Earliest deadline first scheduling
From Wikipedia, the free encyclopedia
Earliest deadline first (EDF) scheduling is a dynamic scheduling principle used in real-time operating systems. It places processes in a priority queue. Whenever a scheduling event occurs (task finishes, new task released, etc.) the queue will be searched for the process closest to its deadline. This process will then be scheduled for execution next.
EDF is a optimal scheduling algorithm on preemptive uniprocessors, in the following sense: if a collection of independent jobs, each characterized by an arrival time, an execution requirement, and a deadline, can be scheduled (by any algorithm) such that all the jobs complete by their deadlines, the EDF will schedule this collection of jobs such that they all complete by their deadlines.
With scheduling periodic processes that have deadlines equal to their periods, EDF has a utilization bound of 100%. That is, EDF can guarantee that all deadlines are met provided that the total CPU utilization is not more than 100%. So, compared to fixed priority scheduling techniques like rate-monotonic scheduling, EDF can guarantee all the deadlines in the system at higher loading.
However, when the system is overloaded, the set of processes that will miss deadlines is largely unpredictable (it will be a function of the exact deadlines and time at which the overload occurs.) This is a considerable disadvantage to a real time systems designer. The algorithm is also difficult to implement in hardware and there is a tricky issue of representing deadlines in different ranges (deadlines must be rounded to finite amounts, typically a few bytes at most). Therefore EDF is not commonly found in industrial real-time computer systems.
There is a significant body of research dealing with EDF scheduling in real-time computing; it is possible to calculate worst case response times of processes in EDF, to deal with other types of processes than periodic processes and to use servers to regulate overloads.
[edit] Example
Consider 3 periodic processes scheduled using EDF, the following acceptance test shows that all deadlines will be met.
Process | Execution Time | Period |
---|---|---|
P1 | 1 | 8 |
P2 | 2 | 5 |
P3 | 4 | 10 |
The utilization will be:
The theoretical limit for any number of processes is 100% and so the system is schedulable.