Simplício Hydroelectric Complex

Simplício Hydroelectric Complex
Location of Simplício Hydroelectric Complex
Official name Hidrelétrico UHE Simplício
Country Brazil
Location Rio de Janeiro, Minas Gerais
Coordinates
Status Under construction
Construction began January 2007
Construction cost $1.2 billion USD
Owner(s) Eletrobrás Furnas
Constructor(s) Simplicio Construction Consortium (Odebrecht and Andrade Gutierrez)
Power generation information
Installed capacity 333.7 MW

The Simplício Hydroelectric Complex is an under construction hydroelectric complex on the Paraíba do Sul river on the border of Rio de Janeiro and Minas Gerais states in Brazil. Supported by the Anta Dam, it will transfer water throughout a 26 kilometres (16 mi) circuit to a downstream power plant. Under the supervision of Eletrobrás Furnas, the complex is under construction and will have a capacity of 333.7 MW when complete in 2011.

Contents

Background

Construction on the complex began in January 2007 after the Brazilian Institute of Environment and Renewable Natural Resources (IBAMA) issued an installation permit. One goal of the project is to reduce environmental impacts created by large reservoirs. The complex's five reservoirs will have a surface area of 15.36 square kilometres (6 sq mi).[1] On August 5, 2009, the river was diverted through the Anta Dam's spillway.[2] The rate progress is such that the completion of construction is on schedule for the planned inauguration at the end of August 2011. As of April, the complex is more than 90 percent complete.[3]

Operation

Water from the Paraíba do Sul is impounded at the 29.5 metres (97 ft) high and 260 metres (853 ft) long roller-compacted concrete Anta Dam before being diverting into a series of eight water channels, four water tunnels and five reservoirs totaling 26 kilometres (16 mi) in length. At the end of the circuit, the water is fed to a power station containing 3 x 101.3 MW Francis turbines. The Anta Dam itself supports a 28.8 MW power station with 2 x 14.4 MW Kaplan turbine-powered generators.[4]

The water diverted by the dam first enters channel C1 which is 1.9 kilometres (1 mi) long, 28 metres (92 ft) wide and 8 metres (26 ft) deep. After C1, the water moves into the 1,458 metres (4,783 ft) long tunnel T1 before entering the 1 kilometre (1 mi) long channel C2. After C2 and the use of a dike, the water forms the Tocaia reservoir before entering channel C3 which is 565 metres (1,854 ft) long. From C3, water is led into tunnel T2 and then to the 85 metres (279 ft) long channel C4 before reaching tunnel T2A. Water from T2A enters a valley and with the assistance of two dikes, creates Louriçal reservoir. From the reservoir, water enters channel C5 which directs it to the third Calçado reservoir which is partially created by the project's largest dike of 75 metres (246 ft) in height and 400 metres (1,312 ft) in length. The Calçado reservoir uses an outlet works to remove any excess water from the reservoir and help maintain appropriate levels.[4]

Water from the reservoir then moves into the 73 metres (240 ft) long channel C6 which feeds the project's longest tunnel, T3, at 6.03 kilometres (4 mi) in length. From T3, water moves into the Antonina reservoir before reaching the 203 metres (666 ft) long channel C7 and then into the Peixe reservoir which is created with the assistance of three dikes. After the reservoir, the water is transferred to intake channel C8 and from there into three 300 metres (984 ft) long penstocks which feed the Simplício Power Plant's three Francis turbines. The penstocks provide 80 metres (262 ft) of hydraulic head and are at a 12.48 percent angle. Once the water is discharged from the power station, it returns to the Paraíba via a 760 metres (2,493 ft) long tailrace channel.[4]

Popular culture

The project was featured on Build It Bigger during a season 8 episode.[5]

References