There have been a number of proposals to build a Taupo Line as a branch railway linking the township of Taupo in the central North Island of New Zealand to New Zealand's rail network. One proposal proceeded as far as the construction stage before being stopped.

Contents

[edit] Background

By 1952, nearly every main centre in New Zealand was served by a railway, the exceptions being Kaitaia, Queenstown and Taupo. Taupo is one of New Zealand's biggest forestry centres and is a very popular tourist destination.

[edit] Proposed routes

[edit] North Island Main Trunk line

The first time that consideration was made to link Taupo with a railway was in 1884 when routes for extending the North Island Main Trunk (NIMT) railway south from Te Awamutu to Wellington were being explored and surveyed. One of the proposed routes was from just south of Te Awamutu following the course of the Puniu River inland through to Taupo, and onwards east to link at Hastings with the proposed Palmerston North - Gisborne Line. This route did not eventuate and the present route via Taumarunui was chosen.

[edit] Taupo Totara Timber Company line

In 1903 the Taupo Totara Timber Company (TTT Co) constructed an 82km tramway to link their milling centre at Mokai with the New Zealand Government Railways line (NZR) at Putaruru. The line was built over the former NZR Lichfield Branch line, which was originally built by the Thames Valley and Rotorua Railway Company to be part of the line to Rotorua. The TTT Co line then went onwards south of Lichfield through what are now Tokoroa and Kinleith and crossed the Waikato River at Ongaroto.

At Ongaroto the company built a large timber bridge of locally-sourced totara, designed by TTT Co construction engineer F. Furkett. In later years this timber bridge deteriorated and was condemned, but the company could not afford to replace it immediately because its sawmill had burned down in 1928. In the last few years of service, trains arriving at the bridge would stop and the passengers and fireman would walk across while the driver gently opened the throttle and then jumped off. The train would slowly ease across the bridge before being stopped on the other side by the fireman, where everyone would reboard the train. This bridge was replaced in 1931 by a steel truss bridge with a central pier.

In general the TTT Co line was constructed to a fairly high standard for a bush tramway, with 1 in 30 grades and 30 metre radius curves. This reflected the company's ultimate intention to sell the line to NZR.

In 1911 the TTT Co put forward a proposal to extend their line from Mokai into Taupo township via Oruanui. The station, and terminus of the line, was to be on Spa Road where Taupo-Nui-a-Tia College now stands. This would have required another bridge across the Waikato River.

The proposal was quickly endorsed and praised by many in Taupo, and to support the extension the Taupo District Railway League was formed with powers to support the scheme and ensure it succeeded. The TTT Co proposed running the railway as a private trust-owned company.

Considerable objection was made by the people of Rotorua, in particular the Rotorua Chamber of Commerce. They believed that the railway should be from the railhead at Rotorua, running south to Taupo via Waiotapu and Wairakei. The Rotorua Chamber of Commerce lodged a complaint to Parliament regarding the proposal. The Taupo District Railway League consequently lodged a complaint to the Member of Parliament for the district, Mr MacDonald, protesting the opposition being made by the Rotorua Chamber of Commerce.

As time passed the proposal for the TTT Co scheme was eventually shelved, largely due to the outbreak of World War I and due to the considerable objections being made by the Rotorua Chamber of Commerce. The line would have required considerable improvements to bring it up to NZR standard as it was only built to carry timber and it consequently had very tight curves, narrow cuttings and light rails. It was not a fast railway line at all and the passengers that the TTT Co trains carried were noted to be able to climb off the train and walk alongside the train as it slowly crawled along.

The TTT Co line eventually closed on 26 October 1944. However the Government saw that the line had greater potential and in September 1946 acquired the first 29 km between Putaruru and Kinleith. This section of line opened again on 9 June 1947 under the control of the Public Works Department using steam locomotives purchased from the TTT Co.

Around the same time plans were being made for a large pulp and paper mill to be constructed at Kinleith. The line with its sharp curves, steep grades and light rails, needed to be significantly upgraded to enable heavy traffic. Reconstruction of the line began in 1949, reducing grades from 1 in 44 to 1 in 70 and curves from 201 metre radius to 322 metre radius. The rebuilt line was handed over to NZR on 12 June 1950.

Around this time there was a proposal to rebuild the line and extend it to Taupo. Nothing further was heard of this proposal after the 1949 election. This proposal has been brought up many times since.

[edit] Rotorua - Taupo line

Proposals to link Taupo with Rotorua and the greater Bay of Plenty with a railway date back to 1911. It had long been intended that the Rotorua Branch would be extended into the Bay of Plenty to connect with the line being built from Gisborne. A railway into the Bay of Plenty would link Rotorua and surrounding regions to the Port of Tauranga. Rotorua interests at the time were consequently lobbying very hard to have a line built between Rotorua and the Bay of Plenty, claiming the considerable amounts of land which would be opened up and linked to the port, particularly if the line were to be extended to Taupo.

When the TTT Co announced a proposal in 1911 to extend its line running from Putaruru to Mokai into Taupo, this caused much upset in Rotorua, as it weakened Rotorua's case to have a line built to link Rotorua with the Port of Tauranga. The Rotorua Chamber of Commence consequently voiced strong opposition to the TTT Co proposal, and said that "any railway connection to Taupo should be from the Government railway at Rotorua".

The Government however was more focused on completing the East Coast Main Trunk Railway linking Tauranga and Gisborne, and would not consider linking Rotorua to the Bay of Plenty until that line was completed. The outbreak of World War I temporarily put a stop to the Rotorua proposal but once the war was over, enthusiasm for a line to link Rotorua and Taupo with the Port of Tauranga was renewed.

Much lobbying continued by Rotorua interests and support for the Rotorua - Taupo line was by 1928 very strong and it supporters, the settlers living between Taupo and Rotorua, formed the Rotorua Taupo Railway League lead by E. Earl Vaile, to gain support for the line. A finding by the Taupo Tramways Lands and Timber Royal Commission brought forward a unanimous finding "There is urgent necessity in order to avoid great national waste, for an extension of the Rotorua Government Railway to Waiotapu with as little delay as possible".

[edit] Cabinet approval

In July 1928 the Cabinet approved the construction of the Rotorua - Taupo railway. The line was to be constructed initially as far as Waiotapu, and then onwards to Taupo via Reporoa and Wairakei. Work began almost immediately with teams of construction workers transferred from the Taneatua – Opotiki line, which had been stopped. It had been hoped though in Rotorua, that work on the line may have given to Rotorua people as unemployment was very high in the town. Work on the line started almost immediately and for approximately one year from the date of approval by cabinet, men worked on constructing embankments and cuttings along the proposed route a short distance out of Rotorua between Waipa and Waiotapu.

However in 1929 as a result of the depression and a downturn in economic activity, cabinet announced that work on the Rotorua - Taupo railway would cease as soon as jobs could be found in other parts of the country for the men working on this scheme. This was a real blow to those that supported the railway and did not help Rotorua at a time when unemployment was very high. There was much vocal opposition in Rotorua at the line being stopped and calls for the work to be resumed. The work did not resume and the formation and cuttings were abandoned. Some of this work can still be seen between Rotorua and Taupo along State Highway 5, on the western side of the road, a short distance out of Rotorua.

From 1929 onwards there were various calls for the railway between Rotorua and Taupo to be restarted but nothing of any great significance until 1968 when NZR announced a proposal to construct a new line to Rotorua from Paengaroa on the East Coast Main Trunk, with an extension to the Waipa State Mill. An extension to Taupo was also seen by NZR "as being very attractive".

The proposal created much attention both in support and against the idea. NZR wanted a better link into the Rotorua region to tap into and serve the central North Island pine forests with the Port of Tauranga and a line with easier grades than the steep line over the Mamaku ranges.

The route of the proposed new line and in particular, the proposed siting of new marshaling yards at Rotorua was the reason for much of the objections. NZR wanted to extend the existing Rotorua branch line from the central city station, across Fenton Street to Ngapuna where they proposed having a large marshaling yard, along with a spur line running south to the Waipa State Mill. Many people in Rotorua objected to having a railway crossing Fenton Street and wanted the railway marshaling yards located at Waipa instead of Ngapuna. NZR objected to shifting the marshaling yards, as it would significantly increase the cost of the project.

However an equally great number of people in Rotorua supported the railway proposal and consequently it became a hot political debate. By 1973 NZR started to back down on the proposal and stated that the scheme would only proceed if the people of Rotorua agreed upon where the marshaling yards would be located. This of course was never likely to occur and consequently the scheme fell though shortly after. This was the last time serious consideration was given for a railway to Taupo from Rotorua.

In 1989 the central city station and railway yard at Rotorua closed, and along with the last 2 km of the line, were lifted and relocated to Koutu.

[edit] Kakahi - Pukawa line

A proposal to construct a railway between Kakahi on the North Island Main Trunk and Pukawa on the shores of Lake Taupo, near Tokaanu, was made by a group of three people - Te Heuheu Tukino, Paramount chief of the Ngati Tuwharetoa iwi (tribe); Lawrence Grace, who was closely related through marriage to the tribe; and Tudor Atkinson, the founder of the TTT Co.

The three set up a company called the Tongariro Timber Company Limited with the intention to construct the railway and to have branch lines heading into the bush at various points along the route to harvest the native timber along the way. The railway was intended to be paid for using some of the large sums of money expected to be earned from the timber to be harvested. It was agreed that the land would remain in Maori ownership and that the Tongariro Timber Company Limited would operate the railway. Once the railway was built the company would carry freight other than timber, such as dressed flax and grain, and passengers at Government rates. The railway would connect with a ferry service on Lake Taupo.

In January 1908 an Order in Council was made allowing the Maori owners to sell land for the construction of the railway. Work began immediately on surveying the proposed railway line. Tudor Atkinson tried locally to raise the necessary capital to build the railway. His efforts proved unsuccessful, and in 1916 he went to London where he formed a separate company to finance the railway. However World War I intervened and the company ended up being dissolved with all money being returned to the prospective shareholders.

In 1913 the Egmont Box Company Limited arrived at Kakahi in search of white pine (Kahikatea) for constructing boxes for dairy products. The company found suitable quantities of white pine on land next to which the Tongariro Timber Company held cutting rights to. The company obtained the cutting rights to this land, however it was found that the Egmont Box Company would need to construct a light railway to haul the logs out on. With the Tongariro Timber Company already having plans to build such a railway, it was proposed that the railway be constructed jointly by the two companies.

It was agreed that the Egmont Box Company would construct the railway as far as the land that they were to harvest logs from, and then the Tongariro Timber Company would construct the rest of the line to Pukawa. Work started immediately and soon various cuttings, bridging, and track had been laid. However with World War I by now claiming many of the necessary fit and able men needed to do the job, work began to slow and it was becoming increasingly difficult to obtain materials.

In 1916 progress was further hindered with the New Zealand Government Railways (NZR) changing its mind on how the line was to connect with their line at Kakahi station. This meant that the Egmont Box Company would need to spend a very large amount of money to change the route to that now required to join up with the NZR line at Kakahi. This was money the company did not have and nor did the Tongariro Timber Company. Tudor Atkinson tried very hard to obtain the necessary capital but from this time onwards it was to be the end of the scheme as far as the Tongariro Timber Company and Egmont Box Company were concerned.

Other parties tried to carry out and construct the railway, but all failed to do so with either not being able to obtain the necessary capital or the economic viability of the scheme prevented them making any progress. One group in the 1920’s however did raise the necessary capital and gained the support from the Maori landowners but not the Government. Consequently this lack of support from the Government was why their scheme did not eventuate.

The forest between Kakahi and Lake Taupo remained standing until after World War II when it was felled. By then the railway proposal had given way to road transport. Today all that can be seen of this scheme is the rail formation and large cutting built from Kakahi to the Whakapapa River.

[edit] Murupara Branch line

Since 1983 there have been proposals to extend the Murupara Branch line to Taupo. The principal reason for extending this line has been to tap into the plantation pine forests in the central North Island and in particular those in the Taupo region.

[edit] 1983 proposal

In 1983 a study by town and country planners of the Ministry of Works found that if a railway were to constructed into the Taupo region, it would be very beneficial in transporting logs and sawn timber out of the region to the Pulp and Paper Mill at Kawerau and for export through the Port of Tauranga. It was also found that such a line would break even with revenue made from it covering the costs of constructing it.

The line was to be constructed from the present railhead at Murupara, across the Kaingaroa plains where it would sweep around the southern flank of Mt Tauhara in an arc like shape and then head north towards the Taupo industrial area before sweeping around in another arc in the Broadlands Road area and terminating at the Taupo Mill on Centennial Drive. It was also suggested that there be a second stage to construct a line from the first stage line, near the State Highway 5 Napier - Taupo road through to Rangipo, so as to tap into forests in the Turangi area.

[edit] 1985 proposal

In 1985 Deputy General Manager of the New Zealand Railways Corporation, Bob Henare, stated that the proposed line would be a "no frills" style of railway with sharper curves and steeper grades so as to keep costs down. The line was to be a forestry style railway similar to the Murupara Branch, with its key role being to transport timber. Predicted increases in the number of logging trucks on public roads would also become a major problem when logging commenced in the region. He also said that the line would need to be constructed quickly as the rapidly maturing forests would not wait while people argued over whether or not to build the line. It was also intended for the line to be electrified from Taupo through to Mt Maunganui, once men who were at the time working on the electrification of the North Island Main Trunk, could be transferred on completion of the project.

The 1985 proposal did eventuate, but proposals to have the line extended to Taupo have been raised since that time, the last being in 1998.

[edit] 1998 proposal

In 1998 the findings of a study by consultants Woodward-Clyde for Environment Bay of Plenty, Environment Waikato, the Taupo District Council and Tranz Rail Limited were published to evaluate the various proposals to deal with transporting forestry products out of the Taupo region. The report stated that railheads could be accessed at Waiouru, National Park, Kinleith, and Murupara. The report said that it would be unlikely that rail connections would be made at National Park or Waiouru as the distance to forestry ports and processing plants would increase. A connection from Kinleith was a possibility but it would need to traverse difficult terrain and two crossings of the Waikato River may be needed. The report recommended an extension of the Murupara Branch line as being the best rail option.

The route recommended was similar to the 1985 proposal. The line would have traveled across the Kaingaroa Plains and followed the route more or less presently taken by the private forestry road, High Level Road. Stage one of the proposal would terminate at the junction between the two private forestry roads, High Level Road and the Off-Highway road leading from the Taupo Mill, near the State Highway 5 Napier - Taupo road. A recommendation was made that a log-processing yard be built at the junction of these two roads in conjunction with the rail line extension from Murupara.

The second stage of the proposal was to extend the line into the Taupo industrial area. The line would extend from the proposed log-processing yard around the southern flank of Mt Tauhara and head north towards Broadlands Road before completing a horseshoe like curve into the Taupo Mill on Centennial Drive. The report said the line would be used for transporting sawn timber from the processing yard to the mill on Centennial Drive. Forest industry people did not express an interest in this option, as they did not believe it would bring any new opportunities to them.

The report concluded in respect to the rail options that Tranz Rail and Fletcher Challenge Forests would need to check the opportunities in extending a line south from the Murupara railhead.

A roading option was consequently chosen and the rail proposal did not eventuate.

[edit] External link

[edit] Bibliography

  • Don Stafford Collection – Railways, Rotorua Public Library, Rotorua
  • The Era of the Bush Tram in New Zealand, Paul Mahoney, IPL Books, Wellington, 1998
  • Guide to New Zealand Rail Heritage, John Garner, IPL Books, Wellington, 1996
  • The New Century in Rotorua, D M Stafford/Rotorua District Council, Ray Richards Publisher, Auckland, 1988
  • New Zealand Historical Atlas, David Bateman Limited, Auckland, 1997
  • Mokai, Ida Davis and Ruth Forshaw, 175 Taharepa Road, Taupo, 1990
  • Rails magazine, November 1985, March 1994, November 1998, Southern Press Limited, Porirua
  • Rails over the Mamakus, R.Brett Green, Albion Press Limited, New Lynn, 1988
  • Rotorua Taupo Railway League Campaign Pamphlet, Rotorua Taupo Railway League, 1928
  • Tales of early Taupo, H M Fletcher, Times Commercial Printers, Hamilton, 1980
  • Archives New Zealand
  • Land Information New Zealand
  • New Zealand Railways Corporation
  • The Putaruru Timber Museum Society
  • Rotorua District Council
  • Taupo District Council
  • Taupo Museum
  • Taupo Times