I removed the following example as it is a work breakdown structure (WBS) and not a PBS.
WBS of a baking a cake:
- Gather recipy
- Gather ingredients
- Mix ingredient
- Gather tools
- Mix
- Put it in a
- Bake Cake
- Gather ingredients
Everything in the example above is about activities in baking a cake. An example of PBS of a cake:
- Cake
- Icing
- List of ingredients...
- Sponge base
- List of ingredients...
- Cake box
- Icing
Rellis1067 10:21, 4 September 2005 (UTC)
A product breakdown structure has a far wider application then just defining a project deliverable.
It is used in (for example) systems engineering in conjunction with a functional breakdown, your off-the-shelf car maintenance manual to illustrate the bits that make up the engine and where they fit into higher-level assemblies (an illustrated parts breakdown IPB), and MIL-STD-13882B compliant databases for military logistics support.
And I'm not sure how the reference to Prince2 adds to the definition of product breakdown structure.
ALH