Precedence Diagram Method

From Wikipedia, the free encyclopedia

The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.

  • Critical Tasks, noncritical tasks, and slack time
  • Shows the relationship of the tasks to each other
  • Allows for what-if, worst-case, best-case and most likely scenario

Key elements include determining predecessors and defining attributes such as

  • early start date
  • last-last
  • early finish date
  • late finish date
  • Duration
  • WBS reference