Overnight cost
From Wikipedia, the free encyclopedia
Overnight cost is the cost of a construction project if no interest was incurred during construction, as if the project was completed "overnight." An alternate definition is: the present value cost that would have to be paid as a lump sum up front to completely pay for a construction project.
The overnight cost is frequently used when describing power plants. The unit of measure typically used when citing the overnight cost of a power plant is $/kW. For example, the overnight cost of a nuclear plant might be $1500/kW, so a 1000MW plant would cost $1.5 billion.