Yme field

From Wikipedia, the free encyclopedia
Yme field
Location of Yme field
Country Norway
Location Central North Sea
Block 9/2-3, 9/2-6 S, 9/2-7 S, 9/2-9 S
Offshore/onshore Offshore
Coordinates 57°48′57.91″N 4°32′07.69″E / 57.8160861°N 4.5354694°E / 57.8160861; 4.5354694Coordinates: 57°48′57.91″N 4°32′07.69″E / 57.8160861°N 4.5354694°E / 57.8160861; 4.5354694
Operator Statoil (1996–2001)
Talisman Energy (2010–...)
Partners Talisman Energy
Norske AEDC
Wintershall
Grupa Lotos
Field history
Discovery 1987
Start of production 1996
Production
Recoverable oil 56 million barrels (~7.6×10^6 t)

Yme is an oil field in the Egersund basin area in the central part of the North Sea. It is located 160 kilometres (99 mi) northeast of the Ekofisk oil field.[1] The water depth is 93 metres (305 ft). The field was discovered in 1987 and was developed by Statoil with production from 1996 to 2001.[2] In 2001 low oil prices led to the abandonment of the field. After the production license was relinquished by Statoil, a new license group led by Talisman Energy was formed to redevelop the field. In 2007 Talisman were granted permission to redevelop the field, this marked the first time that a previously abandoned Norwegian oil field has been restarted.[2]

Original development by Statoil

The field was produced by Statoil from February 1996 until it was closed down in 2001. The field was produced using the jackup rig Maersk Giant equipped with oil producing facilities.[3] The produced oil was transferred to the tanker Polysaga. Polysaga had a storage capacity of up to 160,000 cu meters of oil. It was moored and loaded by the subsea turret loading system (STL). The oil from Polysaga was offloaded to a shuttle tanker and transported to the Statoil Mongstad terminal near Bergen for final processing and fiscal metering. Mongstad had to beef up its desalters in order to be able to handle the Yme crude. The field was abandoned in a time of low oil prices after having produced 56 million barrels (8.9×10^6 m3) of oil (15% recovery of original oil in place).

Redevelopment by Talisman Energy

The Yme field is currently owned and operated by Talisman Energy. Talisman began redevelopment of the field in 2008.[1] The redevelopment project is intended to include the installation of 12 production and injection wells and a subsea storage tank. Talisman Energy initially hoped to recover a further 56 million barrels (8.9×10^6 m3) of oil over a period of 10 years. Since Talisman began redevelopment the project has suffered from large cost overruns and extended delays in bringing the field onstream.[4] As of December 2012 first production from the field is not expected until the middle of 2013.

Talisman selected to develop the field using a production jackup platform with a subsea storage tank (MOPU STOR). Drilling will be completed by a separate drilling rig that will leave the field once drilling is completed. The MOPU STOR platform was designed and constructed by SBM Offshore who previously developed the concept for the Siri field. In July 2011 SBM announced the successful installation of the Yme platform, stating that the remaining commissioning activities were expected to be complete before the end of 2011.[2] Subsequently poor weather conditions led to the delay of the commissioning work and in May 2011 Talisman announced a writedown of $250 million on the project and delayed expected first production for an unspecified amount of time.[5]

MOPU STOR platform structural issues

In July 2012 Talisman evacuated 140 construction workers from the yme platform as a safety precaution after the discovery of cracks in the cement grouting surrounding the legs of the platform.[2][5] In a letter to Norway's Petroleum Safety Authority (PSA) dated 26 July Talisman warned that without repair there is a high probability that the cracks in the cement grouting could lead to the collapse of the platform during winter storms.[6] Talisman were subsequently given until a deadline of 31 December by the Norwegian Petroleum Directorate to deliver a new development plan for Yme which addresses its safety issues. On 26 October 2012 Talisman announced that they had agreed a plan with SBM to repair the faulty grouting by the end of the 2012.[7] Repair activities will be completed by SBM through its subcontractors.

Crude oil quality

The crude oil produced had an API gravity of 38-39 and a sulfur content of 0.17% mass. The formation water had a high salt content with dissolved NaCl of 190.000 ppm. And there was a high asphaltene content in the crude oil.

The Yme reservoirs also had challenges such as low reservoir pressure and low dissolved gas content.

References

  1. 1.0 1.1 Acher, John (2007-01-09). "Talisman to reopen Norway's Yme field". Reuters. Retrieved 2012-12-21. 
  2. 2.0 2.1 2.2 2.3 "Yme". SubSealQ. Rigzone.com, Inc. Retrieved 2012-12-21. 
  3. "Yme Oil Field, Egersund Basin, Norway". Offshore-Technology. Net Resources International. Retrieved 2010-08-29. 
  4. Cresswell, Jeremy. "Yme... A Living Nightmare for Talisman as Troubles Drags On". Aberdeen Press and Journal (Rigzone). Retrieved 2012-12-21. 
  5. 5.0 5.1 Welsch, Edward. "Talisman Finds Cracks in Norway Yme Platform, Evacuates Workers". Dow Jones Newswires (Rigzone). Retrieved 2012-12-21. 
  6. Botterli, Vegard (2012-10-04). "Talisman's Yme oil platform could collapse in storm: document". Reuters. Retrieved 2012-12-21. 
  7. Botterli, Vegard (2012-10-26). "Talisman agrees to fix Yme platform legs to prevent collapse". Reuters. Retrieved 2012-12-21. 

External links

This article is issued from Wikipedia. The text is available under the Creative Commons Attribution/Share Alike; additional terms may apply for the media files.