West Kowloon Terminus
West Kowloon Terminus 西九龍站 | |
West Kowloon Terminus construction site | |
Location | |
City | Hong Kong |
District | Yau Tsim Mong |
Station statistics | |
Line(s) | Guangzhou–Shenzhen–Hong Kong XRL █ Airport Express █ Tung Chung Line █ West Rail Line |
No. of platforms | 15[1] |
West Kowloon Terminus (WKT) is the terminus of the Hong Kong Section of Guangzhou–Shenzhen–Hong Kong Express Rail Link (XRL), and is currently under construction. It is the only station in the Hong Kong Section and will connect to the mainland China section through a dedicated tunnel. It is being constructed by the MTR Corporation.[2]
Aedas in collaboration with AECOM has been awarded the contract to design the multi-story 25-acre (100,000 m2) terminus.[3][4]
WKT will be located in Jordan, Kowloon, north of the proposed West Kowloon Cultural District between the Airport Express and Tung Chung Line Kowloon Station and the West Rail Line Austin Station, extending into the underground area of the West Kowloon Cultural District.[5] It will be commissioned in 2014 at the earliest.[2]
Structure
Construction of the West Kowloon Terminus project was divided into two parts, XRL810A ( northern part ) and XRL810B ( southern part ) [6] (XRL meaning eXpress Rail Link). The northern construction area was awarded to Leighton Contractors & Gammon Construction(Golden Gate) responsible for joint operations. The southern part of the project was awarded to a consortium of Laing O'Rourke, HCCG(Xinchang) & Paul Y jointly responsible for the construction.
West Kowloon Terminus features 9 long distance platforms and 6 short haul regional platforms for a total of 15 platforms.[7][8] In addition, as a cross-border railway railway station, West Kowloon Terminus will also be set up with Hong Kong Customs and Immigration facilities for the passengers to go through the formalities prior to boarding the train and not requiring any stops at the Hong Kong border.[9][10][11]
Platforms
First Floor | Platform |
Footbridge MTR Kowloon Station and Austin Station, shop, garden squares, green Strip |
Ground | Concourse | Entrance, concourses, public transport interchange, green ground Plaza |
Underground Level 1 | Hallway Floor | Ticketing lobby, taxi drop-off stations, parking superstructure |
Underground Level 2 | Entry Level | Austin Road West underpass arrival hall, offices, taxi pick-up stations, subways to Austin Station, the station car park |
Underground Level 3 | Departures Level | Waiting room, departure hall |
Underground Level 4 | Side Platform | |
1Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Island platform | ||
2 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Island platform | ||
3 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Island platform | ||
4 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Island platform | ||
5 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Island platform | ||
6 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link regional train to Guangzhounan (Futian) | |
Side Platform | ||
Side Platform | ||
7 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link long-distance trains to major cities outside Guangdong Province (Shenzhenbei) | |
8 Platform | ||
Island platform | ||
9 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link long-distance trains to major cities outside Guangdong Province (Shenzhenbei) | |
10 Platform | ||
Island platform | ||
11 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link long-distance trains to major cities outside Guangdong Province (Shenzhenbei) | |
12 Platform | ||
Island platform | ||
13 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link long-distance trains to major cities outside Guangdong Province (Shenzhenbei) | |
14 Platform | ||
Island platform | ||
15 Platform | Guangzhou–Shenzhen–Hong Kong Express Rail Link long-distance trains to major cities outside Guangdong Province (Shenzhenbei) |
Green Belt
West Kowloon Terminus will feature an extensive green garden and parklands across the roof area of the station. It will also set up a large collection of cultural elements and entertainment spaces. Passengers can easily cross the ground floor between Kowloon Station, Austin Station and West Kowloon Cultural District, providing Hong Kong residents and visitors ample public open space and a comfortable green walking environment. Above the station, an area of approximately 8,900 square metres will be planted with a large number of plants and trees with traffic separated. All to create a pedestrian area, a green platform and wooded park that will integrate with the West Kowloon Cultural District harbourside parklands.
In addition, the West Kowloon Terminus entrance lobby area will feature a green ecological leisure channel zone to tie in with the greenery on top of the building.
Train services
The West Kowloon Terminus will be served by both short distance services and long distance train services. Short distance services consist a frequency service to neighbouring Guangdong province, mainland China cities including Shenzhen, Dongguan and Guangzhou, while long distance services link Hong Kong with at least 16 major destinations in mainland China.[12] Six platforms will be designated for short haul trains, while nine will be designated for long haul trains.
Short distance services
- 4 trains per hour to Shenzhenbei
- 2 trains per hour to Guangzhounan
Preceding station | China Railway High-speed | Following station | ||
---|---|---|---|---|
Terminus | Guangzhou-Shenzhen-Hong Kong XRL
Short haul service |
Terminus |
||
Terminus | Guangzhou-Shenzhen-Hong Kong XRL
Short haul service |
Shenzhenbei
towards |
||
Terminus | Guangzhou-Shenzhen-Hong Kong XRL
Short haul service |
Terminus |
||
Terminus | Guangzhou-Shenzhen-Hong Kong XRL
Short haul service |
Guangzhounan
towards |
Long haul services
- 33 trains per day to 16 major Chinese cities including Beijingxi Shijiazhuang Zhengzhoudong Wuhan Changshanan and Shanghai.
Preceding station | China Railway High-speed | Following station | ||
---|---|---|---|---|
Terminus | Guangzhou-Shenzhen-Hong Kong XRL
Long haul service |
Shenzhenbei
towards |
According to a 2008 study, it is expected that by 2030, train services will increace in frequency.[13][14]
- To and From Futian Railway Station (Shenzhen): 54 trains per day
- To and From Shenzhenbei (Longhua, Shenzhen): 54 trains per day, on average every 15 minutes
- To and From Humen (Humen): 7 trains a day
- To and From Guangzhounan (Guangzhou): 25 trains per day, on average every 30 minutes
- To and From Cities outside Guangdong (e.g. Beijing and Shanghai) long-distance trains: 33 per day
It is expected that by 2016, the West Kowloon Terminus daily number of passengers carried will be about 99,000 passengers.
Transport links
MTR
West Kowloon Terminus is located between two MTR stations, Kowloon Station and Austin Station. It is intended to develop into commuter hub as the goal. Passengers can gain transfer through the ground pedestrian area, a number of footbridges and subways to connect with the MTR Kowloon Station and Austin Station. It is expected that a walk from Kowloon Station to West Kowloon Terminus Station will require 8–10 minutes, transfer to/from Austin station needs only 2–3 minutes.
From the West Kowloon Terminus via the MTR to the various regions of Hong Kong :
- East Tsim Sha Tsui : 5 minutes
- Central : 10 minutes
- Wan Chai : 10 minutes
- Yuen Long : 25 minutes
- Shatin : 25 minutes
- Tung Chung : 25 minutes
- Tai Koo : 30 minutes
- Kwun Tong : 35 minutes
Public Interchange
In addition, at the northern terminus in West Kowloon will set up a public transport interchange and long-distance coach berthing facilities. Walking from the West Kowloon Terminus to these facilities only takes one minute. Passengers can use different modes of transport to reach for the bus station, minibus station and taxi stand.
Time needed to travel to/from West Kowloon Terminus using road transport :
- Kwun Tong, Tai Koo Shing : 15–20 minutes ( via Central–Wan Chai Bypass when completed )
- Shatin, Yuen Long, Hong Kong International Airport : 30 minutes
Nearby Road Network
Related developments by the Hong Kong government in West Kowloon, expect to improve the efficiency of road and pedestrian access routes, as well as to resolve a problematic traffic intersection in West Kowloon. These road developments hope to meet the transport needs of the entire area of the new development area of West Kowloon Cultural District and West Kowloon Terminus after completion.
Transportation Study identified the following specific road improvement measures:
- Build a connection from Austin Road West (near Canton Road) to Lin Cheung Road (Jordan Road north) via an underground carriageway, so that pedestrians will have unimpeded access and ergress between West Kowloon Cultural District, West Kowloon Station and Kowloon Terminus;
- Conduct Austin Road and Canton Road junction improvement works, including considering the widening of the Canton Road carriageway and expansion of existing underground pedestrian tunnel system;
- Other road improvement projects in West Kowloon will be directly connected to a newly developed area near the West Kowloon Highway, in order to reduce the load on the region's transportation network.
Awards
In 2010, the West Kowloon Terminus design won "Cityscape Awards for Architecture" in the Emerging Markets of Tourism, Travel & Transport Future Awards.[15] In the same year on November 4, the West Kowloon Terminus design won the "Best Future Project ─ Infrastructure" World Architecture Festival Awards.[16]
See also
- Guangzhou-Shenzhen-Hong Kong Express Rail Link
References
- ↑ "Railway Facilities". MTR Corporation. Archived from the original on 19 October 2013. Retrieved 19 October 2013.
- ↑ 2.0 2.1 Guangzhou-Shenzhen-Hong Kong Express Rail Link
- ↑ "West Kowloon Terminus, Hong Kong". AECOM. Retrieved 27 December 2012.
- ↑ "Express Rail Link West Kwoloon Terminus Hong Kong". Aedas. Retrieved 27 December 2012.
- ↑ West Kowloon Terminus (WKT)
- ↑ 廣深港高速鐵路-已批合約
- ↑ 環境評估報告:廣深港高速鐵路香港段(環境評估報告NOL/ERL/300/C/XRL/ENS/M50/024號文件),2009年7月22日,香港環境保護署
- ↑ Express Rail Link West Kowloon Terminus Hong Kong 凱達環球
- ↑ 環境評估報告:廣深港高速鐵路香港段(環境評估報告NOL/ERL/300/C/XRL/ENS/M50/025A號文件),2009年7月22日,香港環境保護署
- ↑ 環境評估報告:廣深港高速鐵路香港段(環境評估報告NOL/ERL/300/C/XRL/ENS/M50/026A號文件),2009年7月22日,香港環境保護署
- ↑ 政府當局就西九龍總站介紹提供的文件 2009年11月17日,香港立法會
- ↑ "Frequency and Capacity". MTR Corporation. Retrieved 13 November 2010.
- ↑ 大珠三角之鐵路發展 第25頁,香港鐵路公司,2008年10月18日
- ↑ 高鐵班次及載客量 香港鐵路公司
- ↑ Real Estate Investment, Development and Construction Exhibition - 2010 Winners Cityscape,2010年