Onehunga Branch

From Wikipedia, the free encyclopedia
Onehunga Branch

ADL 810 at Onehunga station, with new electrification infrastructure installed
Overview
Type Urban rail
Status Open
Termini Penrose
Onehunga Station
Stations 3
Daily ridership 1200/day[1]
Operation
Opening December 1873
Reopened September 2010
Closed 1973 (for passenger trains)
2006 (for freight trains)
Owner KiwiRail Network
Operator(s) Veolia
Character Urban
Rolling stock ADL class
Technical
Line length 3.6 km (2.2 mi)[2]
No. of tracks Single
Track gauge 1,067 mm (3 ft 6 in)
Electrification 25kV installed, not in service.[3][4]
Route map
Legend
North Auckland Line
00 km Penrose
North Auckland Line
O'Rorke Rd
Maurice Rd
Mays Rd
1.95 km Te Papapa
Captain Springs Road
Church St
3.32 km Onehunga
Neilson St
3.20 km State Highway 20
3.41 km Onehunga Wharf

The Onehunga Branch railway line is in Auckland, New Zealand. It was constructed by the Auckland Provincial Government and opened from Penrose to Onehunga on 24 December 1873, and extended to Onehunga Wharf on 28 November 1878. It is 3.6 kilometres (2.2 mi) in length.[2]

After being closed to passenger traffic in 1973 and mothballed in 2007, the line was reopened on 18 September 2010 with regular passenger services beginning on 19 September 2010.[2][5]

History

Construction and original services

Onehunga railway station, circa 1873.

The Onehunga Branch was one of the first government-funded railways in New Zealand. Along with a further 10 km north to Auckland (now part of the North Auckland Line and the Auckland–Newmarket Line), the Onehunga Branch was the first operating section of the railways in the North Island. Construction had begun in 1865 under the auspices of Auckland's provincial government, to standard gauge, 1,435 mm (4 ft 8 12 in), but due to a lack of funds and disputes between the government and the contractors building the line, construction stalled two years later. The line featured in Julius Vogel's 1870 Great Public Works programme and construction resumed in 1872, with to New Zealand's new narrow gauge of 1,067 mm (3 ft 6 in). With the dissolution of the provinces of New Zealand, the line was integrated into the state-run system on the creation of the New Zealand Railways Department.[6]

Connecting the Port of Onehunga with Penrose and hence the port of Auckland, the line became a busy link between the two harbours of the rapidly expanding city. Onehunga was a busy port despite its treacherous harbour entrance, and was well served by coastal shipping, some of which plied to New Plymouth. With the completion of the Wellington and Manawatu Railway Company's railway line in 1886, passengers from Auckland to Wellington rode a "Boat Train" from Auckland to Onehunga, connected with a steamer to New Plymouth, then the New Plymouth Express to Wellington. The boat trains ran to the wharf and in 1878 a small station was sited there and remained in use until 1927. By 1897 there were 14 trains daily, both passenger and mixed trains. In 1903 electric trams were introduced between Auckland and Onehunga, running along Manukau Road, resulting in a significant drop in passenger patronage on the branch line. The boat trains finished in the 1920s and the through service from Auckland to Onehunga in 1950, but passenger services from Penrose ran until April 1973. The line then served local industries until it was mothballed. Freight shunts continued to operate as far as Mays Rd until late 2007 and an annual enthusiast excursion with ADL class DMU ran until 2006. Three visits by Silver Fern railcars occurred in 1996, 1999 and 2000. The last steam trains before closure was a series of excursions over Labour Weekend 1993 with a tank engine and carriages from Glenbrook Vintage Railway. JA 1275 ran shuttle trains with DC 4536 on 18 September 2010 to celebrate the reopening of the line, before regular passenger services commenced the next day.

The original Onehunga Railway Station was on the corner of Princes Street and Onehunga Mall. The old station building has been relocated to 38 Alfred Street, not far away, and is owned by the Railway Enthusiasts Society and used as their clubrooms and a railway museum. Other stations were at Te Papapa and Onehunga Wharf.

2010 reopening

The campaign to reopen the line was launched by Auckland Regional Council (ARC) councillor Mike Lee in mid-2002. The cause was taken up by Campaign for Better Transport. Lee and CBT's concept was to rebuild the line, with new stations at Mt Smart, Te Papapa and Onehunga, and in mid-2006 CBT had received 8,000 signatures on a petition to reopen the line.[7]

The petition was presented to the ARC, which formally endorsed it and passed it to its subsidiary, ARTA, recommending that passenger services should be started to both Onehunga and to Helensville. The petition was later handed back by ARTA to the ARC, with ARTA stating that the track was the responsibility of government track organisation, ONTRACK (now part of KiwiRail). The petition was presented to Parliament's Transport and Labour Relations Select Committee by Lee as Chairman of the ARC. On 13 March 2007 the Government announced that it had given approval for ONTRACK to spend $10 million on reopening the line for passengers and freight. As part of the rehabilitation work a private siding was built at the Owens truck depot.[8]

The blocked former underpass of the branch line at the Onehunga Port.

In August 2007 coastal shipping firm Pacifica Shipping called for the section of the line between Onehunga Wharf and the end of the line at the Port of Onehunga to be reopened,[9] to allow for export freight from the South Island to be unloaded at the wharf and transferred by rail to the port of Auckland on the Waitemata Harbour. Currently the freight is carried by road to the port, leading to delays due to traffic. A full freight service reopening could potentially remove around 200 containers to and 250 containers from the port per week from the local streets.[10]

In 2009 the locations of stations on the branch were still to be determined by ARTA and ONTRACK.[11] It was also unclear in May 2009 whether the reopened line would reach as far as Onehunga Mall (as originally planned) and it was noted that continuation to the port of Onehunga would depend on Ports of Auckland's willingness to fund a terminal within its land.[12] However, detailed design for Te Papapa and Mount Smart stations was underway.[13]

On 24 June 2009 ARTA and the New Zealand Transport Agency (NZTA) agreed to jointly fund three stations on the branch – Mt Smart, Te Papapa and Onehunga (on the site of the ITM, 109-113 Onehunga Mall). NZTA was to pay 60% of the $3.9 million cost of building the stations.[14]

In mid-2010, construction started on the terminal station at Onehunga, and its opening was delayed past its intended date to September 2010. Concern was raised that the new station would not be able to take three-car trains due to its short length, but ARTA responded by noting that initial usage predictions did not require three-car trains, and that the length of the platform could be extended later, though new consents would be needed.[5]

On Saturday 18 September reopening ceremonies were held, with Sunday 19 September being the first day of normal passenger services. The cost of reopening the line was about $21.6 million, of which KiwiRail contributed $10 million for track work and ARTA $3.6 million for three stations. The ARC also used $8 million to buy the site for the Onehunga station, where a 60-space park & ride facility was to open one week after the train services began.[15]

Patronage on the line quickly grew to respectable levels, 1200 passengers a day in mid-2011,[1] far exceeding computer transport modelling predicting only 340 passengers a day by 2016.[16]

Electrification

The line is currently being upgraded as part of the Auckland railway electrification programme. It is supposed to be the first line to be commissioned.[4] Installation of overhead wires was completed during the summer shut down from 2011—2012, stopping just short of Penrose.[3] The overhead line is currently not active, and is awaiting the delivery of the first electric trains over 2013-2014. It is likely that the Britmart-Onehunga services will be the first to be run with electric trains.

Potential future extension

Extension of the line to Auckland International Airport has been proposed. The main barrier has been crossing Manukau Harbour between Onehunga and Mangere Bridge. Transit New Zealand, NZTA's predecessor, announced that a bridge across the harbour would be designed to accommodate a rail link.[17] In September 2007 ARTA announced that it was willing to pay Transit $2.5 million to "future-proof" the duplication of the Manukau harbour crossing in order "to accommodate a passenger rail connection."[18] The bridge was built to accommodate this, and NZTA has provided for a rail corridor near the motorway as far as Walmsley Road.[1]

There is a proposal to build an Avondale–Southdown line, connecting the North Auckland Line (the MAXX Western line) near Avondale to Auckland Freight Centre at Southdown. KiwiRail owns most of the corridor, which leaves the North Auckland Line east of Avondale and follows Oakley Creek and the SH20 Waterview Connection motorway corridor (construction of which has made provision for the rail line's construction).[19]

Another proposal is to connect the Onehunga Branch at Galway Street to the Avondale—Southdown line by building a tunnel under Onehunga Mall to meet Hugh Watt Drive (SH 20), connecting to the proposed route at Hillsborough.[20]

References

  1. 1.0 1.1 1.2 Dearnaley, Mathew (4 June 2011). "Stuck in traffic". The New Zealand Herald. Retrieved 12 July 2011. 
  2. 2.0 2.1 2.2 Dearnaley, Mathew (12 May 2010). "ARC chief unhappy at delay to new service". The New Zealand Herald (Auckland: APN Holdings NZ). 
  3. 3.0 3.1 "Auckland rail electrifcation: current activities". KiwiRail. Retrieved 17 January 2012. 
  4. 4.0 4.1 "EMU, Depot and Electrification Infrastructure". Report to the Auckland Council Transport Committee. 7 December 2011. Retrieved 22 December 2011. 
  5. 5.0 5.1 "Auckland platform woes can be fixed - ARTA". The New Zealand Herald. 8 July 2010. Retrieved 8 July 2010. 
  6. Geoffrey B. Churchman and Tony Hurst, The Railways of New Zealand: A Journey Through History (Auckland: HarperCollins, 1991), 101.
  7. Dearnaley, Mathew (21 April 2010). "Work starts at new Onehunga rail station". The New Zealand Herald. Retrieved 16 January 2011. 
  8. "Onehunga rail upgrade gets green light". The Beehive. 13 March 2007. Retrieved 2007-09-01. 
  9. Heather McCracken (8 August 2007). "Firm floats port rail plan". Auckland Central Leader. Retrieved 2007-09-01. 
  10. Dearnaley, Mathew (16 August 2007). "Rail freight studied for Onehunga". The New Zealand Herald. 
  11. Phoebe Falconer (14 April 2009). "Revamped rail link will lead to airport service". New Zealand Herald. Retrieved 2009-04-12. 
  12. Dearnaley, Mathew (5 May 2009). "Train plans on track, Onehunga told". The New Zealand Herald. Retrieved 1 November 2011. 
  13. Monthly Business Report, March 2009 (from ARTA. Accessed 2009-05-10.)
  14. Rhiannon Horrell (24 June 2009). "Action on Onehunga line". Central Leader. Retrieved 2009-09-24. 
  15. "Rail link puts fun back into getting to school". The New Zealand Herald. 21 September 2010. Retrieved 22 September 2010. 
  16. "Reopening Onehunga rail line cheaper option". The New Zealand Herald. 23 May 2006. Retrieved 3 November 2013. 
  17. Dearnaley, Mathew (9 February 2007). "Transit opens door to cross-harbour rail link to airport". New Zealand Herald. 
  18. Dearnaley, Mathew (7 September 2007). "$2.5m offer to link Auckland airport to Britomart". New Zealand Herald. Retrieved 2007-09-07. 
  19. "Evidence of Pamela Marie Butler on behalf of KiwiRail". KiwiRail / Environmental Protection Authority. 17 December 2010. Retrieved 15 January 2011. 
  20. "Maungakiekie Area Plan". Auckland City Council. Retrieved 2009-04-14. 

External links

This article is issued from Wikipedia. The text is available under the Creative Commons Attribution/Share Alike; additional terms may apply for the media files.