Fort Peck Dam

From Wikipedia, the free encyclopedia

Fort Peck Dam
Enlarge
Fort Peck Dam

The Fort Peck Dam is the highest of six major dams along the Missouri River, located in northeast Montana in the United States. At 21,206 feet (6,464 m) in length and over 250 feet (75 m) in height, it is the largest hydraulically filled dam in the United States, and creates Fort Peck Lake, the fifth largest man-make lake in the U.S. It currently lies within the Charles M. Russell National Wildlife Refuge; the dam and 134-mile (216 km) long lake exist for the purposes of hydroelectric power generation, flood control, and water quality management.

Originally authorized by U.S. President Franklin D. Roosevelt in 1933, construction on the Fort Peck Dam employed over 11,000 workers at its peak in 1939. The dam, named for a 19th-century trading post, was completed in 1940, and began generating electricity in July 1943. The site is located near Glasgow, Montana, and the community of Fort Peck, Montana originally developed as a boomtown during the dam's construction. The dam presently has a power-generating capacity of 185,250 kilowatts.

Fort Peck Dam is probably best known for being the subject of a photograph taken by Margaret Bourke-White while still under construction that was the cover photo of the first issue of Life magazine on November 23, 1936.

The dam is also center-stage in Bucking the Sun, by the Montana-born writer Ivan Doig, published in 1996. The novel tells the story of the fictional Duff family and their various roles in the mammoth dam project, and in the process describes the working conditions and way of life of the thousands of workers hired to construct the Fort Peck Dam, many of them homesteaders from upriver farms destined to disappear under the waters of the newly formed Fort Peck Lake.

[edit] Dam failure

The site chosen was on a stretch of the Missouri River flowing from south to north. The river bed at the site consisted of approximately 160 feet (49 meters) of alluvial deposits, varying from coarse, pervious sands and gravels to impermeable clays. Beneath these deposits lay a thick (approximately 1000 ft (305 m)) deposit of Bear Paw shale. This shale is classified as a firm shale and contains thin (<1 to 6 inch (<2.5 to 15.2 cm)) layers of bentonite. The topmost layer of soft clay was removed from the alluvium in order to found the dam on the stable sandy deposits beneath, at an elevation of approximately 2050 feet (625 m). The remaining deposits consisted of the alluvial materials mentioned above. These deposits had many interconnecting layers of coarse sands and gravels, necessitating the installation of a steel sheet pile wall down to the firm shale, from the left to the right abutment.

The dam was planned to extend to an elevation of 2275 ft (694 m), for a total height of 225 ft (69 m) from the cleared river bed and had a length from the left to the right abutment of approximately 10,500 ft (3200 m). The upstream face was designed with an average slope of one vertical on four horizontal and included three horizontal shelves built into the slope. A flatter (1 on 7.5) berm was to be placed between stations 30+00 and 75+00 (approximately the center half of the length of the dam).

Since the construction method of hydraulic fill was chosen, four electric dredges needed to be built. Due to the distance of the site from the nearest shoreline, a shipyard was started on the site, affectionately dubbed “The Fort Peck Navy” and “The Biggest Shipyard in Montana” by the workers. These dredges would pump material from nearby borrow pits to the dam site where it was discharged by pipes along the outside edges of the fill. The coarser material settled out quickly, while the fines were carried downhill toward what would eventually become the core of the dam. Samples were take from all zones regularly to ensure that the material had the gradation and consolidation characteristics specified by the design.

This process proceeded until elevation of the fill reached approximately 2250 ft (686 m) (200 feet (61 m) above the foundation), while the reservoir was at an elevation of 2117.5 feet (645.6 m). At this point, the danger of the core pool overtopping or bursting the shell became greater because the beaches became narrower. For this reason, an extensive alarm system was implemented along the narrower upstream shell. This alarm system could immediately shut off the dredge pumps if a shell breach was detected. Part of this alarm system involved monitoring the elevations of the core pool and the pipelines carrying the dredged fill.

On the morning of September 22, 1938, an inspection by the engineer in charge of construction revealed that the elevation of the pipeline relative to the core pool near station 15+10 (see attached overhead photo) was only 2.5 ft (0.76 m) when it should have been 4.5 ft (1.4 m). A survey crew was dispatched immediately to determine if the fill on which the pipeline was founded was settling or if the pipeline footing itself was settling. Preliminary measurement showed that the pipeline was closer to the pool than expected from station 15+00 to station 17+00. A meeting with the district engineer and supervisory personnel was scheduled for 1:15 p.m. near the location in question.

At approximately 1:15 p.m. the core pool near station 15+00 began to settle slowly. As its rate of settlement increased, cracks appeared 30 feet (9.1 m) below the crest in the upstream embankment. As the settlement of the pool got larger, portions of the shell began to slide backwards into the core pool area and the majority of the upstream shell began to move into the reservoir, translating south and rotating slightly about the east abutment (see attached arial photograph). The west end of the slide mass broke away from the dam near station 27+00 and the core pool water rapidly poured out of the breach that was created in the shell. Portions of the core in the still-stable portion of the dam continued to slump into the hole created by the loss of the slide mass. One construction supervisor was backing his car away from the advancing scarp to the west along the beach to avoid the slumping and noted that the small scarp in the core was advancing to the west at a speed equal to his own (approximately 10 mph (16 km/h)).

A pump barge moored near the dam at the east abutment was swamped by the slide and was lost along with several tractors, loadmasters, and draglines on the slope. Of the 134 men working in the area at the time, 34 were carried into the sliding material. Of these 34, eight were unable to be rescued and lost their lives.

In the testing and analysis done by the Corps of Engineers and others to determine the cause of the slide, several modes of failure were considered. These were: movement along a weak zone in the shale in the abutment, movement along the shale surface, bursting of the shell due to excessive core pressure, and temporary liquefaction of the shell or foundation sand. Extensive laboratory tesing of the shale, both weathered and unweathered indicated strengths leading to a factor of safety greater than one. Also, portions of the weathered shale were found in the slide mass, indicating that the slip surface was located somewhere in the shale, but probably at a shallow depth. The core material turned out to be much stronger than expected (having a friction angle of approximately 29 degrees) and was carried out into the slide nearly in a solid mass, making it unlikely that the core was the weak point in the slide. Laboratory testing was done on the shell material and the foundation sand and it was determined that both materials were denser than the critical state for liquefaction. There was no evidence of ground vibration, seismic or otherwise. Some liquefaction may have occurred after the sliding was initiated, but it was unlikely that it caused the slide.

The major weak point in the dam seemed to be the bentonite seams in the Bear Paw shale. Very high water pressures were reported at some points in the shale during the construction. This was likely caused by consolidation due to the overburden of the fill being placed for the dam. The excess pore pressures could not be relieved due to the low permeability of the surrounding shale. This resulted in a low effective stress in the bentonite and a very low shear strength.

[edit] References

  • Middlebrooks, T. A. (1942), “Fort Peck Slide,” Transactions of the American Society of Civil Engineers, 107, 723-764
  • “Report on the Slide of a Protion of the Upstream Face of the Fort Peck Dam” (1939), Corps of Engineers, US Army.