S88, shorthand for ANSI/ISA-88, is a standard addressing batch process control. It is a design philosophy for software, equipment, and procedures. It was approved by the ISA in 1995. It was adopted by the IEC in 1997 as IEC 61512-1.
The current parts of the S88 standard include:
- ANSI/ISA-88.01-1995 Batch Control Part 1: Models and terminology
- ANSI/ISA-88.00.02-2001 Batch Control Part 2: Data structures and guidelines for languages
- ANSI/ISA-88.00.03-2003 Batch Control Part 3: General and site recipe models and representation
- ANSI/ISA-88.00.04-2006 Batch Control Part 4: Batch Production Records
S88 provides a consistent set of standards and terminology for batch control and defines the physical model, procedures, and recipes. The standard sought to address the following problems: lack of a universal model for batch control, difficulty in communicating user requirement, integration among batch automation suppliers, difficulty in batch control configuration.
The standard defines a process model which consists of a process which consists of an ordered set of process stages which consists of an ordered set of process operations which consists of an ordered set of process actions.
The physical model begins with the enterprise which must contain a site which may contain areas which may contain process cells which must contain a unit which may contain equipment modules which may contain control modules. Some of these levels may be excluded, but not the Unit.
The procedural control model consists of recipe procedures which consist of an ordered set of unit procedures which consists of an ordered set of operations which consist of an ordered set of phases. Some of these levels may be excluded.
Recipes can have the following types: general, site, master, control. The contents of the recipe include: header, formula, equipment requirements, procedure, and other information required to make the recipe.