Route map. Existing metro stations are shown as filled squares, metro stations under construction or planned as hollow squares. Dashed lines denote the first phase of the extension, dotted lines denote the second phase. The municipality boundary between Helsinki and Espoo runs mostly through sea between the Koivusaari and Keilaniemi stations.

Länsimetro (the Western Metro Extension, Swedish: Västmetron) will be an extension of the Helsinki Metro system from central Helsinki, Finland, to the neighbouring city of Espoo. The new stretch of line will extend from the existing Ruoholahti metro station via the island of Lauttasaari, the Aalto University Otaniemi campus, and Tapiola to a new terminus at Matinkylä, and will run completely underground. A possible second construction phase might extend the line to Kivenlahti.

Final approval for a 13.5-kilometre (8.4 mi) route was granted on 4 April 2007, and the construction began in November 2009. Rock blasting is expected to be complete by the end of 2012, followed by the fitting out of the tunnels. The extension is currently expected to open for service at the end of 2015.[1]

History

The first designs for a metro system in Helsinki, made in the 1950s, already contained lines to Espoo. After the two forks of the metro line in eastern Helsinki had been completed in 1998, the city of Helsinki continued to pursue the Länsimetro proposal, but the city of Espoo continued to reject it until the early 2000s.

Espoo is the second most populous city in Finland (after Helsinki), currently served by roads, bus transport, and commuter trains. It is connected to Helsinki by the Rantarata coastal railway and by two motorways: Finnish national road 1 (Turun moottoritie, to Turku) in the middle and the Western Highway (the Länsiväylä) in the south, near the coast. As the primary passageway between southern Espoo and central Helsinki, the Länsiväylä has been repeatedly enlarged to cope with congestion, but is still seeing chronic traffic jams in the morning rush hours. Widening the Länsiväylä has not solved the traffic jams, but has instead only moved them closer to the centre of Helsinki.

Since the 1990s, the Finnish state and the city of Helsinki had been willing to finance a part of the Länsimetro project and prepared to commence construction. However, Espoo opposed the project for a long time, mainly because of the cost: the state had only agreed to pay 30% of the costs, while Espoo wanted it to contribute at least 70%.

In 1997, Helsinki made an official proposal to Espoo to construct the Länsimetro. A year later, on 8 December 1998, the Espoo city council decided to only support extending the line to Tapiola, rejecting a continuation to Matinkylä and to Kivenlahti. On 16 February 1999, the city council changed its mind, and voted 48 to 18 in support of building the extension to Matinkylä. (These decisions did not yet authorize construction. As of June 2012, Espoo is keen on continuing the line from Matinkylä to Kivenlahti as soon as possible, wishing to commence the construction of this second phase even before the first phase enters service.[2])

The issue of the extension was reawakened in 2002, when the Helsinki Metropolitan Area Council (YTV) was writing a new master plan for public transportation in the Helsinki area. Counter to the view taken by the Espoo city council, YTV prioritised the Länsimetro over constructing a light rail line (an express tram) between Helsinki and Espoo. A compromise solution was reached: an investigation into the alternative of constructing such a light rail line was added to the plan, with a proposed construction schedule from 2010 to 2020. (See the subsection Controversy and alternatives, below.)

According to a survey requested by Helsingin Sanomat in late 2005, 77% of Espoo residents and 90% of Helsinki residents were in favour of the Länsimetro.[3]

On 25 September 2006, the Espoo city council approved constructing the Länsimetro by a vote of 45 to 19.[4] In its decision, the council set a number of conditions for the project:

  • The Finnish state must commit to financing the Länsimetro extension all the way to Kivenlahti.
  • The existing heavy railway line between Leppävaara and Espoo Centre should be widened from two tracks to three, in conjunction with the Länsimetro project.
  • The orbital Jokerilinja bus line should be converted to a light rail line/tram as soon as possible.
  • The orbital Kehä I ring road should be improved.
  • The orbital Kehä II ring road should be extended into Helsinki via Vihdintie to Hämeenlinnanväylä.

After the construction decision by the Espoo city council, allowing city taxes to be used for the project, critics of the decision worried that such a large construction project could conceivably bankrupt the city, and sued the city in the Supreme Administrative Court of Finland on a charge of "neglect in the decision-making".[5] Since administrative courts cannot rule on the substance of the decision, only the formal procedure was questioned. The court rejected the complaint.

On 11 November 2009, the Helsinki city council approved constructing the Länsimetro. Construction started on 24 November 2009.[6] Judicial complaints and appeals postponed the start for a year or so, but all were rejected by the Supreme Administrative Court.[7] Indeed, As of June 2012, Finnish courts have rejected all charges made against the extension.

Controversy and alternatives

In 2002, a joint study[8] by the city of Helsinki, the city of Espoo, and the Ministry of Transport and Communications compared the impact of the metro extension with that of building a bus rapid transit system. The running costs of the systems were estimated to be roughly equivalent. The metro extension would reduce emissions in Helsinki, but feeder buses would increase them in Espoo.[8] The metro would make it faster and more convenient to travel to Helsinki from the parts of Espoo near the new stations, but would increase the travel time from outlying areas.

A second study[9] by the same parties, published in 2004, investigated the alternative option of a light rail line. Its supporters claimed[citation needed] that it would be cheaper, faster to implement, and more environmentally friendly than a traditional metro line. The primary disadvantage of the metro was seen to be[citation needed] the requirement to build denser housing along the line to make it more efficient. Espoo is a relatively loosely built city with many detached houses, leading to its reputation as an upper middle class city. There have been fears[citation needed] that constructing the Länsimetro would create tighter residential centres around each new metro station, and that therefore the "image" of Espoo might suffer. Supporters of the metro point out that as the population of the Helsinki area keeps increasing through domestic and international migration, building more housing is necessary in any case.

Opponents of the light rail line noted that it would be yet another form of rail transport among the already diversely composed rail transport network in the capital area (trams, railway, metro); and that passengers could travel on the same metro system between all stations in Espoo and all stations in Helsinki, while constructing a light rail line would lead to all passengers travelling between east Helsinki and Espoo having to switch train systems. Supporters of the light rail line claimed that it could be easily integrated with the existing Helsinki tram network and that it would be much cheaper to build than the metro extension.

In 2006, an informal private-sector shadow plan for a light rail alternative called TramWest[10] was released. According to its critics, the plan underestimated costs and that the line was partly placed in areas where it would have been impossible to implement. TramWest also included many level crossings, which, if done badly, would slow down public transport. The proposed tracks would also have cut through the parks next to the Kiasma museum and the Helsinki Music Centre, and all the lines would have terminated at the Elielinaukio square next to the central railway station, without being integrated with any existing or future rail system. A revised version of the plan was released in early 2008, claiming to address most of these concerns.[11] It proposed connecting Espoo with both the Länsiväylä and with Helsinki's city centre, with the eastern terminus being relocated to either Viikki or Laajasalo.

Now that construction of the Länsimetro has commenced, all these alternatives have become moot.

The current state of the project

The cities of Espoo and Helsinki jointly founded a company called Länsimetro Oy (in English, "Western Metro Limited") to construct the extension.[citation needed] The CEO of the joint company is Matti Kokkinen.

The work started in January 2010 with the extension of the tunnels at the Ruoholahti metro station,[12] and rock blasting in Espoo commenced in August 2010.[13] All contracts for tunneling and station building were signed in December 2011,[14] and rock blasting reached 50% completion in July 2012.[15][16] The excavation of the rail tunnel is expected to be finished by 2013, and excavation of the first stations began in 2012. On the current schedule, the Länsimetro extension should enter service in late 2015.[1] Excavation is 75% complete as of December 2012. The first contracts for construction of the station structures and tracks have been signed.[17]

Cost

Preliminary plans, made in 2000 and 2001, cited the cost of building the infrastructure for the metro extension to Matinkylä to be about €400 million. When the Espoo city council decided on construction of the metro in 2004, the estimated price was €452 million. In September 2007, the estimated price of the Länsimetro was at least €530 million.[18] In December 2007, Olavi Louko estimated that the price will rise to at least €600 million. According to Louko, the price of the excavation work has risen a third more than that of other ground construction work, due to security requirements and to the increase in simultaneous excavation work elsewhere, including the construction of the Kehärata (Ring Rail Line) in nearby Vantaa.[19]

As of 2008 the estimated cost had risen to over €800 million.[20]

Route

A metro line extension was accepted as a basis for further planning in 2000. The locations of the stations were confirmed by the cities of Espoo and Helsinki in June 2007. The extension will be completely underground. The stations will be:

Ruoholahti–Matinkylä
Ruoholahti (Gräsviken)
Lauttasaari (Drumsö)
Koivusaari (Björkholmen)
Keilaniemi (Kägeludden)
Otaniemi (Otnäs)
Tapiola (Hagalund)
Urheilupuisto (Idrottsparken)
Niittykumpu (Ängskulla)
Matinkylä (Mattby)

The Ruoholahti—Matinkylä section (currently being constructed; the first three stations in Helsinki, the others in Espoo; Swedish station names in parentheses):

The approved future extension to Kivenlahti (all stations in Espoo; Swedish station names in parentheses):

  • Suomenoja (Finno)
  • Iivisniemi (Ivisnäs)
  • Soukka (Sökö)
  • Espoonlahti (Esboviken)
  • Kivenlahti (Stensvik)

See also

References

  1. 1.0 1.1 http://www.lansimetro.fi/en/component/content/535/16
  2. "Espoon kaupunginhallitus hyväksyi Länsimetron jatkamisen". Helsingin Sanomat (in Finnish). 2012-05-28. Retrieved 2012-06-02. 
  3. "The majority of Espooans support the Länsimetro". Helsingin Sanomat. 
  4. Oksanen, Kimmo (2006-09-25). "Espoon valtuusto hyväksyi metron äänin 45–19". Helsinki Sanomat (in Finnish). Retrieved 2010-02-16. 
  5. "Valitus Helsingin hallinto-oikeuden 5.12.2007 antamaan päätökseen, joka koski valitusta Espoon kaupunginvaltuuston 25.9.2006 tekemästä päätöksestä Espoon eteläosien joukkoliikennejärjestelmästä (Länsimetro)" (in Finnish). City of Espoo. 
  6. "Länsimetro construction launched". Railway Gazette. 2009-12-27. Retrieved 2010-02-16. 
  7. http://www.lansimetro.fi/fi/component/content/506/2
  8. 8.0 8.1 http://www.espoo.fi/redirect.asp?path=1;28;11866;17468;16395;41718;16390;42402;46346;46348&guid=C7350370-D2CB-4EEB-9B68-AD7E960123D8&site=4&appendvoucher=true
  9. http://www.raideyva.fi/
  10. http://www.tramwest.fi/
  11. http://www.tramwest.fi/index.php#Anchor-Uusitt-55095
  12. http://www.lansimetro.fi/fi/component/content/481/2
  13. http://www.lansimetro.fi/fi/component/content/566/2
  14. http://www.lansimetro.fi/fi/component/content/698/2
  15. http://lansimetro.fi/en/component/content/771/2
  16. Excavation passes halfway mark. Accessed on 29 August 2012.
  17. http://lansimetro.fi/en/component/content/823/2
  18. (Finnish) Länsimetron hinta noussut ainakin 80 miljoonaa euroa, Helsingin Sanomat 9 September 2007 page A11
  19. (Finnish) Länsimetron hinta on kivunnut jo ainakin 600 miljoonaan euroon, Tarkka hinta riippuu siitä, mitä päättäjät lopulta haluavat. Helsingin Sanomat 21 December 2007
  20. Länsimetron hinta on nyt 800 miljoonaa