Wyaralong Dam
Wyaralong Dam | |
---|---|
Dam wall from viewing platform | |
Location | 14km North-West of Beaudesert, Queensland |
Coordinates | 27°54′33″S 152°52′52″E / 27.9092°S 152.881°ECoordinates: 27°54′33″S 152°52′52″E / 27.9092°S 152.881°E |
Type | Reservoir |
Primary inflows | Teviot Brook |
Primary outflows | Teviot Brook |
Catchment area | 533 km2 |
Basin countries | Australia |
Max. length | 500 m |
Surface area | 1,230 hectares |
Water volume | 103,000 ML |
The Wyaralong Dam is a water project that was initiated by the Queensland Government in 2006 as a result of a prolonged drought which saw the catchment areas of South East Queensland's dams receive record low rain.
Construction of the dam wall was completed prior to the 2010–2011 Queensland floods. On January 11, during the flood period, Logan City’s Mayor Pam Parker and Scenic Rim’s Mayor John Brent said they believed Logan had been spared a great deal of flood damage because of the dam.[1]
Conception
The site was identified in a 1990 study, “Water Supply Sources in South-East Queensland”, as a future source of water supply for the South East Queensland region. In this report it was ranked 13th out of 15 studied possible dam locations in South East Queensland. A location on the Albert River at Glendower, also near Beaudesert, was the preferred location and the government subsequently bought back all the land required for the Glendower Dam. A new dam was not expected to be required until 2060 or later and Glendower Dam remained the preferred dam site, the land already fully government owned.[citation needed]
In October 2005, with an election pending, the Queensland government announced Wyaralong Dam as the new preferred option, even after recent studies into possible dam locations found a location upstream on the Logan River to be a more reliable option. After a series of studies, a Senate Inquiry and much contested information, Federal Environment Minister Peter Garrett granted approval for the dam in November 2008.[2]
The dam is a storage and regulation facility. It does not discharge directly into the piped reticulation network, but rather discharges back into the natural drainage network of creeks and brooks. Water released from the dam flows downstream along Teviot Brook to Cedar Grove Weir, where it is diverted for treatment and use in the piped network.
Construction
The construction was tendered under an alliance contract. In this type of contract risks and rewards are shared by all the proponents including designers constructors and the owner. Queensland Dam Consortium won the tender for the dam's construction, and the Alliance was formed from their members which included Macmahon Construction as the lead contractor, Hydro Tasmania, Snowy Mountains Engineering Corporation, Paul Rizzo and Associates (USA), ASI Contractors (USA) and Queensland Water Infrastructure the special purpose vehicle created by the Queensland Government owner to deliver the project.[3] The Alliance contract for dam construction was for a little over A$100 million. However it was widely reported that the building costs for the dam would total A$333 million.[4] The latter figure includes the cost of the Bromelton Offpeak Storage Project, Cedar Grove Weir and the reconstruction of a length of the Boonah to Beaudesert Road.
Work on access roads began in early 2009 and construction of the dam wall began in early 2010.[4] The diversion channel was plugged on 17 December 2010, allowing the dam to begin to fill.[5] The dam site was opened to the public on 3 June 2011.[6]
The dam wall is 500 m in length and 48 m high. It is constructed from a medium cementitious mix roller compacted concrete.[3] The foundation is a sub horizontal dipping blocky sandstone. The dam is built with a 130m wide uncontrolled central primary spillway and an uncontrolled left bank secondary spillway which commences discharging at the 1:100 year flood level. The dam cross section is rather squat in order to provide sufficient resistance against potential sliding along foundation bedding planes.
The outlet is on the right bank and is capable of abstracting water from any level of the reservoir by the use of baulks. The outlet includes an innovative and operationally complex bidirectional fish lift, which uses a single hopper to transport fish in both upstream and downstream directions.
The twelve kilometres of new road between Boonah and Beaudesert were constructed under a separate contract by Fulton Hogan.[3]
The dam cost AUS$380 million to construct, including purchasing farmland flooded by the dam reservoir.[7]
Catchment
Teviot Brook has a 533 km² catchment (to the dam wall) and has its headwaters in the western part of the McPherson Range and flows in a north easterly direction to join with the Logan River north east of Beaudesert. Teviot Brook and the surrounding land is a recognised Aboriginal Pathway with significant cultural heritage values.
January 2011 floods
As a result of rainfall during the 2010–2011 Queensland floods the dam filled to 100% capacity, just 25 days after the wall was plugged to hold water, but before its completion.[5] By January 10, during the flood period, the dam held 83,133 megalitres, 80.7 per cent of its 103,000 megalitre capacity. Parts of the dam were still under construction, but its wall was plugged to hold water on December 17 2010.[8] On January 11 the dam filled and began to overtop at 9:27am, Following the overtopping, in the first 24 hours over 17,300 megalitres of water flowed over the primary spillway and entered the Logan River at Cedar Grove.[5]
Treatment
By late 2012 the dam still had not been connected to the SEQ Water Grid because it contains water so mineralised it is cheaper to produce desalinated water than to treat it.[7] The Wyaralong water treatment plant is expected to cost $235 million to construct.[9] Funding for the plant is planned for the 2014/15 financial year.
See also
- List of reservoirs and dams in Australia
References
- ↑ "On the road in Logan today". Logan West Leader. 11 January 2011. Retrieved 2011-01-13.
- ↑ "Wyaralong dam decision 'devastating' for residents". ABC News Online. Australian Broadcasting Corporation. 26 November 2008. Retrieved 2009-10-22.
- ↑ 3.0 3.1 3.2 "Wyaralong Dam contractors announced". Queensland Water Infrastructure Pty Ltd. Retrieved 2009-10-22.
- ↑ 4.0 4.1 "Wyaralong Dam to boost jobs, economy: Lucas". ABC News Online. Australian Broadcasting Corporation. 21 January 2009. Retrieved 2009-10-22.
- ↑ 5.0 5.1 5.2 "Wyaralong Dam". Seqwater. Retrieved 27 November 2012.
- ↑ Melanie Maeseele (4 June 2011). "Summer rains fill up dam". The Queensland Times. Retrieved 27 November 2012.
- ↑ 7.0 7.1 Tuck Thomson (16 October 2012). Bligh government-built Wyaralong Dam an expensive 'mistake'. The Courier Mail. Retrieved on 16 October 2012.
- ↑ "Wivenhoe Dam hits record high". The Queensland Times. The Queensland Times. 11 January 2011. Retrieved 2011-01-13.
- ↑ Patrick Lion (19 June 2011). "Water wasted as State Government decides against tapping into $350m dam". The Sunday Mail (Queensland Newspapers). Retrieved 27 November 2012.
External links
Wikimedia Commons has media related to Wyaralong Dam. |