Boguchany Dam
Boguchany Dam | |
---|---|
Construction works in 2011 | |
| |
Official name | Богучанская ГЭС |
Location | Kodinsk, Russia |
Coordinates | 58°41′41″N 99°08′56″E / 58.69472°N 99.14889°ECoordinates: 58°41′41″N 99°08′56″E / 58.69472°N 99.14889°E |
Construction began | 1974 |
Opening date | 2012 |
Dam and spillways | |
Type of dam | Combined gravity and rock-fill dam |
Impounds | Angara River |
Length | 2,587 m (8,488 ft) |
Height | 79 m (259 ft) |
Width (crest) |
Rock-fill section: 20 m (66 ft)[1] |
Width (base) |
Rock-fill section: 212 m (696 ft)[1] |
Spillway type |
surface-stepped and penstocks, gate-controlled |
Spillway capacity | 11,078 m3/s (391,216 cu ft/s) |
Reservoir | |
Creates | Boguchany Reservoir |
Total capacity | 58.2 km3 (47,183,508 acre·ft) [2] |
Active capacity | 2.31 km3 (1,872,747 acre·ft) |
Catchment area | 831,000 km2 (320,851 sq mi) |
Surface area | 2,326 km2 (898 sq mi) |
Max. water depth | 75 m (246 ft) |
Power station | |
Operator(s) | RusHydro |
Commission date | 2012 |
Turbines | 9 × 333 MW Francis-type |
Installed capacity | 1,332 MW |
Annual generation | 17.6 TWh |
The Boguchany Dam (Russian: Богучанская ГЭС) is a large hydroelectric dam on the Angara River in Kodinsk, Russia. Its primary purpose is hydroelectric power production and it will have an installed capacity of 2,997 MW. After decades of project delays, the first two generators were commissioned with the dam's inauguration on 15 October 2012.
History
Preparatory works for construction started in 1974. The design was performed by Hydroproject in 1976. Construction of the power station started in 1980 but was suspended in 1994 due to the lack of financing. Work on the project resumed in 2005 when RAO UES (then owner of RusHydro) and Rusal agreed to develop the project jointly.[3] Construction restarted in 2007.[4] The first turbine was dispatched in 2008.[5][6] The dam began to fill its reservoir in May 2012 and by August of that year, the first two turbines were installed.[7] They later became operational on 15 October 2012,[8] and full capacity is expected to be reached by 2013.[9][10]
Description
The Boguchany Dam is a 2,587 m (8,488 ft) long dam of combined type, which includes reinforced concrete 774 m (2,539 ft) long gravity segment for power station building and 1,813 m (5,948 ft) long rock-fill segment with asphaltene-concrete diaphragm throughout all its length. The dam was equipped with ship lock until 2010, later it was closed and its former location was included in concrete gravity section.[citation needed]
The power station will consist of nine Francis turbines with a capacity of 333 MW each. It will generate 17.6 TWh of electricity per year. Turbines are manufactured by Power Machines.[5] The power station is built by and will be owned and operated by JSC Boguchanskaya GES, a joint venture of RusHydro and Rusal.[11] The energy from the plant will be used, among others, by a large Boguchany Aluminium Smelter, which is to be launched in 2013.[citation needed]
Locale
Main facilities of the dam are located on the Angara river, in Kodinsk gorge, 444 km upstream from the river mouth, and are surrounded by taiga. The Angara flows in latitudinal direction here, cutting through Cambrian and Ordovician sedimentary massif interspersed with diabase intrusions. The valley's width barely exceeds 1 mile here, with rocky asymmetric bluffs overhanging the riverstream. The region is potentially seismic, with up to 7 degrees MSK-64 earthquake chance (1 in 5000 years possible recurrence).[citation needed]
As it reaches the dam, The Angara's river basin area accounts for 831,000 km3. The river's supply is greatly dependent on the lake Baikal and superincumbent reservoirs of Irkutsk, Bratsk and Ust-Ilimsk dams. The Angara's discharge amounts to 16,210 m³/s.[citation needed]
The climatic conditions in the vicinity may be described as continental. Summers are short and warm, whilst winters are prolonged and severe. Annual average temperature ranges between −2,6 to −4,3 °С, with the average July high of +18,5 °С and the average January low of −27,4 °С.[citation needed]
Navigation conditions improvement
In 2012, the present design of all dams on the Angara river doesn't allow passage of any ships. Additionally the river was not navigable within the section between Boguchany Dam and Ust-Ilimsk Dam. After its completion in 2012-2013 the reservoir of the Boguchany Dam will be 375 km (233 mi) long and will reach Ust-Ilimsk Dam upstream. It will flood the last section of the Angara channel, which was inaccessible for safe navigation because of shallow rapids in the river.[citation needed]
The downstream part of the river has a shallow channel too and stays unavailable for large seaworthy ships. According to various sources related to this subject, there are plans to build additional dams in the lower part of Angara river or, according to original soviet plans, to build one large hydro power plant in Yenisei River below its join with Angara. The latter variant presumes construction of the largest hydo power plant in Russia with an annual production of over 40 TWh.[citation needed]
Gallery
-
Rock-filled section of the dam in 2011
-
Upstream view in May 2011
-
Power station hall
-
One of intake flux control blades for water turbine
-
Rotor of one of nine generators
-
Surface spillway section
-
Penstocks spillway section
-
Downstream view of machine hall, May 2011
-
Mockup tests of the dam spillways
See also
Wikimedia Commons has media related to Boguchany hydroelectric power plant. |
- Bratsk Hydroelectric Power Station
- Irkutsk Hydroelectric Power Station
- Ust-Ilimsk Hydroelectric Power Station
- Boguchany Aluminium Smelter
References
- ↑ 1.0 1.1 (Russian) Готовность каменно-набросной плотины Богучанской ГЭС по укладке асфальтобетона к вводу первой очереди станции достигла 100 процентов, PJSC RusHydro, 2010/10/05
- ↑ "Богучанская ГЭС: Предварительная социальная и экологическая оценка в рамках подготовки банковского ТЭО" (in Russian). Центр по экологической оценке «Эколайн», Москва, 2006. Retrieved 2012-02-15.
- ↑ Kornysheva, Alena; Grib, Nataliya (2005-07-11). "Lords of the Stations". Kommersant. Retrieved 2009-08-20.
- ↑ "UC RUSAL and HYDROOGK Commence Work on New Aluminium Smelter". AZo Journal of Materials Online. 2007-05-15. Retrieved 2009-08-20.
- ↑ 5.0 5.1 "Power Machines pushes ahead with Boguchanskaya, La Yesca units". International Water Power and Dam Construction (Progressive Media Markets Ltd.). 2009-07-30. Retrieved 2009-08-20.
- ↑ "Power Machines Ships First Hydro Turbine for Installation at Boguchansk HPP". Datamonitor (RedOrbit, Inc.). 2008-08-19. Retrieved 2009-08-20.
- ↑ "Putin congratulates energy workers with inauguration of Boguchany HPP units". HydroWorld. 15 October 2012. Retrieved 20 October 2012.
- ↑
- ↑ "Rusal and RusHydro join forces in Boguchanskaya hydropower plant build". Industrial Fuels and Power. September 17, 2010. Retrieved 18 September 2010.
- ↑ (Russian) Каменно-набросная плотина Богучанской ГЭС построена до отметки 202 метра, RusCable.Ru: Отраслевые новости, 09.11.2011
- ↑ Vasilyeva, Nataliya (2009-08-19). "13 dead, 61 feared dead in Siberia plant explosion". Associated Press. Retrieved 2009-08-20.