Dependency (project management)

From Wikipedia, the free encyclopedia

In a project network, a dependency is a link amongst a project's terminal elements.

There are four kinds of dependencies with respect to ordering terminal elements (in order of decreasing frequency of use):

  1. Finish to start (FS)
    • A FS B = B doesn't start before A is finished
    • image:Dependency-FS.png
    • (Foundations dug) FS (Concrete poured)
  2. Finish to finish (FF)
    • A FF B = B doesn't finish before A is finished
    • image:Dependency-FF.png
    • (Last chapter written) FF (Entire book written)
  3. Start to start (SS).
    • A SS B = B doesn't start before A starts
    • image:Dependency-SS.png
    • (Project work started) SS (Project management activities started)
  4. Start to finish (SF)
    • A SF B = B doesn't finish before A starts
    • image:Dependency-SF.png
    • (New shift started) SF (Previous shift finished)

There are three kinds of dependencies with respect to the reason for the existence of dependency:

  1. Causal (logical)
    • It is impossible to edit a text before it is written
    • It is illogical to pour concrete before you dig the foundations
  2. Resource constraints
    • It is logically possible to paint four walls in a room simultaneously but there is only one painter
  3. Discretionary (preferential)
    • I want to paint the living room before painting the dining room, although I could do it the other way round, too

Traditional critical path-derived schedules are based only on causal (logical) dependencies. The critical chain method necessitates taking into account resource constraint-derived dependencies as well.

Time related information can be used in conjunction with any of the relationships for any of the reasons outlined above. This is known as a lead or lag. For example: When building two walls from a novel material, one might start the second wall 2 days after the first so that the second team can learn from the first.

It is also useful to use lead/lag when tasks are in parallel in a Finish-Finish relationship. For example: The document for 'Activity A' should finish 5 days before the document for 'Activity B' so that the reviewers have time to read each individually. Although Document A and Document B may take different times to write, they will be planned to finish 5 days apart.

[edit] See also

Languages