Muslim Town Flyover

From Wikipedia, the free encyclopedia
Muslim Town Flyover, Lahore

Muslim Town Flyover, Lahore
Location
Lahore, Pakistan
Roads at
junction:
Ferozepur Road
Wahdat Road
Canal Road
Construction
Type: Flyover
Lanes: 3 x 3
Constructed: by NLC and Habib Construction Services
Opened: 29 April, 2012

Muslim Town Flyover is flyover in the Muslim Town, Lahore.

Project overview

The subject project involved construction of a flyover along Ferozepur Road at Canal/Wahdat road junction.In order to make Ferozepur Road a signal-free corridor in addition to streamline traffic coming from various parts of the city. The project was a stupendous task and a race between time frame and quantum of work. Before execution of project a foolproof traffic diversion plan was prepared and implemented to ensure smooth flow of traffic despite a huge traffic saddle. Informatory and warning signboards were placed on various routes coming towards the construction site for guidance of road users.

Scope of work

The project consists of four bridges, two along Ferozepur Road, an exit ramp towards Wahdat road, and a canal bridge for canal service roads. Flyover no. 1 is carrying Kalma Chowk Flyover bound traffic while Ichra bound traffic is being served through Flyover no. 2. Traffic coming from Kalma Chowk Flyover, bound to Wahdat road is making use of exit ramp. Canal bridge is for U-Turn. The structures consist of massive reinforced concrete piles, piers, transoms, I&L-shape pre-stressed girders, box girders and deck slab. Reinforced concrete retaining walls are designed to serve as ramps of flyovers. In addition to these structures various slip lane and service roads have been constructed at grade.

Box girder bridge. A beautiful evening view of Muslim Town Flyover, Lahore

Construction details

Type Description
Name Muslim Town Flyover, Lahore[1]
Client Government of Punjab, Communication and Works Department [2]
Consultant NESPAK [3]
Contractor NLC in association with Habib Construction Services[4]
Commencement Date October 28, 2011
Completion Date April 21, 2012
Time for Completion 177 Days (5 months, 25 days)
Length of Flyovers including Ramps Flyover-1 (Kasur Bound) = 949 M

Flyover-2 (Ichra Bound) = 1308 M Flyover-3 (Wahdat Road Slip) = 298 M

Total = 2655 Meters

Construction Cost Rs. 2.3 Billions
Number of Spans 58
Width of Flyover 11 M (Flyover-1 and 2), 8.1 M (Wahdat Road Slip)
Number of Lanes 3 No. (Flyover-1 and 2), No. 3 (Wahdat Road Slip)
Number of Piles 307
Number of Girders 534
Number of Box Girders 4 Spans
Radius of Box Girder curve 48 Meters