinforced concrete construction, each batch of concrete used was tested to ensure it could withstand certain pressures. CTLGroup, working for SOM, conducted the creep and shrinkage testing critical for the structural analysis of the building.[91]

The consistency of the concrete used in the project was essential. It was difficult to create a concrete that could withstand both the thousands of tonnes bearing down on it and Persian Gulf temperatures that can reach 50 °C (122 °F). To combat this problem, the concrete was not poured during the day. Instead, during the summer months ice was added to the mixture and it was poured at night when the air is cooler and the humidity is higher. A cooler concrete mixture cures evenly throughout and is therefore less likely to set too quickly and crack. Any significant cracks could have put the entire project in jeopardy.

The unique design and engineering challenges of building Burj Khalifa have been featured in a number of television documentaries, including the Big, Bigger, Biggest series on the National Geographic and Five channels, and the Mega Builders series on the Discovery Channel.

The biggest share of the on-site concrete works is dedicated to the slabs totalling 224,808 m² (532 slabs on 154 floor levels) MEVA supplies a complete formwork solution with its slab formwork system MevaDec. A total of only 3,000 m² of MevaDec slab formwork are required to supply the entire construction process. The slabs are poured at 6 pm formwork is stripped at noon the following day.[92]

Milestones

Burj Khalifa and skyline of Dubai, 2010

Real estate values

In March 2009, Mohamed Ali Alabbar, chairman of the project's developer, Emaar Properties, said office space pricing at Burj Khalifa reached US$4,000 per sq ft (over US$43,000 per m²) and the Armani Residences, also in Burj Khalifa, sold for US$3,500 per sq ft (over US$37,500 per m²).[102] He estimated the total cost for the project to be about US$1.5 billion.[2]

The project's completion coincided with the global financial crisis of 2007–2012, and with vast overbuilding in the country; this led to high vacancies and foreclosures.[43] With Dubai mired in debt from its huge ambitions, the government was forced to seek multibillion dollar bailouts from its oil-rich neighbor Abu Dhabi. Subsequently, in a surprise move at its opening ceremony, the tower was renamed Burj Khalifa, said to honour the UAE President Khalifa bin Zayed Al Nahyan for his crucial support.[8][103]

Because of the slumping demand in Dubai's property market, the rents in the Burj Khalifa plummeted 40% some ten months after its opening. Out of 900 apartments in the tower, 825 were still empty at that time.[104][105] However, over the next two and a half years, overseas investors steadily began to purchase the available apartments and office space in Burj Khalifa.[106] By October 2012, Emaar reported that around 80% of the apartments were occupied.[107]

Official launch ceremony

The opening ceremony of Burj Khalifa

The opening of Burj Khalifa was held on 4 January 2010.[108] The ceremony featured a display of 10,000 fireworks, light beams projected on and around the tower, and further sound, light and water effects.[109] The celebratory lighting was designed by UK lighting designers Speirs and Major.[110] Using the 868 powerful stroboscope lights that are integrated into the façade and spire of the tower, different lighting sequences were choreographed, together with more than 50 different combinations of the other effects.

The event began with a short film which depicted the story of Dubai and the evolution of Burj Khalifa. The displays of sound, light, water and fireworks followed.[109] The portion of the show consisting of the various pyrotechnic, lighting, water and sound effects was divided into three. The first part was primarily a light and sound show, which took as its theme the link between desert flowers and the new tower, and was co-ordinated with the Dubai Fountain and pyrotechnics. The second portion, called 'Heart Beat', represented the construction of the tower in a dynamic light show with the help of 300 projectors which generated a shadow-like image of the tower. In the third act, sky tracers and space cannons enveloped the tower in a halo of white light, which expanded as the lighting rig on the spire activated.[109]

The ceremony was relayed live on a giant screen on Burj Park Island, as well as several television screens placed across the Downtown Dubai development. Hundreds of media outlets from around the world reported live from the scene.[109] In addition to the media presence, 6,000 guests were expected.[111]

Reception

Awards

In June 2010, Burj Khalifa was the recipient of the 2010 "Best Tall Building Middle East & Africa" award by the CTBUH.[112] On 28 September 2010 Burj Khalifa won the award for best project of year at the Middle East Architect Awards 2010.[113]

A new award was bestowed on the Burj Khalifa by the CTBUH at its annual "Best Tall Buildings Awards Ceremony" on 25 October 2010 when the building was honored as first recipient of CTBUH’s new Tall Building "Global Icon" Award. According to the CTBUH the new "Global Icon" award recognizes those very special supertall skyscrapers that make a profound impact, not only on the local or regional context, but on the genre of tall buildings globally. Which is innovative in planning, design and execution, the building must have influenced and reshaped the field of tall building architecture, engineering, and urban planning. It is intended that the award will only be conferred on an occasional basis, when merited by an exceptional project perhaps every ten or fifteen years.[114]

CTBUH Awards Chair Gordon Gill, of Adrian Smith + Gordon Gill Architecture said:

"There was discussion amongst members of the jury that the existing ‘Best Tall Building of the Year’ award was not really appropriate for the Burj Khalifa. We are talking about a building here that has changed the landscape of what is possible in architecture a building that became internationally recognized as an icon long before it was even completed. ‘Building of the Century’ was thought a more appropriate title for it."[114]

Beside these awards, Burj Khalifa was the recipient of following awards.[115][116]

BASE jumping

The building has been used by several experienced BASE jumpers for both authorized and unauthorized BASE jumping:

Climbing

On 28 March 2011, Alain "Spiderman" Robert scaled the outside of Burj Khalifa. The climb to the top of the spire took six hours. To comply with UAE safety laws, Robert, who usually climbs in free solo style, used a rope and harness for the climb.[124]

Suicide

Within 17 months of the building's official opening, a man described as "an Asian in his mid-30s" who worked at one of the companies in the tower, committed suicide on 10 May 2011 by jumping from the 147th floor. He fell 39 floors, landing on a deck on the 108th floor. Dubai police confirmed the act as a suicide, reporting that "We also came to know that the man decided to commit suicide as his company refused to grant leave."[125] On 16 November 2014. Laura Vanessa Nunes, a Portuguese National who was in Dubai on a tourist visa, fell to her death from Burj Khalifa's At the Top Sky Observation Deck on the 148th floor. After the tragedy, police requested the Burj Khalifa make the gaps between the glass panes smaller, which they did..[126]

In popular culture

Fireworks displays

Labor controversy

Burj Khalifa was built primarily by workers from South Asia and East Asia.[138][139] This is generally because the current generation of UAE locals prefer government jobs and consider private sector jobs to be below them. Also, because of the benefits available from the UAE government, most locals would rather rely on these benefits and not go to work.[140] On 17 June 2008, there were 7,500 skilled workers employed at the construction site.[34] Press reports indicated in 2006 that skilled carpenters at the site earned £4.34 a day, and labourers earned £2.84.[138] According to a BBC investigation and a Human Rights Watch report, the workers were housed in abysmal conditions, and worked long hours for low pay.[141][142][143] During the construction of Burj Khalifa, only one construction-related death was reported.[144] However, workplace injuries and fatalities in the UAE are "poorly documented".[141]

On 21 March 2006, about 2,500 workers, who were upset over buses that were delayed for the end of their shifts, protested, damaged cars, offices, computers, and construction equipment.[138] A Dubai Interior Ministry official said the rioters caused almost £500,000 in damage.[138] Most of the workers involved in the riot returned the following day but refused to work.[138]

Gallery

Construction

1 February 2006
 
29 August 2006
 
19 November 2006
 
21 March 2007
 
9 May 2007
 
15 July 2007
 
2 December 2007
 
4 December 2007
 
10 December 2007
 
11 March 2008
 
8 May 2008
 
8 May 2008
 

Photos

Aerial view of Downtown Dubai from Burj Khalifa
 
Burj Khalifa Name Plate
 
View of Downtown Dubai from Old Town Hotels and Restaurants with Burj Khalifa visible on the right
 
Night view of Downtown Dubai from Old Town Hotels and Restaurant with Burj Khalifa visible on the right
 
Burj Khalifa as seen from the Dubai Metro station
 
Dubai Skyline with Burj Khalifa 

See also

References

  1. 1.0 1.1 1.2 "Official Opening of Iconic Burj Dubai Announced". Gulfnews. 4 November 2009. Retrieved 4 November 2009.
  2. 2.0 2.1 Stanglin, Douglas (2 January 2010). "Dubai opens world's tallest building". Dubai: USA Today. Retrieved 4 January 2010.
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 "Burj Khalifa - The Skyscraper Center". Council on Tall Buildings and Urban Habitat.
  4. Baldwin, Derek (1 May 2008). "No more habitable floors to Burj Dubai". Gulfnews. Retrieved 7 January 2010.
  5. "The Burj Khalifa". Glass, Steel and Stone. Retrieved 8 January 2010.
  6. Blum, Andrew (27 November 2007). "Engineer Bill Baker Is the King of Superstable 150-Story Structures". Wired. Retrieved 11 March 2008.
  7. 7.0 7.1 7.2 7.3 "Burj Dubai (Dubai Tower) and Dubai Mall, United Arab Emirates". designbuild-network.com. Retrieved 23 March 2009.
  8. 8.0 8.1 8.2 Bianchi, Stefania; Andrew Critchlow (4 January 2010). "World's Tallest Skyscraper Opens in Dubai". Dow Jones & Company, Inc. Retrieved 4 January 2010.
  9. 9.0 9.1 "World's tallest building opens in Dubai". BBC News. 4 January 2010. Retrieved 4 January 2010.
  10. 10.0 10.1 "Burj Dubai reaches a record high". Emaar Properties. 21 July 2007. Retrieved 24 November 2008.
  11. Keegan, Edward (15 October 2006). "Adrian Smith Leaves SOM, Longtime Skidmore partner bucks retirement to start new firm". ArchitectOnline. Retrieved 23 March 2009.
  12. "Burj Dubai, Dubai – SkyscraperPage.com". SkyscraperPage. Retrieved 23 March 2009.
  13. http://www.al-ghurair.com/en/its-about-commitment/building-the-burj-khalifa/
  14. http://www.ctbuh.org/SponsorExhibit/ConferenceSponsors/PlatinumSponsorship/PlatinumSponsorAlGhurair/tabid/3881/language/en-US/Default.aspx
  15. Stack, Megan (13 October 2005). "In Dubai, the Sky's No Limit". Los Angeles Times. Retrieved 26 March 2006.
  16. "WTC Timeline". Silverstein Properties. Retrieved 28 March 2013.
  17. 17.0 17.1 "the world's vainest skyscrapers".
  18. "Burj Khalifa". Construcitonweekonline.com. Retrieved 3 August 2010.
  19. 19.0 19.1 19.2 19.3 19.4 19.5 19.6 "Burj Khalifa: Towering challenge for builders". GulfNews.com. 4 January 2010. Retrieved 10 February 2010.
  20. "Burj Khalifa". Otis Elevator. Retrieved 15 April 2013.
  21. 21.0 21.1 21.2 Burj Khalifa -- Conquering the World's Tallest Building
  22. 22.0 22.1 22.2 "Burj Dubai, Dubai, at Emporis.com". Emporis. Retrieved 1 March 2007.
  23. 23.0 23.1 Willett, Megan (17 October 2014). "Dubai's Burj Khalifa Now Has The Highest Observation Deck In The World At 1,821 Feet, And It Looks Incredible". businessinsider.com. Business Insider. Retrieved 6 December 2014.
  24. 24.0 24.1 "At the Top, Burj Khalifa Experience". burjkhalifa.ae. Burj Khalifa. Retrieved 6 December 2014.
  25. 25.0 25.1 25.2 25.3 25.4 25.5 25.6 25.7 25.8 "Burj Dubai Construction Timeline". BurjDubai.com. Retrieved 31 December 2009.
  26. "World highest nightclub in Burj Khalifa". BurjDubai.com. Retrieved 20 November 2010.
  27. "And the world’s highest restaurant is ready to serve". Emirates 24/7. Retrieved 29 May 2011.
  28. "Foodie Gossip: At.mosphere Bar & Grill opens in Dubai". Foodiegossip.blogspot.com. 23 January 2011. Retrieved 29 May 2011.
  29. 29.0 29.1 "Jaw-dropping Fireworks at Burj Khalifa Enthrall Thousands". Gulfnews.com. 31 December 2010. Retrieved 29 May 2011.
  30. Landon Thomas Jr (5 January 2010). "Dubai's skyscraper has world's highest Mosque". Retrieved 5 January 2010.
  31. Robinson, Paul (27 February 2003). "Grollo tower to go ahead, in Dubai". Melbourne, Australia: The Age. Retrieved 6 January 2010.
  32. 32.0 32.1 "Architect reveals Burj Dubai height". Arabian Business. 3 December 2008. Retrieved 3 December 2008.
  33. Cityscape Daily News PDF (264 KB) Cityscape, 18 September 2005. Retrieved on 5 May 2006.
  34. 34.0 34.1 34.2 "Emaar increases height of Burj Dubai; completion in September 2009". Emaar Properties. 17 June 2008. Retrieved 17 October 2008.
  35. Das Augustine, Babu (9 June 2008). "Burj Dubai completion delayed by another eight to nine months". Gulf News. Retrieved 21 June 2008.
  36. "Burj Dubai opening date announced". Homes Overseas. 31 July 2009. Retrieved 1 August 2009.
  37. 37.0 37.1 "Top 10 world's tallest steel buildings". Constructionweekonline.com. Retrieved 14 June 2013.
  38. "Burj Khalifa". AllAboutSkyscrapers.com. 19 November 2012. Retrieved 14 June 2013.
  39. Bayley, Stephen (5 January 2010). "Burj Dubai: The new pinnacle of vanity". Telegraph (London).
  40. 40.0 40.1 "Burj Dubai becomes tallest manmade structure". Hyder Consulting. Retrieved 10 January 2010.
  41. "Hyder reinforces its reputation for unrivaled engineering ability with the opening of the Burj Khalifa – the world's tallest building". Hyder Consulting. Retrieved 10 January 2010.
  42. "GHD is playing a vital role in managing the long term structural integrity of the world’s tallest building, the Burj Dubai Tower.". GHD. Retrieved 11 April 2009.
  43. 43.0 43.1 Christopher Hawthorne (1 January 2010). "The Burj Dubai and architecture's vacant stare". Los Angeles Times. Retrieved 4 January 2010.
  44. Saberi, Mahmood (19 April 2008). "Burj Dubai is the height of success". Gulf News. Retrieved 31 December 2009.
  45. 45.0 45.1 45.2 45.3 45.4 45.5 45.6 "Structural Elements – Elevator, Spire, and More". BurjDubai.com. Retrieved 31 December 2009.
  46. "Skidmore, Owings & Merrill Leads Process for Art Program at Burj Dubai". 28 May 2009.
  47. "Burj Dubai will officially open for the UAE National Day". Dubai Chronicle. 29 July 2009. Retrieved 9 January 2010.
  48. "Temperature and Elevation". United States Department of Energy. 21 May 2002. Retrieved 11 April 2009.
  49. "Armani Hotel Burj Dubai, United Arab Emirates". hotelmanagement-network.com. Retrieved 11 April 2009.
  50. "Worlds first Armani Hotel to open on 18 March 2010 in Dubai". EyeOfDubai.com. 4 January 2010. Retrieved 8 January 2010.
  51. Sambidge, Andy (4 January 2010). "Burj Dubai's Armani hotel to open on Mar 18". Arabian Business. Retrieved 8 January 2010.
  52. "Armani hotel opens in Dubai's Khalifa tower". The Jerusalem Post. 27 April 2010. Retrieved 27 April 2010.
  53. "Burj Dubai: Fact Sheet". Eyeofdubai.com. Retrieved 11 May 2010.
  54. 54.0 54.1 "Burj Dubai to welcome residents in Feb 2010". Business Standard. 1 January 2010. Retrieved 9 January 2010.
  55. "Burj Dubai To Welcome First Residents From February 2010 Onwards". DubaiCityGuide. 31 December 2009. Retrieved 9 January 2010.
  56. CW Staff. "How the Burj was built". ConstructionWeekOnline.com. Retrieved 11 May 2010.
  57. "Top 10 Burj Khalifa facts: Part 3". ConstructionWeekOnline.com. Retrieved 8 January 2010.
  58. "Burj Dubai Design work at Brash Brands". brashbrands.com. Retrieved 11 June 2009.
  59. "Burj Dubai Armani Residences Roadshow Brands". ida.us. Retrieved 11 June 2009.
  60. 60.0 60.1 60.2 "Escaping the Dubai Downturn: Voltas’s Latest Engineering Feat". Wharton, University of Pennsylvania. 20 April 2010. Retrieved 21 May 2011.
  61. Frechette, Leung & Boyer (24–26 July 2006). Mechanical and Electrical Systems for the Tallest Building/Man-Made Structure in the World: A Burj Dubai Case Study (PDF). Fifteenth Symposium on Improving Building Systems in Hot and Humid Climates. Orlando, Florida. p. 7. Retrieved 15 July 2013.
  62. "Air Conditioning in Burj Khalifa". Timeoutdubai.com. Retrieved 17 April 2011.
  63. "A tall order: Burj Dubai all set to come clean". Gulf News. 25 August 2009. Retrieved 7 December 2009.
  64. Window cleaning the world's tallest building on YouTube from Supersized Earth - Episode 1 - BBC One
  65. 65.0 65.1 Dobbin, Marika (5 January 2010). "So you think your windows are hard to keep clean?". Melbourne, Australia: The Age. Retrieved 6 January 2010.
  66. Malkin, Bonnie (5 January 2010). "Burj Khalifa: window cleaners to spend months on world's tallest building". London: The Daily Telegraph. Retrieved 15 August 2011.
  67. "Emaar brings world class water, light, and music spectacle to Burj Dubai Lake". Emaar Properties. 9 June 2008. Retrieved 13 June 2008.
  68. "'Dubai Fountain' is winning name of Emaar's water spectacle in Downtown Burj Dubai". Emaar Properties. 26 October 2008. Retrieved 26 October 2008.
  69. "Burj Dubai Observation Deck Opens to The Public On Jan 5". Bayut.com. 4 January 2010. Retrieved 6 January 2010.
  70. "Cloud Top 488 on Canton Tower Opened to public". The People`s Government of Guangzhou Municipality. 19 December 2011. Retrieved 23 January 2012.
  71. "Augmented Reality – gsmprjct°". gsmprjct°. Retrieved 6 December 2014.
  72. "At the Top, Burj Khalifa". gsmprjct°. Retrieved 6 December 2014.
  73. "Une firme québécoise dans la plus haute tour du monde". Journal de Montréal (in French). 4 January 2010. Retrieved 19 August 2010.
  74. "'At The Top' Observation Deck Ticket Information". Emaar Properties. Retrieved 9 February 2010.
  75. "Emaar Says Burj Khalifa Observation Deck Closed for Maintenance". Bloomberg. 8 February 2010. Retrieved 9 February 2010.
  76. Tomlinson, Hugh (10 February 2010). "Terrifying lift ordeal at Burj Khalifa tower, the world’s tallest building". UK: The Times. Retrieved 10 February 2010. (subscription required (help)).
  77. "Burj Khalifa to Reopen Feb. 14". Bloomberg BusinessWeek. 10 February 2010. Retrieved 10 February 2010.
  78. "World's tallest building, Burj Khalifa, reopens observation deck". UK: The Guardian. 5 April 2010. Retrieved 6 April 2010.
  79. "Burj Khalifa observation deck reopens". GulfNews.com. 5 April 2010. Retrieved 6 April 2010.
  80. Rackl, Lori (5 April 2010). "Machu Picchu and Burj Khalifa back in biz". Chicago Sun-Times. Retrieved 5 April 2010.
  81. "An 11-hectare green oasis envelops the foot of Burj Dubai". Emaar Properties. 20 December 2009. Retrieved 20 March 2010.
  82. "An 11-hectare green oasis envelops the foot of Burj Dubai". BurjDubai.com. 20 December 2009. Retrieved 10 January 2010.
  83. 83.0 83.1 Baxter, Elsa (20 December 2009). "11-hectare park unveiled at Burj Dubai site". Arabian Business. Retrieved 10 January 2010.
  84. "An 11-hectare green oasis envelops the foot of Burj Dubai". Emaar Properties. 20 December 2009. Retrieved 10 January 2010.
  85. "Inside the Burj Dubai". Maktoob News. 28 December 2009. Retrieved 10 January 2010.
  86. SOM rendering
  87. "Samsung E&C Projects". Samsung Engineering & Construction. Retrieved 23 March 2009.
  88. "Turner International Projects – Burj Dubai". Turner Construction. Retrieved 23 March 2009.
  89. Croucher, Martin (11 November 2009). "Myth of ‘Babu Sassi’ Remains After Burj Cranes Come Down". Khaleej Times. Retrieved 3 June 2011.
  90. Puckett, Katie (3 October 2008). "Burj Dubai: Top of the world". Building. Retrieved 31 December 2009.
  91. "Clients & Projects – Burj Khalifa, the Tallest Building in the World". CTLGroup. Retrieved 29 May 2011.
  92. "Burj Khalifa“ – highest building ever".
  93. "Dubai skyscraper world's tallest". BBC News. 22 July 2007. Retrieved 31 December 2009.
  94. "Burj Dubai: Unimix sets record for concrete pumping". Dubai News Online. 25 May 2007. Retrieved 11 April 2009.
  95. "Burj Dubai Official Website". Emaar Properties. Retrieved 8 March 2008.
  96. "CN Tower dethroned by Dubai building". Canadian Broadcasting Corporation. 12 September 2007. Retrieved 13 September 2007.
  97. "Burj Dubai surpasses KVLY-TV mast to become the world's tallest man-made structure". Emaar Properties. 7 April 2008. Retrieved 7 April 2008.
  98. "Burj Dubai now a record 688m tall and continues to rise". Emaar Properties. 1 September 2008. Retrieved 1 September 2008.
  99. "Burj Dubai all set for 09/09/09 soft opening". Emirates Business 24-7. Retrieved 17 January 2009.
  100. "Burj Dubai exterior done, to open this year". Maktoob News. 1 October 2009. Retrieved 1 October 2009.
  101. "Tallest Trends and the Burj Khalifa". Council on Tall Buildings and Urban Habitat. 10 March 2010.
  102. "Burj Dubai offices to top US$4,000 per sq ft". Zawya. 5 March 2008. Retrieved 23 March 2009.
  103. "828-metre Burj Dubai renamed Burj Khalifa". Maktoob Group. 4 January 2010. Retrieved 10 February 2010.
  104. Reagan, Brad (14 October 2010). "Burj Khalifa rents tumble 40%". The National. Retrieved 6 November 2010.
  105. McGinley, Shane (21 October 2010). "Armani Residences defy 70% Burj Khalifa price drop". Arabian Business. Retrieved 6 November 2010.
  106. "Offices stand empty in tallest tower, the Burj Khalifa". BBC. 21 July 2012. Retrieved 28 March 2013.
  107. "Emaar Reports 80% Occupancy Levels In Burj Khalifa". REIDIN.com. Retrieved 1 October 2012.
  108. Huang, Carol (5 January 2010). "World's tallest building: What's it worth to have the Dubai tower – and what should people call it?". The Christian Science Monitor. Retrieved 6 January 2010.
  109. 109.0 109.1 109.2 109.3 Sambidge, Andy (3 January 2010). "Burj Dubai ceremony details revealed". Arabian Business. Retrieved 5 January 2010.
  110. Devine, Rachel (21 February 2010). "Designer's light touches far and wide". UK: The Times. Retrieved 29 November 2010.
  111. "Two billion to watch Burj Dubai opening". Maktoob Business. 3 January 2010. Retrieved 5 January 2010.
  112. "CTBUH 9th Annual Awards, 2010". Council on Tall Buildings and Urban Habitat. Retrieved 5 June 2007.
  113. "Burj Khalifa won Best Project of Year at Middle East Architect Awards 2010". Constructionweekonline.com. Retrieved 30 September 2010.
  114. 114.0 114.1 "Burj Khalifa won "Global Icon" Award". Council on Tall Buildings And Urban Habitate. Retrieved 2 November 2010.
  115. "Burj Khalifa Project Awards". Skidmore, Owings & Merril LLP (SOM). Retrieved 24 February 2013.
  116. "Jmhdezhdez.com". Burj Khalifa Project Awards. Retrieved 24 February 2013.
  117. Bednarz, Jan; Schmidt, Robin; Harvey, Andy; Le Gallou, Hervé (2008). "World record BASE jump". Current TV. Retrieved 4 January 2010. Video documentary about the BASE jump from the Burj Dubai tower.
  118. Tom Spender (24 November 2008). "Daredevils jumped off Burj Dubai undetected". The National. Retrieved 4 January 2010.
  119. Highest base jump-Nasr Al Niyadi and Omar Al Hegelan sets world record. Retrieved 9 January 2010.
  120. Mansfield, Roddy (8 January 2010). "Daredevils Jump Off World's Tallest Building". Sky News. Retrieved 8 January 2010.
  121. "Highest BASE jump from a building". Guinness World Records Limited. Retrieved 26 April 2014.
  122. "Fred Fugen and Vincent Reffet took BASE jumping higher than ever before in Dubai.". Red Bull. Retrieved 26 April 2014.
  123. Burj Khalifa Pinnacle BASE Jump - 4K. YouTube. 24 April 2014. Retrieved 22 August 2014.
  124. "'Spiderman' Alain Robert scales Burj Khalifa in Dubai". BBC. 28 March 2011. Retrieved 29 March 2011.
  125. "Man dies in jump from world's tallest building". News.blogs.cnn.com. 12 May 2011. Retrieved 29 May 2011.
  126. Lieutenant Colonel Tariq Mohd of Bur Dubai Police Station
  127. "All about dangling Tom Cruise 1,700 feet over Dubai for 'Mission: Impossible - Ghost Protocol'". www.nydailynews.com. 11 December 2011. Retrieved 29 September 2012.
  128. Ellis, Dominic. "Dubai Sets Two World Records For National Day Including Tallest Chocolate Structure", Gulf Business, Dubai, 30 November 2014. Retrieved on 30 November 2014.
  129. "Burj Khalifa to Ring in 2011". Uaeinteract.com. Retrieved 29 May 2011.
  130. "Burj Khalifa Fireworks 2012". Constructionweekonline.com. Retrieved 24 February 2013.
  131. "New Year fireworks illuminate world’s tallest building, Dubai's Burj Khalifa 2013". Alarabiya.net. Retrieved 24 February 2013.
  132. "Burj Khalifa fireworks after winning Expo 2020". Arabia.msn.com. Retrieved 1 December 2013.
  133. "Dubai sees in New Year with largest fireworks display world record". Guinness World Records. 1 January 2014. Retrieved 2 January 2014.
  134. "Dubai ushers in New Year with fireworks world record 2020". Gulfnews.com. Retrieved 1 January 2013.
  135. "led facade report emmar".
  136. "2015 fireworks".
  137. "LED illumination".
  138. 138.0 138.1 138.2 138.3 138.4 Whitaker, Brian (23 March 2006). "Riot by migrant workers halts construction of Dubai skyscraper". UK: The Guardian. Retrieved 25 March 2006.
  139. "Burj Dubai opens tomorrow, final height still a secret!". India: The Hindu. 3 January 2010. Retrieved 6 January 2010.
  140. Emiratisation won't work if people don't want to learn The National
  141. 141.0 141.1 "Building Towers, Cheating Workers Section V.". Human Rights Watch. 11 November 2006. Retrieved 26 July 2010.
  142. "Dark side of the Dubai dream". BBC. 6 April 2009. Retrieved 15 July 2013.
  143. "Behind the Glamorous Facade of the Burj Khalifa". Migrant-Rights.org. 4 January 2010. Retrieved 6 January 2010.
  144. "Keeping the Burj Dubai site safe for workers". gulfnews. 4 January 2010. Retrieved 29 May 2011.

External links

Wikimedia Commons has media related to:
Records
Preceded by
Warsaw Radio Mast
646.38 m (2,120.67 ft)
World's tallest structure ever built
2008 – present
Incumbent
Preceded by
KVLY-TV mast
628.8 m (2,063 ft)
World's tallest structure
2008 – present
Preceded by
CN Tower
553.33 m (1,815.39 ft)
World's tallest free-standing structure
2007 – present
Preceded by
Taipei 101
509.2 m (1,670.6 ft)
World's tallest building
2010 – present
Preceded by
Willis Tower
108 floors
Building with the most floors
2007 – present