Bruce Nuclear Generating Station
Bruce Nuclear Generating Station |
Bruce B Nuclear Generating Station |
Location of Bruce Nuclear Generating Station
|
Country |
Canada |
Location |
Bruce County, Ontario |
Coordinates |
|
Status |
Operational |
Construction began |
1970–1987 |
Construction cost |
$14.4 billion CAD |
Owner(s) |
Ontario Power Generation (OPG) |
Operator(s) |
Bruce Power |
|
Reactor information |
Reactors operational |
6 reactors |
Reactor type(s) |
CANDU |
|
Power generation information |
Installed capacity |
6,232 MW |
Website
Bruce Power |
As of 2009-07-16 |
Bruce Nuclear Generating Station is a Canadian nuclear power station located on the eastern shore of Lake Huron, in the communities of Inverhuron and Tiverton, Ontario. It occupies 932 ha (2300 acres) of land.[1] The facility derives its name from Bruce County in which it is located, in the former Bruce Township. It is the second largest nuclear generating station in the world by net electrical power rating.
Formerly known as the Bruce Nuclear Power Development (BNPD),[1] the facility was constructed in stages between 1970 and 1987 by the provincial Crown corporation, Ontario Hydro. In April 1999 Ontario Hydro was split into 5 component Crown corporations with Ontario Power Generation (OPG) taking over all electrical generating stations. In June 2000, OPG entered into a long term lease agreement with private sector consortium Bruce Power to take over operation of the Bruce station. In May 2001, Bruce Power began operations. The lease is for 18 years (until 2019) with an option to extend a further 25 years (to 2044).[2]
The Bruce station is the largest nuclear facility in North America, and second largest in the world (after Kashiwazaki-Kariwa in Japan),[3][4] comprising 8 CANDU nuclear reactors having a total output of 6,232 MW (net) and 7,276 MW (gross) when all units are online. Current output with 6 of the 8 reactors on line is 4,640 MW. The Bruce station has two 500 kV transmission lines going out of it to feed the major load centres in southern Ontario, in addition to three 230 kV lines serving the local area.[5]
The station is the largest employer in Bruce county, with 3800 workers.
In November 2009, the Canadian Nuclear Safety Commission renewed Bruce Power’s operating licences for 5 years (until 2014), as well as giving permission to refuel units 1 and 2.[6]
Description
The 8 reactors are arranged into two plants (A and B) of 4 reactors. Each reactor is within a reinforced concrete containment, with eight steam generators. The steam generators are 12m tall, and weigh 100 tonnes each. Reactors share fueling machines which travel in a duct traversing the entire plant. The duct is cut through solid rock beneath the reactors, and doubles as part of the pressure relief system, connected to the vacuum building.[7] Each reactor has its own turbine generator set, with one high pressure turbine and 3 low pressure turbines driving one generator.[8][9] The turbine hall (about 400 m long) at each plant houses the four turbine generator sets. Cooling water is taken from Lake Huron.[2] There is (originally) one control room per 4 reactors.
Bruce A
- BRUCE A 1
- plant construction begins 1969 [8]
- construction of Bruce-1 begins June 1, 1971 (Bruce-2 work started first) [10]
- first criticality December 17, 1976 [10]
- in service September 1, 1977 (about 8 years to build)
- out of service December 1997 (after about 20 years);
- currently being refurbished (as of December 2010 idle 13 years)
- expected retirement 2043
- BRUCE A 2
- construction begins December 1, 1970 [10]
- first criticality July 27, 1976 [10]
- first electricity generated September 4, 1976 [10]
- in service September 1, 1977 [10]
- out of service October 1995 (after approx. 18 years)
- currently (Feb 2011) being refurbished, expected restart 2012
- expected retirement 2043
- BRUCE A 3
- construction start July 1, 1972 [10]
- in service 1978
- out of service April 1998
- returned to service March 2004
- limited to 92.5% of power [2]
- BRUCE A 4
- construction start September 1, 1972 [10]
- in service 1979
- out of service January 1998
- returned to service November 2003
Construction of Bruce A began in 1969, making it the successor to the Pickering A plant.
Bruce A units are rated at 750MW of electricity net, and 805MW gross.[11] Another source gives the figures of 769 MW and 825 MW.[2] Each reactor requires 6240 fuel bundles that weigh 22.5 kg each, or about 140 tonnes of fuel. There are 480 fuel channels per reactor, containing 13 bundles each. There is storage capacity for about 23000 bundles. About 16 bundles are discharged per reactor per day.
The Bruce A steam generators have a separate, horizontal steam drum (one steam drum common to four steam generators). This design had been dropped in most other plants at the time. Issues related to the (AECL requested) design of the tube supports caused repair and delay costs which exceeded the net worth of the builder Babcock & Wilcox Canada.[12]
Bruce A reactors uses unique booster rods to control reactivity. Booster rods contain 93% uranium-235, and are inserted to overcome xenon poisoning. Bruce B and all other Ontario Hydro reactors use absorber rods called adjusters that are normally in and are removed to overcome xenon poisoning.[13]
Bruce A demonstrated an "excellent" early operating history. Together with Pickering A, the eight units achieved an overall average capability factor of 83% over the initial five year period.[14] In 1982, Unit 3 set a (then) world record of 494 days of continuous operation. Bruce A was the most reliable multi-unit station in the world in 1984.[15]
In 1982 Bruce-2 was temporarily shutdown due to a pressure tube leak. In[10] 1986 a fuel channel failed in Bruce-2 while the reactor was shutdown. Some of the fuel elements were swept into the moderator (calandria) and were difficult to remove.[10][13] In 1986 maintenance workers accidentally left a protective lead blanket in the steam generator of Bruce A 2. By the time the mistake was discovered six years later, the blanket had melted, severely damaging the boiler.[15][16][17] In 1990 a software error caused a fueling machine error on Bruce-4, damaging a fuel channel.[10] In 1993, reactor power was reduced to 60% until various LOCA scenarios could be addressed. Subsequently Bruce A units returned to 89% of rated power.[10] At the time Bruce Power took the lease (2001), all Bruce A units were laid-up[2]
Bruce B
- BRUCE B 5
- in service 03/01/1985
- scheduled shutdown 2016[18]
- BRUCE B 6
- in service 09/14/1984
- scheduled shutdown 2018
- BRUCE B 7
- in service 04/10/1986
- scheduled shutdown 2015
- BRUCE B 8
- in service 05/22/1987
- scheduled shutdown 2019
The Bruce B plant stands somewhat to the south of the original Douglas Point and Bruce A plants. Construction began in 1977.[8]
Bruce B units are slightly larger capacity: 817 MW net, 840 MW gross. The slightly higher value is attributed to an improved steam generator design, where[19] the steam drum is integral to each steam generator in a "light bulb" arrangement, eliminating the horizontal cross-drum.[12]
With the completion of Bruce B in 1987, Bruce was the largest nuclear site in the world.[20]
In 2007 Bruce 7 was the top performing nuclear reactor in Ontario with 97.2% performance.[21] In 2009, Bruce 5 was first with 95.4% [20]
Electrical Output
By year, the station (A and B combined) produced the following amounts of electricity:
- 2001 20.5 terawatt hours (TWh);
- 2003 24.5 TWh;
- 2004 (planned) 34 TWh.[2]
- 2007 35.47 TWh
- 2008 35.26 TWh [22]
In 2006, OPA proposed increasing transmission line capacity from the plant, at a cost of between $200–600 million,[23] described as "the largest electricity transmission investment in Ontario in the last 20 years."[24]
In 2010, Bruce Power was paid approximately $60 million for contracted, but unused power.[25]
Comparison with Pickering
- Compared to the previous Pickering station, the Bruce reactors have higher power output, achieved by: increasing the number of fuel channels, increasing the number of bundles per channel, and a change in the fuel bundle itself.
- At Bruce, the fueling equipment is shared by the four reactors of each plant, while at Pickering each reactor has a fueling machine.
- Bruce has a second, fully independent Shutdown System (SDS2) which uses a liquid neutron poison injection method, whereas at Pickering the moderator water is dumped.
- The Bruce system also has a high-pressure Emergency Coolant Injection System (ECIS).[14]
- The design of the reactor buildings differs, Bruce uses a squarish "close-in" design, in which as much of the equipment as possible is arranged outside the main containment envelope for easier access during maintenance and emergencies.[13] The steam generators penetrate the containment.
- Each Bruce "4 pack" has its own Vacuum Building, while Pickering has one per eight reactors.
- At Pickering, the vacuum duct is closed by nonreturn valves, which would prevent flow of the steam/air mixture from the duct to a non-accident reactor unit following a LOCA. In the Bruce concept, there is no such non-return valve; the reactor buildings are all interconnected during normal operation.[13]
- Bruce uses single-circuit heat transport system, while Pickering has two circuits.[13]
- The first two reactor units of Pickering A originally used Zircaloy-2 pressure tubes. All subsequent CANDU units use a zirconium - 2.5% niobium alloy.[13]
- Bruce uses a pressuriser to maintain coolant pressure, Pickering a different system.
- The Pickering design utilizes 12 small steam generators operated in groups of three. Steam generators can be individually valved out of the heat transport loop, as can the pumps. There are 16 pumps per reactor, with 4 being spare. At Bruce, the number of steam generators and coolant pumps was reduced (to 8 and 4 respectively, there are no spare pumps), thereby simplifying the piping. The Bruce system permits reactor power level to be adjusted more quickly and easily.[13][26]
Construction Costs
Bruce A was projected to cost $0.9 billion (1969), and actually cost $1.8 billion (1978). Bruce B was projected to cost $3.9 billion (1976), and actually cost $6 billion (1989) in "dollars of the year".[18]
Blackout of 2003
During the Northeast Blackout of 2003 three Bruce B units were able to continue running at 60% reactor power and at 0% grid electrical power. They were able to do so for hours, because they had steam bypass systems that were designed to de-couple the reactor output from the generator electrical output.[27] The three units were reconnected to the grid within 5 hours.[10]
The Bruce A and B stations were designed to operate through grid disturbances and to operate for at least 6 hours disconnected from the grid. Bruce A subsequently lost this capability due to safety concerns with the booster rod system. "Contrary to popular belief, the electrical generators of nuclear plants can follow the load demands of the electrical grid provided specific engineered systems to permit this mode of operation are included in the plant design."[27]
Refurbishment
Retubing of Bruce A units was planned in 1992, although this was deferred, as Ontario Hydro had a surplus of generation at the time.[8]
In late 2005, Bruce Power and the Government of Ontario committed to return units 1 and 2 to service, in order to help meet increasing energy demand in the province of Ontario.[28] The project was originally estimated to cost $4.25 billion.[29] It was determined that while Units 1&2 could have been restarted without refurbishment, it was believed to be economical advantageous to do so, since refurbishment would have been required shortly thereafter.[2] The goal is to keep units 1&2 in service until 2043,[2] 66 years after original commissioning.
The refurbishment required:
- Pressure tube and calandria tube replacement
- Steam generator replacement
- Shutdown System 2 (SDS2) enhancement
- Significant other work and maintenance (for example, 30 transformers containing PCBs will be replaced).
A new fuel bundle design (Low Void Reactivity Fuel, LVRF) is being considered, which uses slightly enriched (1% U-235) fuel pellets, within a CANFLEX 43-element bundle (compared to the existing 37-element bundle).[2]
In 2006 and 2007, the restart project was judged to be the largest infrastructure project in Canada by ReNew Canada magazine.[30] Estimated cost for the project later grew to $5.25 billion when Bruce Power decided to replace all 480 fuel channels in Unit 4, which will extend its working life to 2036, in line with the other 3 units of Bruce A.[31] In 2008, due to difficulties developing the necessary robotics, the estimated cost of restarting Units 1 and 2 was raised between $400 and $700 million.[32] The project, however, remained on schedule.[33][34]
The auditor general reviewed the refurbishment deal in 2007[35]
In January 2010, up to 217 workers were potentially exposed to radiation during the refurbishment.[36] 27 workers may have received 5 mSv. Only one lab in Canada (at Chalk River ) was qualified to do the testing. Bruce Power had to seek permission to use alternative labs.[37][38]
In 2010, a plan to ship decommissioned, low-level radioactive steam generators to Sweden via the Great Lakes caused controversy.[39] The CNSC approved the plan in February 2011.[40]
In 2011, it was reported that Unit1 and 2 refurbishment, originally scheduled for 2009, is now predicted to be in commercial operation in 2012. Cost is $3.8 billion so far; the final cost is expected to be $4.8 billion. The original 2005 estimate was $2.75 billion.[41]
As of January 2011, fuel channel installation in Unit 2 was complete.[42]
New Station/Future Development
As part of a plan submitted to the Ontario Energy Board for approval, the Ontario Power Authority recommended building a new nuclear power station consisting of at least two reactors.[43] The leading candidate is AECL's Advanced CANDU Reactor.[44] Environmental assessments are currently underway both at Bruce and at Ontario Power Generation's Darlington Nuclear Generating Station.[45]
In 2009, Bruce Power withdrew its application to the Canadian Nuclear Safety Commission (CNSC) for the Bruce C plant[46][47][48]
Also On Site
There are more than 56 kilometres of roads on site, and at least 25 major structures. The site has its own fire department, laundry and medical centre.[8]
Douglas Point
Encompassed by the Bruce site is the shut-down Douglas Point reactor, an earlier version of the CANDU design. Construction began in 1960; was operational in 1967; and was shut down in 1984.[8] The present Bruce reactors each are roughly 4 times the capacity of the 200MW Douglas Point unit.
Bruce Heavy Water Plant (BHWP)
At one time the Bruce Heavy Water Plant (BHWP) also occupied the site. Atomic Energy of Canada Limited contracted the Lummus Company of Canada Limited in 1969 to design and construct the first phase of the plant, while Ontario Hydro was responsible for commissioning and operating.[49]
It was planned to consist of four sub-plants, A through D:
- A was in production in 1973, shutdown in 1984, and demolished in 1993;
- B was in production in 1979, partially shutdown in 1993, completely closed in 1997, and subsequently demolished;
- C was cancelled, and never built;
- D was 70% completed when cancelled, and subsequently demolished in 1995.
During its lifetime, BHWP produced 16,000 megagrams (Mg) of reactor grade heavy water. Capacity of each sub-plant was planned to be 800 Mg/annum. The plant size was approximately 960 m by 750 m.[1] The heavy water was 99.75% pure.[49] The production of a single pound of heavy water required 340,000 pounds of feed water.[50]
Bruce Bulk Steam System (BBSS)
Steam from Bruce A could be diverted to the bulk steam system to provide energy for the production of Heavy Water (750 MW thermal), to heat buildings within the development (15 MW th), or to provide energy (72 MW th) for the adjacent Bruce Energy Centre (BEC). The BEC supported industries such as greenhouses and plastic manufacturers. As one of the largest bulk steam systems in the world, this system could produce 5,350 MW of medium-pressure process steam, and had over 6 km of piping. It was demolished by the end of 2006. Because of the requirement to provide steam, the Bruce A turbines are undersized relative to the reactor power.[19][51][52][53][54]
Waste Storage
The Bruce station area is also the site of OPG's Western Waste Management Facility (WWMF). The WWMF stores all the low and intermediate level nuclear waste from the operation of OPG's 20 nuclear reactors, including those leased to Bruce Power. As of 2009, there are 11 Low level storage buildings.[55] OPG has proposed a deep geologic repository (DGR) for the long-term management of this low-and-intermediate level waste, to be constructed on lands adjacent to WWMF. The proposed DGR would be about 680 metres below surface.[56]
In addition, the WWMF provides dry fuel storage for the Bruce reactors. The Nuclear Waste Management Organization is presently seeking a separate site in Canada for a permanent repository for the used fuel from all of Canada's nuclear reactors.
Inverhuron Provincial Park
While not part of the Bruce site proper, the nearby Inverhuron Provincial Park is owned by OPG and is on lease to the Ontario Ministry of Natural Resources. As a condition of the operating licence for Bruce Nuclear, OPG has retained a 914 m radius exclusion zone in the northwest corner of the park. The former park campground was phased out in 1976 because of safety concerns related to the manufacturing of heavy water. Since heavy water is no longer produced, the park campground was allowed to re-open.[57]
Security
In 1977 three Greenpeace activists canoed into the site to demonstrate the lack of security.[58][59]
On Sept. 23, 2001, a man whose boat capsized on Lake Huron near the Bruce complex squeezed through a gate, entered an office building and phoned for help—all undetected.[60][61]
The pre-9/11 mandate of the security team was to delay attackers for 17 minutes, until local police could respond. Reliance was on passive measures such as fencing and locks.
The "transformed" post 9/11 security team is described as being larger than the police force of the city of Kingston, i.e. equivalent to the force of a city of 100,000. Force members are permitted to carry firearms, and have powers of arrest. The force possesses armoured vehicles, water craft, and the plant is now triple-fenced.[62] In May 2008, the Bruce Nuclear Response Team (NRT) won the U.S. National SWAT Championship (USNSC), defeating 29 other teams from 4 countries, the first time a Canadian team won an international SWAT event. They won again in 2009, 2010, and 2011.[63][64][65][66] [67][68]
In 2010, about 40 contract workers were fired for inappropriate internet usage, raising questions about the security of the plant.[69][70]
Post 9/11, tours of the plant area were discontinued, although there is a visitor center outside of the site.[8]
According to the Bruce County emergency plan, "The Municipality of Kincardine will coordinate the emergency response concerns of a nuclear emergency situation resulting from an accident at the Bruce Power Site in the Municipality of Kincardine.".[71] Kincardine is required to maintain a warning system within 3 km of the plant, and has a network of 10 warning stations equipped with sirens and strobes.[72]
A variety of radiation monitoring measures are in place. Milk samples from local farms are sampled weekly. Drinking water at treatment plants in Kincardine and Southhampton is sampled twice daily, and tested weekly. Ground water is sampled from several surface water, shallow and deep well locations. Aquatic sediment and fish are analysed, as well as livestock feed, honey, eggs, fruits and vegetables.[73]
See also
References
- ^ a b c "Global Security Article". http://www.globalsecurity.org/wmd/library/news/canada/01_e.pdf. Retrieved March 22, 2011.
- ^ a b c d e f g h i "Bruce A Refurbishment". Bruce Power (Golder Associates). December 2004 (revision 1). http://www.brucepower.com/uc/GetDocument.aspx?docid=2161. Retrieved March 22, 2011.
- ^ "The World's Largest Power Plants". http://www.industcards.com/top-100-pt-1.htm. Retrieved 26 March 2011.
- ^ "Nuclear Power in Canada". Canadian Nuclear Association. 2010. http://www.cna.ca/curriculum/cna_can_nuc_hist/nuclear_canada-eng.asp?bc=Nuclear%20Power%20in%20Canada&pid=Nuclear%20Power%20in%20Canada. Retrieved 27 March 2011.
- ^ "The Need for More Transmission in Bruce Region". Ontario Power Authority. http://www.powerauthority.on.ca/Page.asp?PageID=122&ContentID=5363&SiteNodeID=305&BL_ExpandID=. Retrieved 2008-04-18.
- ^ http://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news/archive/2009/11/05/bruce-power-gets-five_2d00_year-operating-licenses-11056.aspx
- ^ http://www.sciencedirect.com/science?_ob=ArticleURL&_udi=B6V4D-4810WF5-DR&_user=10&_coverDate=02%2F02%2F1987&_rdoc=1&_fmt=high&_orig=gateway&_origin=gateway&_sort=d&_docanchor=&view=c&_searchStrId=1687965619&_rerunOrigin=google&_acct=C000050221&_version=1&_urlVersion=0&_userid=10&md5=9c606e4251ff4243322088b918d20828&searchtype=a
- ^ a b c d e f g "Reporter's Guide to Bruce Power". Aug 2007 (R004). http://www.brucepower.com/docs/reports/corporate/A%20Reporters%20Guide%20to%20Bruce%20Power.pdf. Retrieved 24 March 2011.
- ^ http://www.brucepower.com/uc/GetDocument.aspx?docid=2161http://www.brucepower.com/uc/GetDocument.aspx?docid=2161
- ^ a b c d e f g h i j k l m Morgan Brown (updated November 25, 2009). "Canada's Nuclear History Chronology". Canadian Nuclear Society. http://media.cns-snc.ca/history/canadian_nuclear_history.html#1970. Retrieved 31 March 2011.
- ^ http://www.candu.org/brucepower.html
- ^ a b John M. Dyke and Wm. J. Garland (2006-05-19). "Evolution of CANDU Steam Generators – a Historical View". Canteach. http://canteach.candu.org/library/20060101.pdf. Retrieved 26 March 2011.
- ^ a b c d e f g Ontario Nuclear Safety Review (29 February, 198). "The Safety of Ontario's Nuclear Power Reactors (Vol 2 Appendices)". Toronto, Ontario. http://www.iaea.org/inis/collection/NCLCollectionStore/_Public/23/075/23075997.pdf. Retrieved 31 March 2011.
- ^ a b Gord L. Brooks (Revision 2, December 2002). "A Short History of the CANDU Nuclear Power System". Canteach. http://canteach.candu.org/library/19930101.pdf. Retrieved 25 March 2011.
- ^ a b "Bruce A Proves There Are Second Acts in Nuclear Power". Power Magazine. August 1, 2010. http://www.powermag.com/business/Bruce-A-Proves-There-Are-Second-Acts-in-Nuclear-Power_2879.html. Retrieved 27 March 2011.
- ^ "CANDU Flawed". The Canadian Encyclopedia. http://www.thecanadianencyclopedia.com/index.cfm?PgNm=TCE&Params=M1ARTM0011389. Retrieved 26 March 2011.
- ^ Keith Stewart (March 24, 2011). "The Billion Dollar "oops" at the Bruce Nuclear Station". Greenpeace. http://www.greenpeace.org/canada/en/Blog/the-billion-dollar-oops-at-the-bruce-nuclear-/blog/33932. Retrieved 27 March 2011.
- ^ a b "Better Never Than Late". Greenpeace. October 2008. http://www.greenpeace.org/canada/Global/canada/report/2008/11/better-never-than-late.pdf. Retrieved 4 April 2011.
- ^ a b "Bruce Power: Site History". Canadian Nuclear Workers' Council (CNWC). 2009. http://www.cnwc-cctn.ca/bruce-power-site-history/. Retrieved 27 March 2011.
- ^ a b "CNA Nuclear Energy Booklet 2010". Canadian Nuclear Association. 2010. http://www.cna.ca/english/pdf/nuclearfacts/2010/CNA_Booklet_2010.pdf. Retrieved 27 March 2011.
- ^ "CNA Nuclear Energy Booklet 2008". Canadian Nuclear Association. http://www.cna.ca/english/pdf/nuclearfacts/2008/CNA_Nuclear_Energy_Booklet08.pdf. Retrieved 27 March 2011.
- ^ http://www.brucepower.com/uc/GetDocument.aspx?docid=2861
- ^ http://www.cleanairalliance.org/resource/fs23.pdf
- ^ "Ontario’s Long-Term Energy Plan". OPA. 2010. http://www.powerauthority.on.ca/sites/default/files/page/Building_our_Clean_Energy_Future.pdf. Retrieved 26 March 2011.
- ^ "Bruce Power got millions to not produce electricity". CTV News. 2010-09-21. http://toronto.ctv.ca/servlet/an/local/CTVNews/20100921/ontario-electricity-bruce-power-100921/20100921/?hub=TorontoNewHome. Retrieved March 22, 2011.
- ^ Atomic Energy of Canada Limited (1997). Canada enters the nuclear age. ISBN 0-7735-1601-8.
- ^ a b "Ontario Electrical Grid and Project Requirements for Nuclear Plants". Ontario Society of Professional Engineers (OSPE). March 8, 2011. http://www.ospe.on.ca/pdf/03-08-2011%20Ontario%20Electrical%20Grid%20Submission.pdf. Retrieved 4 April 2011.
- ^ "Government and Bruce Power Reach Agreement to Restart Nuclear Units". Queen's Park, Ontario: Canadian Ministry of Energy. 2005-10-17. http://ogov.newswire.ca/ontario/GPOE/2005/10/17/c1757.html?lang=_e.html. Retrieved 2008-04-18.
- ^ "TransCanada to Invest in $4.25 Billion Bruce Power Restart and Increase Its Interest in Bruce A". Calgary, Alberta: Marketwire. 2005-10-17. http://www.transcanada.com/news/2005_news/2005_10_17.html. Retrieved 2008-04-18.
- ^ "ReNew Canada - The Top 100". Archived from the original on 2008-03-21. http://web.archive.org/web/20080321085953/http://www.top100projects.ca/index/view.html. Retrieved 2008-04-18.
- ^ "TransCanada Announces Expanded Unit 4 Refurbishment on Bruce A Restart Project". Calgary, Alberta: Marketwire. 2007-08-29. http://biz.yahoo.com/iw/070829/0296204.html. Retrieved 2008-04-18.
- ^ Tyler Hamilton (2008-04-18). "Reactor repairs confirmed over budget". The Toronto Star. http://www.thestar.com/article/415772. Retrieved 2008-04-18.
- ^ "Bruce Power two-unit restart cost estimate rises to between $3.1 B and $3.4 B". Toronto, Ontario: The Canadian Press. 2008-04-17. http://canadianpress.google.com/article/ALeqM5gIasEEKZ6vUcQqLYp38liK7r1uAg. Retrieved 2008-04-18.
- ^ "TransCanada Provides Update on Bruce A Units 1 and 2 Restart Project". Calgary, Alberta: Marketwire. 2008-04-17. http://www.msnbc.msn.com/id/24180619/. Retrieved 2008-04-18.
- ^ Office of the Auditor General of Ontario (April 5, 2007). "The Bruce Power Refurb shment Agreement". http://www.auditor.on.ca/en/reports_en/brucespecial_en.pdf. Retrieved 27 March 2011.
- ^ http://www.scribd.com/doc/26960282/Bruce-Power
- ^ http://www.brucepower.com/uc/GetDocument.aspx?docid=2974
- ^ "Bruce Nuclear radiation incident shows safety gap". CTV News. February 18, 2010. http://regina.ctv.ca/servlet/an/local/CTVNews/20100218/nuke_leak_100118?hub=TorontoNewHome. Retrieved 24 March 2011.
- ^ Popplewell, Brett (11 July 2010). "Critics slam proposal to ship nuclear waste through Lake Ontario". The Star (Toronto). http://www.thestar.com/news/ontario/article/834724--critics-slam-proposal-to-ship-nuclear-waste-through-lake-ontario.
- ^ "Bruce Power granted licence to transport steam generators". Feb. 4, 2011. http://www.brucepower.com/pagecontent.aspx?navuid=1212&dtuid=84366. Retrieved 26 March 2011.
- ^ http://www.globalnews.ca/story.html?id=3873817
- ^ http://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news/archive/2011/01/26/bruce-power-_1320_-bruce-a-unit-2-completes-installation-of-480-new-fuel-channels.aspx
- ^ "Power plan calls for Ontario to spend $26.5B on nuclear plants". CBC News. 2007-08-29. http://www.cbc.ca/money/story/2007/08/29/ontario-nuclear.html. Retrieved 2008-04-18.
- ^ David Olive (2008-04-14). "Queen's Park prepares for 'power' play". Toronto Star. http://www.thestar.com/article/414160. Retrieved 2008-04-18.
- ^ Tyler Hamilton (2008-04-08). "GE-Hitachi won't bid for reactor". Toronto Star. http://www.thestar.com/article/412700. Retrieved 2008-04-18. "The government plans to pick a winning technology by the end of the year. It also will decide by that time whether the plant will be located in Clarington or Bruce County, and whether the plant's operator will be Ontario Power Generation or Bruce Power."
- ^ Frank Saunders (July 23, 2009). "Withdrawal of Application... [Letter"]. CNSC. http://nuclearsafety.gc.ca/eng/readingroom/newbuilds/withdrawnapplications/bruce_tiverton/docs/Bruce_Power_Withdrawl.pdf. Retrieved 26 March 2011.
- ^ http://nuclearsafety.gc.ca/eng/readingroom/newbuilds/withdrawnapplications/bruce_tiverton/index.cfm?CFID=10348917&CFTOKEN=82fca0fc197db7bb-CA2E1458-3048-9B41-F4EBD169CDED40AB&jsessionid=c6308b930954f6c3efb050702266671c1c39
- ^ http://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news/archive/2009/07/24/bruce-power-will-focus-on-additional-refurbishments-at-bruce-a-and-bruce-b-1014.aspx
- ^ a b "Abstract for "Separation of Hydrogen Isotopes"". American Chemical Society. http://pubs.acs.org/doi/pdfplus/10.1021/bk-1978-0068.ch002. Retrieved 27 March 2011.
- ^ "Heavy Water Production". Federation of American Scientists. http://www.fas.org/nuke/intro/nuke/heavy.htm. Retrieved 27 March 2011.
- ^ "Nuclear heat applications: World overview". IAEA. http://www.iaea.org/Publications/Magazines/Bulletin/Bull264/26404781821.pdf. Retrieved 27 March 2011.
- ^ "Introduction to CANDU processes". http://canteach.candu.org/library/20042624.pdf. Retrieved 27 March 2011.
- ^ Jürgen Kupitz (March–April 2000). "Small and Medium Reactors: Development Status and Application Aspects". IAEA. http://www.iaea.org/inis/collection/NCLCollectionStore/_Public/38/027/38027904.pdf. Retrieved 27 March 2011.
- ^ Meridian Planning Consultants (June 2005). "Bruce Energy Centre Discussion Paper". Municipality of Kincardin.
- ^ http://www.opg.com/power/nuclear/waste/pdf/WasteBrochure11.pdf
- ^ http://www.opg.com/dgr
- ^ "Inverhuron Draft Vegetation Management Pla". Ontario Ministry Natural Resources (OMNR). 2007. http://www.ontla.on.ca/library/repository/mon/17000/272597.pdf. Retrieved 4 April 2011.
- ^ http://www.sierraclub.ca/en/users/john-bennett
- ^ http://www.digitaltermpapers.com/c7551.htm
- ^ Tony Manolatos (2002-07-24). "Nuke foes fight expansion of Canadian plant". The Detroit News. http://www.friendsofbruce.ca/DetroitPressNucWaste.pdf. Retrieved 4 April 2011.
- ^ "Ontario Hansard - 10-October2001". 10-October2001. http://hansardindex.ontla.on.ca/hansardECAT/37-2/L048A-4.htm. Retrieved 4 April 2011.
- ^ http://forums.blueline.ca/viewtopic.php?f=28&t=9535&start=15
- ^ http://www.98thebeach.ca/news_item.php?NewsID=3911
- ^ http://www.brucepower.com/pagecontent.aspx?navuid=1212&dtuid=84008
- ^ http://www.nuclearsafety.gc.ca/eng/pdfs/LETTER_FROM_PM_AUG_2008.pdf
- ^ "US National SWAT Championship". http://www.nationalswatchampionships.com/results.php. Retrieved 24 March 2011.
- ^ "US National SWAT Championship". http://www.brucepower.com/4762/news/bruce-power-team-wins-u-s-national-swat-championship-2/. Retrieved 7 November 2011.
- ^ "Nanticoke Nuclear Power Plant Project Environmental Assessment Fact Sheet 6: Security and Safety". Bruce Power. November 2008. http://www.brucepower.com/docs/reports/corporate/Nanticoke%20Fact%20Sheets.pdf. Retrieved 4 April 2011.
- ^ http://www.thepeterboroughexaminer.com/ArticleDisplay.aspx?archive=true&e=1748848
- ^ Hamilton, Tyler (Sep 10 2009). "Dozens fired at Bruce Power over Web, e-mail use". The Toronto Star. http://www.thestar.com/News/Canada/article/693525. Retrieved 24 March 2011.
- ^ "COUNTY OF BRUCE EMERGENCY RESPONSE PLAN". 2004. p. 1.2.3. http://www.brucecounty.on.ca/download_file2.php?uid=187. Retrieved 24 March 2011.
- ^ "Municipality of Kincardine Public Alerting System". http://kincardine.net/public_docs/documents/Inverhuron%20Park%20siren%20info%202005%20-%20web%20info1.pdf. Retrieved 25 March 2011.
- ^ "Annual Summary & Assessment of Environmental Radiological Data for 2009". Bruce Power. April 30, 2010. http://www.brucepower.com/uc/GetDocument.aspx?docid=3106. Retrieved 26 March 2011.
External links
|
|