Brenner Railway

The Brenner Railway is a major line connecting the Austrian and Italian railways from Innsbruck and Verona climbing the Wipptal (German for “Wipp Valley”), passing over the Brenner Pass and descending down the Eisack Valley to Bolzano and then down the Adige Valley from Bolzano to Rovereto and from there along the section of the Adige valley called in Italian the “Vallagarina” to Verona. The line is part of the Line 1 of Trans-European Transport Networks (TEN-T). It is considered a "fundamental" line by the state railways Ferrovie dello Stato (FS).[1]

Contents

History

The line was designed under the Austro-Hungarian Empire before the middle of the nineteenth century to ensure rapid and safe transport between Tyrol and Northern Italy, especially Lombardy–Venetia. It was thus important not only for economic but also for military reasons as Austria was strongly committed to maintaining its borders south of the Alps.

The first section to be built was that low section between Verona to Bolzano, which was opened in two different parts: 23 March 1859 from Verona to Trento and 16 May 1859 from Trento to Bolzano. This work was commenced by the k.k. Nord- und SüdTiroler Staatsbahn (German: "North and South Tyrol State Railways") but at the beginning of 1859 the company was taken over by the new Austrian Southern Railway (German: Südbahn).[2]

The design of this section was approved on 10 July 1853 by the engineer Alois Negrelli, an employee of the Südbahn, known for having built other alpine lines and for developing a project for the Suez Canal.

Despite the loss of Veneto in the Third Italian War of Independence and the consequent shift of the border between Italy and Austria to Borghetto on the current boundary of Trentino and Verona, which occurred in October 1866, the section from Bolzano to Innsbruck was incomplete, but already under construction and it was opened on 24 August 1867. The 127 km route from Innsbruck to Bolzano took only three years to build. The main designer was the engineer, Karl von Etzel, who died in 1864 and therefore did not see the completion of his work. After the Semmering railway it was the second mountain railway built in Austria. It was also the first line to cross completely over the Alps.

The line south of Borghetto became part of the Società per le strade ferrate dell'Alta Italia (Italian for Upper Italian Railways, SFAI) in 1866[3] and in the 1885 reorganisation it was absorbed by the Società per le Strade Ferrate Meridionali (Adriatic Network).[4] The line became part of Ferrovie dello Stato upon its establishment in 1905.

In 1919 Italy acquired Trentino-South Tyrol under the Treaty of Saint-Germain-en-Laye and the border moved to Brenner. The line from Trento to Brenner was electrified at 3,700 V at three-phase 16.7 Hz between 1929 and 1934.[5] Electrification was converted to 3,000 V DC on 30 May 1965.

In preparation for the proposed Brenner Base Tunnel, the Innsbruck bypass was completed in 1994 to improve access to the Lower Inn Valley railway. The bypass consists of a 12.75 kilometre tunnel (Austria's longest), which removed the bulk of the freight trains from Innsbruck. In Italy several new sections have been built, removing sections of line with several short tunnels with small cross sections. These include the 13.159 metre-long Sciliar tunnel opened in 1994, the 7.267 m-long Pflersch tunnel opened in 1999 and the 3,939 m-long Cardano tunnel opened in 1998.

Brenner railway
Legend
from Kufstein
75.130 Innsbruck  S1   S2   S3   S4   S5  582 metres m AMSL
Arlberg and Mittenwald railways
76.725 Bergisel tunnel 662m
78.198 Sonnenburg tunnel 249m
79.646 Innsbruck bypass
80.291 Ahrnwald tunnel 165m
80.809 Schupfen tunnel 35m
81.295 Unterberg-Stefansbrücke  S3   S4  716 m AMSL
81.648 Unterberg tunnel 49m
82.662 Patsch tunnel 176m
83.905 Innsbruck Hbf 2 crossover
84.718 Patsch  S3   S4  784 m AMSL
85.403 Schönberg tunnel 89m
85.726 Mühltal tunnel 872m
86.936 Moserwiese tunnel 74m
91.847 Matrei tunnel 124m
93.281 Matrei am Brenner  S3   S4  995 m AMSL
97.884 Steinach am Brenner  S3   S4  1084 m AMSL
101.918 St. Jodok  S4  1141 m AMSL
102.427 Sankt Jodok spiral tunnel 480m
104.323 Stafflach tunnel 283m
106.189 Gries tunnel 173m
106.651 Gries am Brenner  S4  1255 m AMSL
106.917 Steinach in T. 2 crossover
111.375 Brennersee 1351 m AMSL
111,663
240,083
Brennero/Brenner  S4  Border
236.2 Brennerbad (former spa) 1371 m AMSL
13.1 Moncucco/Schelleberg 1242 m AMSL
Pflersch tunnel 7.267m
Ast spiral tunnel 761m
226.7 Fleres/Pflersch 1130 m AMSL
222.8 Colle Isarco/Gossensaß 1100 m AMSL
Eisack bridge I 1 span
217.0 Vipiteno/Sterzing 943 m AMSL
Campo di Trens/Freienfeld 935 m AMSL
Palude di Vipiteno bridge 3 spans
208.9 Mules/Mauls 900 m AMSL
204.3 Le Cave/Grasstein 843 m AMSL
200.8 Mezzaselva/Mittewald 798 m AMSL
197.0 Fortezza/Franzensfeste 747 m AMSL
197.0 Puster Valley railway (S.Candido/Innichen)
192.19 Varna/Vahrn 650 m AMSL
188.36 Bressanone/Brixen 577 m AMSL
Eisack bridge II 2 spans
184.70 Albès/Albeins 548 m AMSL
Funes/Villnöß 539 m AMSL
178.24 Chiusa/Klausen Grödner railway 523 m AMSL
172.43 Ponte Gardena/Waidbruck 422 m AMSL
Rötele bridge 1 span
Castelrotto/Kastelruth/ 428 m AMSL
Schlern tunnel 13.159 m
Campodazzo/Atzwang 373 m AMSL
Eisack bridge I 2 spans
Tunnel VII 55m
Tunnel VI 72m
Tunnel V 60m
Tunnel IV 62m
Tunnel III 79m
Tunnel II 57m
Völsersteig/ Fiè allo Sciliar 340 m AMSL
Tunnel I 40m
157.99 Prato all'Isarco/Blumau 315 m AMSL
Kardaun tunnel 3.789m
Prato Tires tunnel 430m
Cardano/Kardaun 283 m AMSL
Kardaun bridge 1 span
150.23 Bolzano/Bozen 266 m AMSL
Überetsch Railway
148.59 To Merano
142.56 Laives/Leifers 230 m AMSL
139.29 Bronzolo/Branzoll 227 m AMSL
134.17 Ora/Auer 223 m AMSL
128.40 Egna/Neumarkt 217 m AMSL
124.42 Magrè/MargreidCortaccia/Kurtatsch 216 m AMSL
118.99 Salorno/Salurn 211 m AMSL
111.62 Mezzocorona
110.50 Trento-Malè railway
104.32 Lavis
95.43 Trento goods station
94.79 Trento
93.01 To Venice
87.22 Mattarello
78.91 Calliano, closed 12.12.2004
71.21 Rovereto
66.91 Mori Rovereto-Arco-Riva railway
60.86 Serravalle
54.68 Ala
50.36 Avio
45.48 Borghetto
40.36 Peri
32.77 Dolcè
22.80 Domegliara–S.Ambrogio
16.98 Pescantina
11.65 Verona Parona
6.39 S.Massimo junction/P.C.[6] to Milan and Bologna
Adige river
3.37 Verona Porta Nuova
0.00 Verona Porta Vescovo
To Venice

Future

Following a sharp increase in freight through the Brenner Pass (largely on road), the railway is currently considered to have insufficient capacity. Moreover, its steep grades, tight radius bends and the need to change the engines at Brenner because of two different electrical systems used in Austria and Italy mean that the average travel speed is low. For these reasons, the creation of a new line is planned from Verona to Munich via Innsbruck. At the heart of this project is a 55 kilometre-long tunnel between Franzensfeste and Innsbruck, known as the Brenner Base Tunnel.

Route

The maximum grade on the track is 31 per thousand. The minimum curve radius is 264 metres. The highest point of the track is Brenner station at 1,371 m, which is also the highest point reached on the standard gauge networks of the Austrian Federal Railways (ÖBB) and the Italian Ferrovie dello Stato (FS) networks.

To overcome the steep climb (796 m between Innsbruck and Brenner) two spiral tunnels were built, using the sides of a valleysat St. Jodok on the Austrian side and the sides of the Pflerschtal (German for "Pflersch Valley") on the Italian side.

At Brenner station, located on the Brenner Pass, there is a monument to the designer, Karl von Etzel. At this station, in addition to the political boundary is found the operational border between the ÖBB and FS networks. The two companies operate different electrical systems, (15,000 V AC at 16.7 Hz in Austria, and 3,000 V DC in Italy), which requires a stop to change electric locomotives. For this reason, for a long time the operation of express trains from Munich to Milan was carried out with diesel railcars. Until 30 May 1965 was also needed a second engine change in Bolzano station, as the Bolzano–Brenner section still operated under three-phase AC electrification.

In recent years the introduction of multicurrent rolling stock that can run on both the Austrian and Italian networks has made it possible, at least in principle, to avoid locomotive changes. However, the need for locomotives to carry equipment for different signalling systems and to have safety approvals for different networks and lines and the need for staff to know operating rules and routes has limited multicurrent operations in practice.

Notes

  1. ^ Ferrovie dello Stato
  2. ^ Kalla-Bishop 1971, p. 21
  3. ^ Kalla-Bishop 1971, p. 41
  4. ^ Kalla-Bishop 1971, p. 52
  5. ^ Kalla-Bishop 1971, p. 103
  6. ^ "Posti di comunicazione", that is a crossover.

References