Talk:Budgeted cost of work scheduled

From Wikipedia, the free encyclopedia

This article is within the scope of the Business and Economics WikiProject.
Stub rated as Stub-Class on the assessment scale
??? This article has not yet received an importance rating on the assessment scale.

What will happen if the there is a schedule slippage. Suppose that a task "test hardware" worth $1000 supposed to be completed in 1 month but is only 75% complete in 1.5 months. What is the planned value for this at the end of 1.5 months?

[edit] January 18, 2008 cleanup

I tried cleaning this article up a little. I'm not really happy with how it reads, but I think it's better than it was before.

I think it would be good to have BCWS, BCWP, and ACWP all point to this one page, and all be defined here. Anyone have an idea how to do that? Shanemcd (talk) 21:04, 18 January 2008 (UTC)