Amarube Viaduct

Coordinates: 35°38′58.74″N 134°33′36.36″E / 35.6496500°N 134.5601000°E

A train crossing the new Amarube Viaduct, August 2011

The Amarube Viaduct (余部橋梁 Amarube Kyōryō) is a railway bridge in the town of Kami, Mikata District, Hyōgo Prefecture, on JR West's San'in Main Line between the stations of Yoroi and Amarube.

Background

Work began on the bridge in December 1909, and it opened for service March 1, 1912. It is 310.59 meters in length and 41.45 meters tall. Construction cost a total of 331,535 yen. It had 11 vertical supports and 23 sections of girders. National Route 178 passes beneath it. The structure's unique design and bright color made it popular not only with rail fans but tourists as well. The closest station is Amarube Station, and the mountain behind it provides a popular point from which photographers take pictures of the bridge. From March 6, 2008, the bridge was closed periodically for the construction of its replacement.

Construction

A signboard with statistics and history about the bridge (now moved to a different location)

The terrain along the Sea of Japan coast is very rugged between the towns of Kami and Shin'onsen, and it was necessary to lay the railbed amongst the mountains. However, due to the area's topography, it would also have to cross over villages between mountains. Finally, using large embankments and paths paralleling National Route 178, a route was chosen. Although there was a plan for a concrete structure, it was dismissed as impractical, and an American engineer's opinion was sought. Taking that into consideration, Ministry of Railways engineer Seiichi Furukawa decided that it would be a trestle bridge. The steel for the piers was imported from the American Bridge Company's Pencoyd Iron Works via Kyūshū, and arrived in August 1910. Girders were made by Ishikawajima Shipworks (now IHI Corporation), and were sent from Kōbe in September 1911. Upon completion, its cost exceeded 330,000 yen and more than 250,000 people had worked on the project. Because of the tremendous danger involved with its construction, workers were covered by a 20,000 yen insurance plan.

This bridge was the San'in Main Line's most difficult project after the Tokan Tunnel, one end of which begins at the bridge's east end. Following the structure's completion, it became possible to travel all the way from Kyōto to Izumo. Over 90 years after its completion, it remains Japan's largest railway trestle and has great historical value as an early railway structure.

Accident

Cenotaph under the bridge

On December 28, 1986 around 1:25 pm, an out-of-service Miyabi train traveling from Kasumi Station was caught by strong winds from the Sea of Japan, and all seven passenger cars of the train fell from the bridge, with only a few bogies remaining on the tracks. The locomotive's weight prevented its derailment. The cars fell directly below, landing on a fish-processing plant. Five women working at the plant and the train's conductor died in the accident. Five others in the plant and one food-service worker aboard the train were seriously injured.

This was the first disaster since the opening of the bridge. The accident is attributed to human error. Although the 25 m/s winds activated warning devices, the train proceeded across the bridge.

Following the accident, Japan National Railways reviewed their policies and decided to stop train operations when wind speeds exceeded 20 m/s. Their guidelines for switching to substitute bus service became more stringent. A cenotaph was put in place on November 23, 1988, and on December 28 of each year a Buddhist service is held.

Maintenance

To protect the bridge's piers from the salt air, the structure is repainted every few years. Although the bridge is being replaced, this work was carried out as recently as 2007.

New bridge construction

Debate

Plans for bridge's replacement have been studied since the 1970s, however for financial reasons it was always decided that the original structure would continue to be maintained. Due to the aging of the bridge, and in order to ensure the punctuality of trains, the prefectural governments of Tottori and Hyōgo with local municipalities organized and decided to proceed with the bridge's replacement. Following the accident of December 28, 1986, delays and cancellations increased, but the main reason for the delays is the increased frequency of service east of Kinosaki Onsen Station, and the operational problems caused by the line's single-track construction. Although the bridge is sometimes closed, it was not a strong influence on the decision. A new prestressed concrete bridge on the existing structure's south side will be built to allow trains to operate in wind conditions of up to 30 m/s. Its design will allow for easy maintenance, and because local governments are providing 80% of the cost, JR West plans to complete the work as quickly as possible. Work has been underway since Spring 2007.

Sightseers and railfans have voiced regret over the replacement of the bridge, and many believe that the new concrete bridge will not be a draw for tourists. During 2006 and 2007, prior to the construction, the surrounding area was inundated with people hoping to see the bridge one last time. Some trespassed on private property, and the unusually large number of visitors proved troublesome for local residents.

The Tottori Prefectural Assembly has announced that they may withhold funding for the work if the overnight express service Izumo is discontinued.

There are plans for the bridge following the completion of its replacement. Some call for the preservation of the structure, others for the construction of a memorial hall. The local government is forming a committee to consider the matter. It has been requested that in any case that the bridge's physical prominence and the 1986 accident will be commemorated for future generations. One plan put forth by the government of Kami preserves the three vertical supports and girders closest to Amarube Station.

On May 27, 2007, the ceremony marking the beginning of construction was held. It was attended by the governor of Hyōgo Prefecture as well as members of the Diet. Even after construction began, regular maintenance was still carried out on the bridge. The presence of construction vehicles detracts from the location's appeal to tourists, and the number of visitors has decreased. With the completion of maintenance in October 2007, scaffolding was dismantled and stored in what was previously a parking lot for tourists. The parking lot has been moved to a location nearby.

Work began in earnest in October 2008, and both the observation area at the station and the station itself were closed for safety purposes.

Construction timeline

The new bridge piers under construction

See also

References

    External links