Broadlands Dam

Broadlands Dam
Location of Broadlands Dam
Country Sri Lanka
Location Kitulgala
Coordinates 06°58′43″N 80°27′16″E / 6.97861°N 80.45444°ECoordinates: 06°58′43″N 80°27′16″E / 6.97861°N 80.45444°E
Purpose Power
Status Under construction
Construction began 17 July 2013
Opening date Early 2017
Construction cost US$82 million
Dam and spillways
Type of dam Gravity dam
Impounds Maskeliya Oya
Height (thalweg) 24 m (79 ft)
Length 114 m (374 ft)
Reservoir
Total capacity 198,000 m3 (7,000,000 cu ft)
Catchment area 201 km2 (78 sq mi)
Normal elevation 122 m (400 ft)
Power station
Operator(s) CEB
Turbines 2 x 17.5 MW
Installed capacity 35 MW
Annual generation 126 GWh
Website
http://www.bhpceb.lk/

The Broadlands Dam (also known as the Broadlands Hydropower Project by the developers) is a 35 MW run-of-the-river hydroelectric complex currently under construction in Kitulgala, Sri Lanka. The project is expected to be completed in late 2017, and will consist of two dams, and a power station further downstream.[1][2]

With an estimated annual generation capacity of 126 GWh, the facility will be the country's last major hydroelectric project, due to the exhaustion of island-wide hydropower potential. Construction of the project was ceremonially inaugurated by the Minister of Power and Energy Mrs. Pavithra Wanniarachchi at the auspicious time of 11:01 on 17 July 2013.[3][4]

Approximately 85% of the US$82 million project funding was met via credit arrangements made with the Chinese government, with the rest borne via a loan from the local Hatton National Bank.[5][6][7] The construction contract of the project was granted to the China National Electric Equipment Corporation (CNEEC).[8]

Dams and reservoirs

The primary gravity dam measuring 24 m (79 ft) in height and 114 m (374 ft) in length is being constructed across the Maskeliya Oya at Kitulgala, and will supply water to the power station via a 3,404.7 m (11,170.3 ft) penstock measuring 5.4 m (17.7 ft) in diameter.[9]

A secondary gravity weir measuring 19 m (62 ft) and 48 m (157 ft) in height and length, is also to be built in the vicinity, over the nearby Kehelgamu Oya, to provide additional hydroelectric capacity. The weir, to be called the Kehelgamu Weir, will create a catchment area of 176 km2 (68 sq mi), and will provide additional head to the penstock of the main dam via a 811 m (2,661 ft) tunnel.[9]

The penstock from the main dam will feed a power station consisting of two 3-phase synchronous turbines, each of 17.5 MW and a rated discharge of 32 m3 (1,130 cu ft) per second.[9]

See also

References

Wikimedia Commons has media related to Broadlands Hydropower Project.
  1. "Broadlands Hydropower project work begins on Monday". Ceylon Today. 2013-07-14. Retrieved 2 October 2013.
  2. "Broadlands hydro power project construction work inaugurated". Daily News. 2013-07-16. Retrieved 2 October 2013.
  3. "Broadlands hydro power project to be constructed". Sunday Observer. 2013-07-14. Retrieved 2 October 2013.
  4. "Major Projects: Broadlands Hydro Power Project". Ceylon Electricity Board. Retrieved 2 October 2013.
  5. "Construction of Broadlands Hydropower Project in Sri Lanka to start on 14th July". ColomboPage.com. 2013-06-10. Retrieved 2 October 2013.
  6. "Sri Lanka to speed up the construction of ‘Broadland’ hydropower project". LBR.lk. 2013-05-07. Retrieved 2 October 2013.
  7. "HNB finances 15% of mega Broadlands Hydro-Power Project". FT.lk. 2013-06-25. Retrieved 2 October 2013.
  8. "Broadlands 35MW hydro power project to begin in May?". The Island. Retrieved 2 October 2013.
  9. 9.0 9.1 9.2 "About the Broadlands Hydropower Project". BHPCEB.lk. Retrieved 2 October 2013.