Tunnel and Reservoir Plan

From Wikipedia, the free encyclopedia

The Tunnel and Reservoir Plan (abbreviated TARP and more commonly known as the Deep Tunnel Project or the Chicago Deep Tunnel) is a large civil engineering project that aims to reduce flooding in the metropolitan Chicago area, and to reduce the harmful effects of flushing raw sewage into Lake Michigan by diverting storm water and sewage into temporary holding reservoirs. The megaproject is one of the largest civil engineering projects ever undertaken in terms of scope, cost and timeframe. Commissioned in the mid-1970s, the project is managed by the Metropolitan Water Reclamation District of Greater Chicago. Full completion of the system is not anticipated until 2019, but substantial portions of the system have already opened and are currently operational. Across 30 years of construction, over $3 billion has been spent on the project.[1]

Contents

[edit] History

[edit] 1800s

The Deep Tunnel Project is the latest in a series of civil engineering projects dating back to 1834. Much of the problems experienced by the city of Chicago are directly related to its topography and the fact that city is largely built upon a marsh. The Chicago River was ineffective in carrying sewage away from the city; when it did, the earliest water pumps in Lake Michigan that provided drinking water to Chicagoans became clogged with sewage. These conditions led to frequent cholera epidemics in the 19th and early 20th centuries.[2]

In 1871, the Illinois and Michigan Canal was built, diverting some sewage water from the Chicago River. In 1900, to improve general health standards, the flow of the main branch of the Chicago River was reversed to drain water from Lake Michigan, as opposed to having the river flow into Lake Michigan. This further improved the sanitation of Lake Michigan, and helped to prevent further cholera epidemics.

[edit] 1900s

The construction of the Sanitary and Ship Canal (1892–1900), enlargements to the North Shore Channel (1907–1910), the construction of the Cal-Sag Channel (1911–1922) and the construction of locks at the mouth of the Chicago River (1933–1938) brought further improvements to the sanitary issues of the time. These projects blocked further amounts of sewage from draining into Lake Michigan. The projects also brought fresh lake water to inland waterways to further dilute sewage that was already in the waterways.

Surrounding farmland also engaged in flood control projects. The Illinois Farm Drainage Act of 1879 established drainage districts. These districts were generally named for the basin they drained — for example, the Fox River Drainage District. After World War II, suburban communities began to realize the benefits of separating stormwater from sewage water and began to construct separate sewer and storm drainage lines. The primary benefit of wastestream separation is that storm water requires less treatment than sewage before being returned to the environment.

Flood damage grew markedly after 1948, when surrounding drainage areas were lost to development and human activity. Serious flooding has occurred in the Chicago metropolitan area in the years 1849, 1855, 1885, 1938, 1952, 1954, 1957, 1961, 1973, 1979, 1986, 1987, and 1996 — but most record-setting crests have been set after 1948.

In the 1960s, the concept of Deep Tunnel was studied and recommended as a solution to continuing flooding issues. The Deep Tunnel system would be built as a network of 109.4 miles (176 km) of tunnels of varying width.

[edit] Current status

As of October 2005, substantial drilling and blasting for the underground tunnels was complete. Reservoirs are scheduled to become operational and hold and process sewage, notably in McCook (2013 and 2019) and Thornton (2014). Currently, water travels to the Thornton Transitional Reservoir, which will be abandoned in 2014. Water is also stored and held in the tunnels themselves while sewage treatment plants release treated water into the Calumet and Des Plaines Rivers.

Mining work was completed on the Little Calumet leg of the Deep Tunnel System, and final connections were scheduled for completion on March 1, 2006. The Little Calumet leg is 7.9 miles (12.7 km) in length. Operation of the Little Calumet leg will mark the total completion of all 109.4 miles (176.1 km) of tunnel included under Phase I of the TARP project, and the culmination of 30 years of tunnel construction.

[edit] Effects

Severe weather events as recent as the early 1990s have forced water management agencies to pump excess wastewater into the lake and river in order to prevent flooding. These incidents have been reduced as more of the Deep Tunnel system has become operational. Long considered an open sewer, the Chicago River now hosts more than 50 species of fish and increased wildlife along its shores. Riverfront property has begun to be classified more as an asset than a liability, and substantial development is occurring along many portions. Canoeing is once again allowed on the waterway, but swimming is still prohibited due to high pollution levels.

On October 31986, a heavy thunderstorm drenched the southern portion of the Deep Tunnel area with several inches of rain in short period of time. While the Deep Tunnel system performed satisfactorily by absorbing excess water, water within the system itself rushed north to North Chicago and near the Bahá'í Temple in Wilmette. Geysers of over 65 feet (20 m) were reported in both locations for up to an hour as the water was redistributed more evenly through the system. A 30 ft (9 m) geyser erupted downtown at the corner of Jackson and Monroe.[3] A system of watertight bulkheads has since been installed to prevent the event from occurring again.

During the Chicago Flood of 1992, the water from the Chicago River that leaked into the then-forgotten underground freight tunnel system was eventually drained into the Deep Tunnel network, which itself was still under construction.

[edit] See also

[edit] Sources

[edit] References

  1. ^ Sanders, Steve (2005-10-10). WGN-TV CoverStories: Deep Tunnel. WGN-TV. Retrieved on 2005-12-23.
  2. ^ Juhl, Arland R. (2004). Flood Control and Drainage. Encyclopedia of Chicago. Retrieved on 2005-12-23.
  3. ^ Karwath, Rob. "Tunnel's Geyser Effect Still Puzzling", Chicago Tribune, 1986-10-17. Retrieved on 2008-04-23. 

[edit] External links